Name Kevin Reisz, PE Gabriel Macias, PE Bobby Pentorali, PE Landon Wright Marty Sanchez TOTAL COST Classification
Project Manager Resident Engineer Structures Inspector (6) Office Engineer / Labor Complaince Officer
Hourly Billing Rate (1) $338.21 $231.46 $276.35 $229.19 $123.35

1.1 Kick-off Meeting 2 4

1.2 Pre-Construction Meeting 6 2

1.3 Pre-construction Photos 2 8
Man Hour Total 2 12 0 8 2
Total Fees $676.42 $2,777.52 $0.00 $1,833.52 $246.70 $5,534.16 Task 2.1 Project Coordination and Correspondence

2.1.1 Interaction with City Staff 8 80

2.1.2 Progress Meetings 84 30 30
Task 2.2 Project Administration and Documentation

2.2.1 Document Control 168 100

2.2.2 Schedule Update Review 84

2.2.3 Statement of Working Days 60

2.2.4 Submittal Management 484 8

2.2.5 Request for Information Management 84

2.2.6 Change Order Management & Cost Control 84

2.2.7 Monthly Payment Review & Cost Control 84

2.2.8 Claims Management 4 60

2.2.9 Labor Compliance 8 112
Task 2.3 Construction Observation Services / Inspection Services

2.3.1 Field Inspection and Daily Reporting 84 4 1026

2.3.2 Storm Water Pollution Prevention Plan(SWPPP) Monitoring 16 80 Task 2.4 Project Control Monument Staking

2.4.1 Project Control Monument Staking (Not Included)
Man Hour Total 12 1380 12 1136 242
Total Fees $4,058.52 $319,414.80 $3,316.20 $260,359.84 $29,850.70 $617,000.06

3.1 Final Inspection & Notice of Completion 8 16

3.2 Prepare & Recommend Final Payment Request 8 4

3.3 Review & Submit As-Builts 16 8

3.4 Deliver Project Files 2 2
Man Hour Total 0 34 0 24 6
Total Fees $0.00 $7,869.64 $0.00 $5,500.56 $740.10 $14,110.30 Man Hour Total Tasks 1 - 3 14 1426 12 1168 250
Total Fees Tasks 1 - 3 $4,734.94 $330,061.96 $3,316.20 $267,693.92 $30,837.50 $636,644.52 Notes and Assumptions: Other Direct Costs

1. NV5 employees hourly rates include project-related overhead, profit, safety equipment, vehicles, laptops, and cell phones.

2. Cost proposal is based on an average of 8-hour shifts according to the Caltrans 5-Day Working Calendar. Overtime hours will be paid in accordance with applicable labor law and prevailing wage rates. Office Expenses $0.00

3. Adjustments to this estimate may be required if the actual schedule requires more or less construction management services than proposed.

5. Time extensions to the project may result in additional Construction Managemnent services & fees. Total Proposal Costs $636,644.52

6. This estimate is based on the specific scope of work described for the Digester Gas Booster Blower Replacement Project E3K305

7. Classifications requiring prevailing wage are subject to the provisions set forth in the latest DIR determination.

8. This cost estimate includes services for dispute resolution through project acceptance. Services for claims after acceptance will be provided at additional costs.

TASK 3: POST CONSTRUCTION & PROJECT CLOSEOUT SERVICES
Fee Proposal for CM and Inspection Services - Wastewater Treatment Plant No. 3 - PROJECT NO. E3K305 Prepared for The City of Bakersfield
TASK I: PRECONSTRUCTION SERVICES
TASK 2: CONSTRUCTION MANAGEMENT SERVICES DURING CONSTRUCTION

4. This cost estimate is based on the project being completed within 530 (498 working days of CM support from NV5 assuming a December 1, 2025 start day) working days of the NTP issued to the Contractor.

Estimated hours in this proposal are based on the contractors schedule reveiwed by NV5, which shows 142 working days in the field. Estimate is also based on a list of submittals received from the City. Total count of submittals at 97 with 12 reviewed to date.

← All documents from this meeting