Mr. Husain Ali, PE
Engineer II
Department of Water Resources, Wastewater Division
City of Bakersfield
6901 McCutchen Road
Bakersfield, CA 93313
May 7th, 2025
Subject: Proposal for Amendment #2 for Wastewater Treatment Plant No. 3 Blower Replacement (E3K305)
Dear Ali:
AECOM Technical Services, Inc. (AECOM) is currently assisting the City of Bakersfield (City) with construction engineering services for the subject project per the City’s Agreement No. 2023-024 as amended . The equipment manufacturer for the blower skids has a procurement lead time of 40 weeks, extending the construction phase past what was originally anticipated during the preparation of the proposal. To date, we have received the anticipated number of Requests for Information (RFI’s) in the original scope of work and anticipate receiving additional RFI’s when construction on the blower skids begins . In addition, during the contractor’s preconstruction efforts, it was found that the MCC room did not have the ability to accommodate breakers for the new chillers resulting in an increase in the number of RFI’s, meetings, and revisions to the design. Separately, the City requested to add the replacement of the master control panel and revision of the blower panels manufacturer from Allen Bradley to Schneider Electric which will result in additional support efforts.
The extensive construction phase timeline, additional RFI’s, and revisions to the electrical design will result in an overrun of the existing budget. AECOM anticipates that additional time will be needed of AECOM to resolve issues that may arise as well as responding to additional submittals and RFI’s.
AECOM anticipates additional scope as follows:
RFI’s and Submittals:
A total of 12 RFI’s and 9 submittals have been received to date with no major construction taken place yet. It is anticipated that additional support will be needed when construction begins as follows. • Respond to an additional 14 RFI’s.
• Review an additional 2 Submittals. (master control panel, and blower skids control panel resubmittal)
Electrical Changes
• Per the City’s direction, the Blower Master Control Panel will be replaced. Its replacement was not part of the original scope of work. No design changes are anticipated, however; the additional effort includes time to support the City to integrate the change into the project including attending additional meetings and an additional submittal review.
• The lack of room in MCC-5 to fit the breakers and buckets for the blowers and the chillers (RFI 003) led to revisions to the electrical design drawings including the addition of a n electrical panel. This change is considered a betterment to the project as the efforts alleviate the congestion in the MCC room. This resulted in additional efforts from AECOM.
AECOM has exhausted our current construction phase engineering budget of $27,000 and is respectfully requesting that the City consider issuing a n amendment in the amount of $ 26,512.50 to provide additional construction phase engineering support services . We are proposing the City reallocate unused budget of $6,512.50 from the Bidding phase to the Construction phase for this work, resulting in a net change order of $20,000.00. Our proposed fee increases is summarized below and detailed in the attached staffing plan.
Previous Task Total Amendment 2 Change New Task Total
Task 1: Design Phase (LS) $134,300.00 $0.00 $134,300.00 Task 2: Bidding Phase (T&M) $9,700.00 -$6,512.50 $3,187.50 Task 3: Cons. Support (T&M) $27,000.00 $26,512.50 $53,512.50 Total $171,000.00 $20,000.00 $191,000.00
We appreciate your review and look forward to your response. If you have questions regarding the addition of scope and/or fee or require further justification, please do not hesitate to call.
Yours sincerely,
Yeimy G. Fernandez-Ojeda, PE
Project Manager
Accepted:
Eric Garibay, PE
Principal in Charge
City of Bakersfield
S:\City of Bakersfield\60702402 - WWTP 3 Blower Replacement\100_Contract [CONT]\110_Client_Contract [CL_CONT]\Amendment one\Added time for engineering services during construction.docx
Project Budget - Amendment No. 2
WWTP Blower Replacement City of Bakersfield
Budget
Task Description
Specialty Principal
Principal
Senior II
Senior I
Associate
CAD Supervisor
CAD Operator
Clerical
Total Hours
Labor
Non-Labor Fee
Total
Task 1 - Design Phase
Kickoff Meeting & Site Visit including minutes - -$ -$ Concept Plan and Process Control Narrative - -$ -$ -$ Technical Specifications - -$ -$ -$ Plans - -$ -$ -$ - General Sheets (Cover, notes, symbols abbreviations, Demo Plan)- 3 sheets - -$ -$ -$ - Mechanical Sheets (Process control, Piping schematic, Equipment layout, Piping layout) 5 sheets - -$ -$ -$ - Structural Sheets (General and notes, Foundations and Canopy) 5 sheets - -$ -$ -$ - Electrical & Instrumentation 10 sheets - -$ -$ -$ Opinion of Probable Construction Cost - -$ -$ -$ Quality Control & Project Management - -$ -$ -$ Subtotal - - - - - - - - - -$ -$ -$ Task 2 - Bidding Phase
Attend Pre-Bid Meeting -$ -$ -$ Respond to Bidder RFIs (Assume 5) -$ -$ -$ Prepare Addenda (Assume 1) -$ -$ -$ Review Bids and recommend lowest responsible bid -$ -$ -$ Subtotal - - - - - - - - - -$ -$ -$ Task 3 - Construction Phase
Attend Pre-Construction Meeting - - -$ -$ -$ Respond to RFIs (Assume 14 Additional) 4 8 30 5 47 7,855$ 236$ 8,091$ Review Submittals (Assume 2 Additional) 4 8 5 17 3,055$ 92$ 3,147$ Electrical Support for Addition of MCP 2 2 4 12 5 25 4,145$ 124$ 4,269$ Electrical Support Change in MCC (RFI #003) 8 2 6 12 10 4 42 7,320$ 266$ 7,586$ Electrical Site Visit - -$ -$ -$ Change Order - -$ -$
Field Visits & Meetings (Assume 2) 4 4 6 2 16 3,320$ 100$ 3,420$ Subtotal 22 8 32 - 54 10 - 21 147 25,695$ 818$ 26,513$ Total 22 8 32 - 54 10 - 21 147 25,695$ 818$ 26,512.50$ Personnel Hours