October 17, 2025
Henry Kouyoumdjian, Engineer II
Water Resources Division
City of Bakersfield – Water Department
1000 Buena Vista Road
Bakersfield, CA 93311
RE: Request for Qualifications – Consulting Services for PFAS Treatment Program (26WDWR03) Mr . Kouyoumdjian:
Provost & Pritchard Consulting Group (Provost & Pritchard) appreciates the opportunity to interview and submit a fee proposal for this important project. In accordance with the instructions contained in the Request for Fee Proposal and Interview, we have enclosed:
• a proposed fee and summary of estimated hours to complete the project work broken out by task and labor category, • a detailed scope of work,
• a schedule of hourly billing rates, and
• a project schedule.
Provost & Pritchard is committed to providing the City with outstanding professional services at a reasonable fee. We are happy to work with the City to refine the assumptions made in our scope of work and corresponding fee proposal. Should you have any questions, please contact Jeane Hill, PE at (661) 616-5900 and [email protected].
Respectfully,
Jeane Hill, PE Kevin Berryhill, PE
Project Manager Principal-in-Charge
Engineering • Surveying • Structural • Geostructural • Planning • Environmental • GIS • Construction Services • Hydrogeology • Consulting Clovis • Bakersfield • Visalia • Modesto • Los Banos • Chico • Sacramento • Sonora • San Luis Obispo • Riverside • Camarillo • Boise, Idaho 1518 Mill Rock Way, Suite 100 • Bakersfield, CA 93311 • (661) 616-5900 www.provostandpritchard.com
1518 Mill Rock Way, Suite 100 Bakersfield, CA 93311 (661) 616-5900 www.provostandpritchard.com
Scope of Services
Our proposed scope of work for this proposal is segregated into several phases, described below.
Design Phase
A. Project Management and Administration
1. Project management and administration (8 months)
2. Internal meetings
3. City monthly meetings (8 months)
4. Prepare and maintain project schedule
5. Prepare and submit monthly billing
6. City kickoff meeting
7. Site Visits
8. Conduct topographic survey and prepare base map (2 sites)
9. On-site underground utility exhibits for City/Cal Water (CWS) confirmation B. Permitting and Land Acquisitions Assistance
1. Coordinate with the State Water Resources Control Board – Division of Drinking Water (DDW) regarding the project.
2. Assist Cal Water by providing treatment process data needed to complete the DDW permitting process.
3. Land Acquisition Support
C. Pre-Design Technical Memorandum
1. Water Quality Assessment
o Review all available raw water quality data including PFAS, TCP, nitrate, TOC, H 2S, iron, and manganese
o Review GAC treatment records for wells with existing GAC treatment (change-out- dates, carbon type, throughput volumes, etc.) and recommend additional PFAS testing at GAC treatment plants as necessary to characterize existing PFAS removal performance.
o Define the City’s treatment objectives (non-detect vs. MCL compliance) taking into consideration evolving regulations.
2. Assessment of Existing GAC Treatment
o Review PFAS and TCP levels at various points in the treatment process o Provide subjective assessment of the cost effectiveness and reliability of the existing GAC systems compared to what can be expected from expanded GAC systems.
3. Identify the preferred treatment vessel sizing, configuration and location for each site.
4. Identify the proposed discharge location for fluidization water and determine whether further coordination with internal City departments or outside agencies is required.
5. Assessment of Well Production Impacts
o Perform hydraulic calculations of head loss through the proposed treatment systems o Estimate the change in well flow rate resulting from the new head losses
6. Establish Basis of Design
o Meet with City and CWS to discuss the desired treatment plant features and any ancillary improvements that may be desired at the sites (e.g. access platforms, sacrificial bed nozzles, process instrumentation, VFDs, water lubrication conversions, etc).
