Hourly Billing Rates
ON-CALL Wastewater Maintenance RFQ
Item
Description Unit Hourly Rate
1. LABOR
a. Project Manager Hour
b. Foreman Hour
c. Superintendent Hour
d. Equipment Operator Hour
e. Journeyman Hour
f. Laborer or Equivalent Hour
2. EQUIPMENT
a. Boom Truck Hour
b. Service Vehicle (utility body pickup) or Equivalent Hour c. Backhoe (Case 580E or comparable) Hour
d. Welder Hour
e. Compressor (150 cfm) Hour
f.
g.
5 Yard Dump Truck
24-inch Vibratory Smooth Drum Roller
Hour
Hour
3. MOBILIZATION AND DEMOBILIZATION
a. Mobilization and Demobilization
(not to exceed 5% of total bid) (Fi
ll In)
5%
$51.74
$126.50
$126.50
$126.50
$99.00
$93.50
$58.22
$161.71
$19.41
$64.68
$143.00
$64.68
$84.09
June 2, 2026
4. OVERHEAD AND PROFIT
a. Overhead and Profit
(Fil
l In)
5. MATERIALS MARKUP
a. Materials Markup
(Fil
l In)
6. SUBCONTRACTOR MARKUP
a. Subcontractor Markup
(Fill In)
7. BONDS AND INSURANCE
a. Bonds and Insurance
(Fil
l In)
12%
10%
7%
1.5%