EXHIBIT A
Project No. Name/Location PCI SB1 Funding (FY 26/27) Description Est. Construction Dates Estimated Useful Life 27PWDE03
Pavement Rehabilitation: Calloway
Drive from Rosedale Highway to Olive
Drive (Ward 4)
62 $6,220,000
The existing pavement on Calloway Drive from Rosedale
Highwayto Olive Drive is in disrepair. This project will rehabilitate/reconstruct the existing pavement on Calloway Drive by removing up to 6" of pavement and replacing it with pavement consiting of HMA and R-HMA overlay cap and make the project ADA Accessible. This will improve the overall rideability of the road for both passenger cars and commercial vehicles.

June 2026 - June 2027 20-25 Years
27PWDE13
Pavement Rehabilitation: Ming Avenue
from New Stine Road to Real Road
(Ward 1)
61 $5,370,000
The existing pavement on Ming Avenue from New Stine Road to Real Road is in disrepair. This project will
rehabilitate/reconstruct the existing pavement on Ming Avenue by removing up to 6" of pavement and replacing it with pavement consiting of HMA and R-HMA overlay cap and make the project ADA Accessible. This will improve the overall rideability of the road for both passenger cars and commercial vehicles.

June 2026 - June 2027 20-25 Years