7. Prepare and submit pre-design technical memorandum
D. Draft Schematic (30%) Design
1. Pre-design technical memorandum review meeting with City and CWS
2. Prepare (30%) plans for wellhead treatment construction project, including the following sheets:
o Design Criteria (6 sheets)
o Process Flow Diagram (6 sheets)
o Hydraulic Profile (6 sheets)
o Site Plan (6 sheets)
3. Prepare list of technical specifications and complete draft GAC system specification in CSI format
4. Submit draft (30%) plans and specifications
5. 30% submittal review meeting with City and CWS
E. Preliminary (60%) Design
1. Address 30% review comments
2. Geotechnical investigations and reports for CBK-09 and CBK-31; geotechnical report updates for CBK-08, CBK-26, CBK-33, and CBK-43
3. Prepare draft final plans, including the same sheets listed in the previous phase o Cover and Sheet Index (1 sheet)
o General notes (2 sheets)
o Legend and abbreviations (1 sheet)
o Design Criteria and Process Flow Diagram (6 sheets)
o Horizontal Control plan (6 sheets)
o Demolition plan (6 sheets)
o Coordinate Plan (6 sheets)
o Site plan (6 sheets)
o Grading plan (6 sheets)
o Piping plan (6 sheets)
o Backwash Disposal Piping Plan and Profile (2 sheets)
o Piping sections (6 sheets)
o Details (6 sheets)
o Electrical sheets prepared by electrical engineering subconsultant
4. Prepare preliminary technical specifications
5. Submit preliminary plans and specifications
6. 60% submittal review meeting with City and CWS
F. Draft Final (90%) Design
1. Address 60% review comments
2. Prepare draft final plans, including the same sheets listed in the previous phase
3. Prepare draft final technical specifications
4. Incorporate City boilerplate bid and contract documents
5. Prepare draft final cost opinions
6. Submit draft final plans, specifications and estimate
7. 90% submittal review meeting with City and CWS
G. Final Bid Set (100%) Plans, Specifications, and Estimates
1. Address draft (90%) review comments
2. Prepare final plans
3. Prepare final technical specifications with final City boilerplate
4. Prepare final opinion of probable construction costs
5. Prepare preliminary bidding and construction phase schedule
6. Submit final plans, specifications, estimate, and preliminary schedule
7. Submit 1 bid-ready documents package
Deliverables:
1. Pre-Design Technical Memorandum (electronic pdf format)
2. 30% Draft Design Submittal: plans and specifications (electronic pdf) and DDW amendment documents (as required)
3. 60% Draft Design Submittal: plans, specifications, and City boilerplate (electronic pdf) and DDW amendment documents (as required)
4. 90% Draft Design Submittal: plans, specifications, City boilerplate and estimate (electronic pdf)
5. Final Bid Package (100%): plans, specifications, Bid documents, estimates, and preliminary schedule (hard copy and electronic pdf and CAD)
Assumptions:
1. Improvements at the six Phase-1 wells will be consolidated into a single set of construction documents.
2. Water production data and well pump information provided by the City will be used to evaluate the treatment sizing.
3. The City will provide a copy of the record drawings and on-site pipeline locations.
4. The City will provide pertinent GAC operational data to allow evaluation of their existing treatment systems.
5. Collection and analysis of water quality samples that may be recommended as part of the Pre- Design Memorandum will be arranged and paid for by the City.
6. The recommendations from the geotechnical investigation reports prepared during the TCP Mitigation Project for CBK-2/8, CBK-26, CBK-33, and CBK-43 will be updated for this project.
No investigations will be required at these sites.
7. The City will prepare the California Environmental Quality Act documents.
8. Permitting of the new treatment plant, including preparation of an Operations Plan, will be accomplished by CWS. Provost & Pritchard will assist by providing treatment process data.
9. The treatment system will be procured by the general contractor.
10. FWD and other GAC wasted water will be directed to the existing standpipes at CBK-2/8, CBK- 26, CBK-33, and CBK-43, to the adjacent City sump at CBK-9, and to a new storm drain pipeline connection assumed to be adjacent to the treatment plant at CBK-31. No off-site pipelines have been included.
