AECOM
5001 E. Commercenter Drive
Suite 100
Bakersfield, CA 93309
www.aecom.com
661 325 7253 tel

Mr. Husain Ali
Engineer II
6901 McCutchen Road
Bakersfield, CA 93313

January 12, 2024

Wastewater Treatment Plant No. 3 Blower Replacement (E3K305) – Request for Amendment No. 1

Dear Ali:

The City of Bakersfield requested that our scope of work for the subject project be expanded to include replacing pressure relief valves, sediment traps, flame arrestors, and back-pressure relief valves for Digesters 3 through 6. We have prepared initial drawings and reviewed them with Brian Villacorta and Jim Groman who represent Varec Biogas. Following that review, our design scope was adjusted to also include a manhole pressure relief cover which is a new code requirement for digesters. The total price of the construction contract with this change should be in the range of $550,000 to $750,000. Our proposed fee increase is to provide design, bid-phase and engineering services for construction is summarized below and included in the attached staffing plan.

Summary

Design: Design services consist of two site visits, research of codes and coordination with vendors, selection of equipment and preparation of design with structural checks, prepare two drawings (one plan and one for sections and details, an additional specification section, addition to the engineering opinion of probable construction cost.
$16,300
Bidding Phase: Added services only include one more RFI. Other items are covered by our original contract.
700
Construction Phase: Engineering services during construction will consist of answering one additional RFI and two additional submittals. Other engineering services offered during construction are covered by our original contract.
2,000

Budgetary impact on total project $19,000

If you concur with the budget increase to our contract, please authorize by signing below. If you have questions regarding the addition of scope and/or fee or require further justification, please do not hesitate to call.

Yours sincerely,

William C. Black, PE
Project Manager
Accepted:

Eric Garibay, PE
Principal in Charge
City of Bakersfield

S:\City of Bakersfield\60702402 - WWTP 3 Blower Replacement \100_Contract [CONT]\110_Client_Contract [CL_CONT] \Amendment one\Added time for engineering services during construction.docx Budget
Task Description
Specialty Principal
Principal
Engineer III
Engineer II
Engineer I
Project Engineer II
CAD Technician
Engineering Tech
Total Hours
Labor
Non-Labor Fee
Total
Task 1 - Design Phase
Site Visits for design (assume 2) 2 0 4 4 10 1,660$ 50$ 1,710$ Research codes and with Vendors 2 0 4 8 14 2,300$ 69$ 2,369$ Design including structural check 4 12 8 24 3,800$ 114$ 3,914$ Plan Drawings (two) - -$ -$ -$
Plan view 2 2 12 16 1,760$ 53$ 1,813$
Sections and details 2 4 12 18 2,080$ 62$ 2,142$
Additional specification section 2 4 6 880$ 26$ 906$
Opinion of Probable Construction Cost 2 4 2 8 1,580$ 47$ 1,627$ Quality Control & Project Management 2 2 2 2 3 11 1,765$ 54$ 1,819$ Subtotal 8 4 6 - 26 32 28 3 107 15,825$ 475$ 16,300$
Task 2 - Bidding Phase
Attend Pre-Bid Meeting (already included) - -$ -$ -$
Respond to Bidder RFIs (One additional) 1 2 1 4 685$ 15$ 700$ Prepare Addenda (One assumed for project. No additional assumed with this change) - -$ -$ -$ Review Bids and recommend lowest responsible bid (already included) - -$ -$ -$ Subtotal - 1 - - - 2 - 1 4 685$ 15$ 700$
Task 3 - Construction Phase
Attend Pre-Construction Meeting (Already included) - -$ -$ -$ Respond to RFIs (One additional) 1 2 1 4 685$ 15$ 700$
Review Submittals (two additional) 1 2 4 1 8 1,245$ 55$ 1,300$ Electrical Site Visit (not required for change) - -$ -$ -$ Change Order (Assume 1)(already included with main project) - -$ -$ -$ Field Visits & Meetings (Assume 4)(already included with main project) - -$ -$ -$ Subtotal - 2 - - 2 6 - 2 12 1,930$ 70$ 2,000$
Total 8 7 6 - 28 40 28 6 123 18,440$ 560$ 19,000$
Personnel Hours
1/12/2024 Page 1 of 1