ADMINISTRATIVE REPORT

MEETING DATE: March 11, 2026 AGENDA CATEGORY: Consent - Agreements TO: Honorable Mayor and City Council
FROM: Zachary Meyer, Public Works Director
DATE: February 19, 2026
SUBJECT: Contract Change Order No.1 to Agreement No. 2023-206 with Crosstown Electric and Data Inc. ($28,755.70; revised not-to-exceed $2,328,755.70) for the Advanced Traffic Management System. Signal Coordination Part 1 (T1K304/CML 5109 (268), Traffic Signal Communications on Arterials (T1K305) CML 5109 (269)). (Wards 2,3,4,6)

RECOMMENDATION:

Staff recommends approval of the change order.

BACKGROUND:

The work to be performed consist s, in general, installation of new signal controller equipment and software along the street corridor segment of:

 Truxtun Avenue between Coffee Road and S Street.
 H Street between White Lane and Truxtun Avenue.
 Oak Street between Palm Street and 24th Steet.
 Ming Avenue between Scarlet Oak Drive and Valley Plaza.  Hageman Road between Old Farm Road and Fruitvale Avenue.  Coffee Road between White Lane and Jayme Avenue.
 23rd Street between F Street and M Street.
 24th between Oak Street and M Street.

Project T1K304 and Project T1K305 were combined and bid together. Change Order No. 1 provides for the replacement of the existing CAT -5 cable . During construction, it was discovered that the new Iteris cameras were not compatible with the existing CAT -5 c abling system. To ensure proper system performance, the existing CAT-5 cable must be replaced with new CAT-6 cable. The contractor agrees to do the above-mentioned work for the lump sum price of $28,755.70.

FISCAL IMPACT:

Project T1K304 and T1K305 are funded with State and Federal funds . Sufficient funds are budgeted to cover the cost of this Contract Change Order.

The total cost increase for contract change order number one is $28,755.70. This is the final change order for the project, and the project has been completed. This final change order reflects a total cost increase of $28,755.70 (1.25% increase to the original contract amount) as illustrated below:

Original Contract Amount = $2,300,000.00
Total of Previous Change order approved by council
contingency

=

$0
Current Contract Change Order = $28,755.70
Amended Contract Amount after Change order = $2,328,755.70 Net Increase to Date = $28,755.70

COUNCIL GOAL:

Reliable Infrastructure