11. Design of a standby generator will not be required.
12. Electrical improvements at the sites will be limited to integration of the flow and pressure instrumentation associated with the new treatment systems. We are assuming that the existing electrical service is adequate for the addition of treatment equipment power and instrumentation.
13. The City’s existing SCADA system has recently been upgraded and it can support the addition of the instrumentation and controls associated with the PFAS treatment plants.
14. Electrical and SCADA design will include schematic layout of conduits only to be installed by selected contractor. CWS will install wiring and complete programming under a separate contract with the City.
15. Evaluation of water treatment process alternatives (e.g. reverse osmosis and ion exchange) is not required.
16. Pilot or bench-scale testing will not be required.
17. The project will be exempt from Site Plan Review by City ordinance.
18. Building permits / plan check will be required only for green tag sign-offs required by PG&E.
19. The City will pay for all permit and service activation fees directly.
20. The City will handle coordination with property owners adjacent to the sites regarding aesthetic impacts and construction activities.
21. Provost & Pritchard CAD standards and title block will be used for the design of this project.
22. Provost & Pritchard’s current CAD version will be used.
23. City boiler plate front-end contract documents will be used.
24. Provost & Pritchard’s technical specifications in CSI format will be used.
Phase BID: Bidding Phase
A. Bidding Services
1. Assist with the preparation of addenda and clarifications as necessary during the bid period (assumed 2 addenda)
Deliverables:
1. Responses to Bidder Pre-Bid Requests for Information
2. Supporting Documents for Addenda (electronic pdf)
Assumptions:
1. The improvements at the six Phase-1 wells will be bid as a single construction project.
2. The City will advertise and facilitate the bidding process.
3. The City will prepare, compile, and distribute addenda to bidders.
Phase CON: Construction Phase
A. Construction Phase Services
1. Attend pre-construction meeting
2. Review contractor submittals (assumed 100 submittals inclusive of resubmittals)
3. Make periodic site visits while construction is active to observe the progress of work, . A total of six (6) construction administration site visits are included in the scope of services.
4. Assist in response to RFIs (assumed 12 RFI responses)
5. Site visit for substantial completion and a final walk-through; prepare list of items for City- prepared punchlist.
6. Review the contractor’s completion documents. Prepare record drawings based on “as-built” information furnished by the Contractor and City. Provide one copy of reproducible record drawings to City for permanent records.
Deliverables:
1. Submittal review letters (electronic pdf)
2. RFI responses (electronic pdf)
3. Record drawings (electronic pdf)
Assumptions:
1. Submittals for the six Phase-1 wells will be common.
2. The City will conduct preconstruction meeting, progress meetings, prepare contract change orders, review contractor progress pay estimates, provide daily observation during construction, and prepare and maintain punchlist.
3. The City will contract directly and coordinate with the soil and materials testing laboratory during construction.
Additional Services
The following services are not included in this proposal, however these and others can be provided at additional cost, upon request.
Additional office or field services required due to any governmental agency changes in ordinances, codes, policies, procedures or requirements after the date of this agreement. Construction staking
Vessel and media pre-procurement documents
Pilot or bench-scale testing
Daily construction observation
CEQA documentation
Preparation of a treatment Operations Plan
Clarifications, adjustments, modifications and other changes due to field and other conditions that change by the time project construction occurs.
The costs of all checking and inspection fees, soils or geotechnical testing fees, and all other fees, permits, bond premiums, applicable taxes on professional services, blueprints and reproductions, and all other similar charges not specifically covered by the terms of this agreement.
Extra work caused by delays beyond Consultant’s reasonable control by reason of strikes, lockouts, work slowdowns or stoppages, accidents, acts of God, failure of Client to furnish timely information or approve or disapprove of Consultant’s services or instruments of service promptly, or faulty performance by Client or other contractors or governmental agencies. Services associated with litigation including responding to subpoenas and providing expert witness services.
Applying for a backwash discharge waiver for Regional Water Quality Control Board General Order R5-2018-0085.
