ADMINISTRATIVE REPORT
MEETING DATE: 2/11/2026 AGENDA CATEGORY: Consent– Agreements TO: Honorable Mayor and City Council
FROM: Zachary Meyer, Public Works Director
DATE: 1/23/2026
SUBJECT: Contract Change Order No. 169 to Agreement No. 19-069 Contract Change Order with Security Paving Company (increasing compensation by $22,000.00; revised not to exceed $152,257,004.59) for the Centennial Corridor Mainline Project. (Wards 1, 2, & 3)
RECOMMENDATION:
Staff recommend approval of the change order.
BACKGROUND:
The Centennial Corridor Mainline Project (Project) proposes extending State Route 58 (SR -58) from the current terminus as a freeway at State Route 99 (SR -99) to the Westside Parkway. At the SR -58/SR-99 interchange, the Project adds a collector -distributor on the northbound SR -99 and constructs a new northbound to westbound connector. The Project also includes various local road improvements including realignment and introducing cul -de-sacs at the end of local roads along the corridor, widening and realignment of Chester Avenue at SR -58, and construction of a traffic signal a t the eastbound SR -58 ramps/Brundage Lane intersection (which is part of the SR -58/Cottonwood Road interchange). This Project was awarded in July of 2019.
Change Order No. 169 provides compensation to the contractor for the casing installation of Pole “I” located at the southwest corner of Chester Avenue and Loustalot Lane. Upon drilling for the signal pole foundation, the soil collapsed due to sandy conditions. The soil condition was not expected and using casing is the method of operation for this case. This change order result s in an estimated increase of $22,000.00.
FISCAL IMPACT:
The sum of all change orders to date on this project reflects a total cost increase of $5,243,348.34 which results in a 3.57% increase of the original contract amount as illustrated below:
Original Contract Amount = $147,013,656.25
Previous Change Orders = $5,221,348.34
Current Change Order = $22,000.00
Amended Contract Agreement after CCOs = $152,257,004.59 Net Increase to date = $5,243,348.34
There is no General Fund impact associated with this change order.
Funding for these change orders is available in project TRCC21 Centennial Corridor Phase 4 Mainline.
COUNCIL GOAL:
Reliable Infrastructure
ATTACHMENTS:
Change Order