ADMINISTRATIVE REPORT

MEETING DATE: 12/17/2025 AGENDA CATEGORY: Consent – Bids TO: Honorable Mayor and City Council
FROM: Zachary Meyer, Public Works Director
DATE: 12/2/2025
SUBJECT: Contract Change Order No. 177 to Agreement No. 19-069 with Security Paving Company (increasing compensation by $10,000; revised not to exceed $152,235,004.59) for the Centennial Corridor Mainline Project. (Wards 1, 2, & 3)

RECOMMENDATION:

Staff recommends approval of the change order.

BACKGROUND:

The Centennial Corridor Mainline Project (Project) proposes to extend State Route 58 (SR -58) from the current terminus as a freeway at State Route 99 (SR -99) to the Westside Parkway. At the SR -58/SR-99 interchange, the Project adds a collector -distributor on the northbound SR -99 and constructs a new northbound to westbound connector. The Project also includes various local r oad improvements including; realignment and introducing cul-de-sacs at the end of local roads along the corridor, widening and realignment of Chester Avenue at SR -58, and construction of a traffic signal at the eastbound SR -58 ramps/Brundage Lane intersect ion (which is part of the SR -58/Cottonwood Road interchange). This Project was awarded in July of 2019.

Change Order No. 177 provides compensation to the contractor for additional work that was originally a part of the Belle Terrace Operational Improvements Project. Conflicts between the two projects results in this scope being moved to the Mainline Project. Work includes installation of concrete barrier and electrical items. This change order at an increase of $10,000.00 provides additional funds for Chan ge Order No. 55 which has been depleted.

FISCAL IMPACT:

The sum of all change orders to date on this project reflects a total cost increase of $5,221,348.34 which results in a 3.55% increase of the original contract amount as illustrated below:

Original Contract Amount = $147,013,656.25
Previous Change Orders = $5,211,348.34
Current Change Orders = $10,000.00
Amended Contract Agreement after CCOs = $152,235,004.59 Net Increase to date = $5,221,348.34
There is no General Fund impact associated with this change order.

Federal, State, and Local funding for these change orders is available in project TRCC21 Centennial Corridor Phase 4 Mainline.

COUNCIL GOAL:

Reliable Infrastructure

ATTACHMENTS:

CCO No 177