CITY OF BAKERSFIELD WATER DEPARTMENT
PFAS TREATMENT PROGRAM - PHASE 1
FEE ESTIMATE
Task No. Task
Principal
Engineer VII
Principal
Engineer III
Principal
Engineer I
Assistant
Engineer V
Assistant
Engineer II
Assistant
Engineer IV
Senior
Technician
IV
Senior
Structural
Engineer III
Associate
Engineer II
Project
Administrat
or IV
Licensed
Surveyor IV
Assistant
Surveyor I
2 man
survey
Prevail Labor Totals Sub-cons. Fee
Mileage/
Reimb. Costs Total Fee
Hourly Rate: $287 $247 $227 $149 $128 $142 $165 $196 $149 $113 $196 $116 $345 15% 15% 1 Design Phase (assuming designing all in one package)
1.1 Project Management and Administration $0 $0 $0 $0
1.2 Project Management and Administration (8 months) 2 20 6 $5,792 $0 $0 $6,371
1.3 Internal Meetings 2 1 2 1 1 1 1 1 2 1 $2,477 $0 $0 $2,725
1.4 City Monthly Meetings (8 months) - Not in scope $0 $0 $0 $0
1.5 Prepare and maintain design schedule 4 $908 $0 $0 $999
1.6 Prepare and submit monthly billing 8 8 $2,720 $0 $0 $2,992
1.7 City Kickoff Meeting 6 4 $2,630 $505 $193 $3,661
1.8 Site Visits 8 8 $4,112 $3,029 $209 $8,085
1.9 Misc. outside coordination meetings (Parks & Rec, AEWSD, City WW Div) 8 8 $4,112 $0 $0 $4,523
1.10 Topographic Survey 2 4 4 12 24 40 $20,646 $0 $16 $22,728
1.11 Onsite utility confirmation exhibits 1 2 $525 $0 $0 $578
1.12 Permitting & Land Acquisitions Assistance $0 $0 $0 $0
1.13 CEQA (By City) 1 $227 $0 $0 $250
1.14 DDW Ops Plan and Applications (By City and CWS) 1 2 6 $1,635 $0 $0 $1,799
1.15 RWQCB WDR for Discharge to Sump (By City) $0 $0 $0 $0
1.16 City Planning Reviews (Exempt) $0 $0 $0 $0
1.17 Storm water connection (capacity and sump volume calculations) - One site 2 6 $1,348 $0 $0 $1,483
1.18 Sanitary sewer connection (capacity calculations) - No sites $0 $0 $0 $0
1.19 Building Department coordination (By City) $0 $0 $0 $0
1.20 Open Street Permits (for Potholing) - No sites $0 $0 $0 $0
1.21 Open Street Permits (for offsite pipelines) - No sites $0 $0 $0 $0
1.22 Land AcquisitionSupport (assuming 3 sites - 08, 33, & 09 8 24 $4,352 $34,500 $0 $42,737
1.23 Pre-Design Technical Memorandum $0 $0 $0 $0
1.24 Water Quality and Existing Treatment Assessment 16 4 12 $7,288 $0 $0 $8,017 System Sizing Including Alternative Vessel Arrangements 12 6 6 $5,700 $0 $0 $6,270
1.25 Vessel Procurement Approach 2 2 $1,028 $0 $0 $1,131
1.26 Impacts on Source Capacity (assuming new treatment on all 6 sites) 1 2 3 3 $1,572 $0 $0 $1,729
1.27 Fluidization Water Disposal 2 4 $1,482 $0 $0 $1,630
1.28 Coordination with Operators 6 12 $4,446 $0 $0 $4,891
1.29 Permitting and regulatory requirements (DDW coordination) 4 2 $1,602 $0 $0 $1,762
1.30 Site Specific Electrical and Controls Improvements 1 2 1 1 $1,018 $1,515 $0 $2,786
1.31 Site Specific Access, Constructability or Other Concerns 2 4 6 6 $3,144 $0 $0 $3,458
1.32 QC review 3 $741 $0 $0 $815
1.33 Submit Draft Report 4 4 4 $2,508 $0 $0 $2,759
1.34 Submit Final Report 2 4 2 $1,708 $0 $0 $1,879
1.35 30% Design $0 $0 $0 $0
1.36 Send out utility letters 2 6 12 $2,704 $0 $115 $3,101
1.37 Incorporate survey files into base maps (2 sites) 12 6 $2,778 $0 $0 $3,056
1.38 Review record drawings and incorporate into base maps (2 sites) 6 24 6 $5,928 $0 $0 $6,521
1.39 Coordinate with vessel suppliers (includes bringing in CAD blocks) 8 4 8 4 $5,308 $0 $0 $5,839
1.40 30% Drawings 40 80 80 80 48 28 24 $67,940 $0 $0 $74,734
1.41 Structural Calculations 3 24 32 $10,153 $0 $0 $11,168
1.42 QC Review 12 $2,964 $0 $0 $3,260
1.43 Easement plat and legal descriptions (Park Site) 1 4 4 $1,475 $0 $0 $1,623
1.44 30% List of Technical Specifications & complete draft GAC system specification 8 2 2 2 2 2 $3,950 $0 $0 $4,345
1.45 Submit 30% Plans and Specification List 4 4 $2,056 $0 $0 $2,262
1.46 30% Design Review Workshop with City and CWS 8 4 $3,204 $0 $193 $3,737
1.51 60% Design $0 $0 $0 $0
1.52 Geotechnical Investigations and reports (2 sites w/o exist TCP vessels) 4 $908 $23,690 $0 $27,058
1.53 60% Plans 24 12 36 120 120 48 12 12 36 $67,776 $0 $0 $74,554
1.54 Electrical plans and specs 3 6 6 $2,991 $10,097 $0 $14,397
1.55 Landscape plans (park site) and specs (By City Parks & Rec) $0 $0 $0 $0 I:\Marketing\Proposals\2025\City of Bakersfield - PFAS Treatment Program - 25-644\Interview\Fee Package\2025 FeeEstimate.xlsx Page 1 of 2 Task No. Task
Principal
Engineer VII
Principal
Engineer III
Principal
Engineer I
Assistant
Engineer V
Assistant
Engineer II
Assistant
Engineer IV
Senior
Technician
IV
Senior
Structural
Engineer III
Associate
Engineer II
Project
Administrat
or IV
Licensed
Surveyor IV
Assistant
Surveyor I
2 man
survey
Prevail Labor Totals Sub-cons. Fee
Mileage/
Reimb. Costs Total Fee
Hourly Rate: $287 $247 $227 $149 $128 $142 $165 $196 $149 $113 $196 $116 $345 15% 15%
1.56 60% Technical specifications and list of front-ends 12 4 24 12 12 8 $14,840 $0 $0 $16,324
1.57 Submit 60% Plans, Technical Specifications, & list of City boilerplate sections 6 12 $4,446 $0 $0 $4,891
1.58 60% Design Review Workshop with City and CWS 8 4 $3,204 $0 $193 $3,737
1.61 90% Design $0 $0 $0 $0
1.62 Plan updates 16 12 36 80 80 24 8 4 16 $45,784 $0 $0 $50,362
1.63 Electrical plans, specs, and estimate 2 6 6 $2,704 $20,194 $0 $25,188
1.64 Full Specification Book (City boilerplate and Tech Specs) 4 4 16 6 6 8 $8,700 $0 $0 $9,570
1.65 Preliminary Engineer's Estimate of Probable Construction Cost (EEOPCC) 6 2 6 16 2 2 4 $7,234 $0 $0 $7,957
1.66 Submit 90% Plans, Specifications, and EEOPCC 4 4 $2,056 $0 $0 $2,262
1.67 90% Design Review Workshop with City and CWS 8 4 $3,204 $0 $193 $3,737
1.71 100% Final Bid Package (Plans, Specs, Bid Docs, and EEOPC) $0 $0 $0 $0
1.72 Plan updates 16 12 36 80 80 24 8 4 16 $45,784 $0 $0 $50,362
1.73 Electrical plans, specs, and estimate 6 6 $2,130 $15,146 $0 $19,003
1.74 Specification and City boiler plate updates 4 2 16 6 6 8 $8,206 $0 $0 $9,027
1.75 Preliminary Schedule 2 4 $1,482 $0 $0 $1,630
1.76 Final EEOPCC 3 2 6 4 $3,313 $0 $0 $3,644
1.77 Submit Final Bid Package (Hard copy, electronic format, and CAD format) 6 6 8 $4,404 $0 $1,150 $6,109 271 66 446 471 389 173 89 101 104 60 25 52 40
Task 1 Fee Subtotal $77,777 $16,302 $101,242 $70,179 $49,792 $24,566 $14,685 $19,796 $15,496 $6,780 $4,900 $6,032 $13,800 $421,347 $108,675 $2,456 $585,726 2 Bidding Phase (assuming bidding all in one package)
2.1 Project Management and Administration (assumes 3 months) 9 3 $2,382 $0 $0 $2,620
2.2 Respond to contractor questions re: plans and specifications (25 assumed) 6 12 $4,446 $0 $0 $4,891
2.3 Prepare modifications to Plans and/or Specifications (City to issue addenda) 4 8 8 $4,156 $0 $0 $4,572
2.4 Electrical Bid Assistance $0 $5,750 $0 $6,325
10 0 29 8 0 0 0 0 0 3 0 0 0
Task 2 Fee Subtotal $2,870 $0 $6,583 $1,192 $0 $0 $0 $0 $0 $339 $0 $0 $0 $10,984 $5,750 $0 $18,407 3 Construction Phase (assuming constructing all in one package)
3.1 Project Management and Administration (assumes 16 months) 48 16 $12,704 $0 $0 $13,974
3.2 Submittal reviews (100 assumed submittals and resubmittals) 8 50 150 50 $41,646 $0 $0 $45,811
3.3 Respond to RFIs (12 assumed) 6 18 $5,808 $0 $0 $6,389
3.4 General observation and on-site consulting service as requested by City 8 12 $5,020 $0 $0 $5,522
3.5 Investigate proposed contract change orders and submit background to City (3 assumed) 3 12 12 $5,373 $0 $0 $5,910
3.6 Assist in final inspection and prepare punchlist 8 12 $5,020 $0 $16 $5,540
3.7 Prepare and submit record drawings (reproducible) 6 48 24 $12,474 $0 $2,300 $16,251
3.8 Electrical Construction Assistance $0 $20,700 $0 $22,770 33 0 158 210 0 0 24 0 0 66 0 0 0
Task 3 Fee Subtotal $9,471 $0 $35,866 $31,290 $0 $0 $3,960 $0 $0 $7,458 $0 $0 $0 $88,045 $20,700 $2,316 $122,167 Project Hour Subtotals 314 66 633 689 389 173 113 101 104 129 25 52 40 2,828 Project Fee Subtotals $90,118 $16,302 $143,691 $102,661 $49,792 $24,566 $18,645 $19,796 $15,496 $14,577 $4,900 $6,032 $13,800 $520,376 $135,125 $4,773 $726,301 I:\Marketing\Proposals\2025\City of Bakersfield - PFAS Treatment Program - 25-644\Interview\Fee Package\2025 FeeEstimate.xlsx Page 2 of 2 2025 STANDARD FEE SCHEDULE
This schedule supersedes previously published fee schedules as of the effective date of January 1, 2025.
Multi-year contracts are subject to any subsequent changes in these rates.
STAFF TYPE FEE RANGE
ENGINEERING
Assistant Engineer $121.00 – $149.00
Associate Engineer $142.00 – $172.00
Senior Engineer $180.00 – $217.00
Principal Engineer $227.00 – $287.00
Associate Structural Engineer $142.00 – $172.00
Senior Structural Engineer $180.00 – $216.00
Principal Structural Engineer $226.00 – $266.00
Assistant Electrical, I&C Engineer $128.00 – $156.00
Associate Electrical, I&C Engineer $163.00 – $192.00
Senior Electrical, I&C Engineer $202.00 – $242.00
SPECIALISTS
Assistant Specialist $101.00 – $121.00
Associate Specialist $126.00 – $156.00
Senior Specialist $163.00 – $201.00
Principal Specialist $211.00 – $271.00
Assistant Biologist $102.00 – $117.00
Associate Biologist $122.00 – $149.00
Senior Biologist $156.00 – $178.00
Principal Biologist $186.00 – $226.00
Assistant Geologist/Hydrogeologist $111.00 – $136.00
Associate Geologist/Hydrogeologist $137.00 – $165.00
Senior Geologist/Hydrogeologist $176.00 – $206.00
Principal Geologist/Hydrogeologist $216.00 – $256.00
Principal Tunneling Consultant $251.00 – $281.00
PLANNING
Assistant Planner $103.00 – $123.00
Associate Planner $130.00 – $151.00
Senior Planner $158.00 – $186.00
Principal Planner $194.00 – $224.00
TECHNICAL
Assistant Technician $90.00 – $107.00
Associate Technician $114.00 – $138.00
Senior Technician $144.00 – $172.00
STAFF TYPE FEE RANGE
CONSTRUCTION SERVICES
Associate Construction Manager $140.00 – $160.00
Senior Construction Manager $167.00 – $191.00
Principal Construction Manager $201.00 – $231.00
Construction Inspector (1) $175.00 – $220.00
Construction Inspector OT (1) $225.00 – $270.00
Construction Inspector Dbl OT (1) $250.00 – $295.00
SUPPORT
Administrative Assistant $80.00 – $100.00
Project Administrator $94.00 – $120.00
Senior Project Administrator $128.00 – $210.00
Intern $70.00 – $85.00
SURVEYING SERVICES
Assistant Surveyor $116.00 – $146.00
Licensed Surveyor $166.00 – $206.00
1-Man Survey Crew $205.00
1-Man Survey Crew (1) $245.00
1-Man Survey Crew OT (1) $270.00
2-Man Survey Crew $315.00
2-Man Survey Crew (1) $345.00
2-Man Survey Crew OT (1) $370.00
(Field work not including survey equipment billed at individual standard rate plus vehicle as appropriate.)
(1) Prevailing wage rates shown for San Joaquin, Stanislaus, Merced, Madera, Fresno, Tulare, Kings, and Kern counties; other counties as quoted.
Additional Fees
Expert Witness / GIS Training: As quoted.
Travel Time (for greater than one (1) hour from employee’s base office): $95/hour (unless the individual’s rate is less) Project Costs
Mileage: IRS value + 15%
Outside Consultants: Cost + 15%
Direct Costs: Cost + 15%
WWW.PROVOSTANDPRITCHARD.COM (559) 449-2700
Attachment 1
1518 Mill Rock Way, Suite 100 Bakersfield, CA 93311 (661) 616-5900 www.provostandpritchard.com
City of Bakersfield Water Department PFAS Treatment Program – TentaƟve Project Schedule 11/17/25
12/15/25
1/12/26
2/9/26
3/9/26
4/6/26
5/4/26
6/1/26
6/29/26
7/27/26
8/24/26
9/21/26
10/19/26
11/16/26
12/14/26
1/11/27
2/8/27
3/8/27
4/5/27
5/3/27
5/31/27
6/28/27
7/26/27
8/23/27
9/20/27
10/18/27
11/15/27
12/13/27
1/10/28
2/7/28
3/6/28
4/3/28
Project Management
Technical Memorandum
30% Design
60% Design
90% Design
100% Design (Bid Set)
Bidding Phase
Construction Phase
Deliverable