Amendment No. 1 to Agreement No. 2025-011 – IMPACT SCIENCES. Page 1 Updated – June 2026
AGREEMENT NO. 2025-011 (1)

AMENDMENT NO. 1 TO
AGREEMENT NO. 2025-011

This AMENDMENT NO. 1 TO AGREEMENT NO. 2025-011 is made and entered into on ________________, by and between the CITY OF BAKERSFIELD, a municipal corporation (referred to herein as “CITY”), and IMPACT SCIENCES, a corporation authorized to do business in California (referred to herein as “CONSULTANT”).

R E C I T A L S

WHEREAS, on February 12, 2025, CITY and CONSULTANT entered into Agreement No. 2025 -011 (the “Agreement”), wherein CONSULTANT agreed to perform the tasks outlined therein in preparation of an Environmental Impact Report (“EIR”) for Site Plan Review No. 24 -0027 and Zone Modification No. 24 - 0032, in the amount of $174,604.00; and

WHEREAS, the parties desire to amend Agreement No. 2025-011 to expand the scope of work and add compensation of $54,000.00 to a new not to exceed amount of $228,604.00.

NOW, THEREFORE, incorporating the foregoing recitals herein, CITY and CONSULTANT mutually agree as follows:

1. Section 1 of Agreement No. 2025- 011 entitled “SCOPE OF WORK ” is hereby amended to read as follows:

1. SCOPE OF WORK. In exchange for the Compensation (defined below), CONSULTANT shall perform the attached scope of work presented in Exhibit “C” (Scope of Work”). The Scope of Work shown in Exhibit “ C” shall include all items and procedures necessary to properly complete the task CONSULTANT has been hired to perform, whether specifically included in the Scope of Work or not.

2. Section 2 of Agreement No. 2025 -011 entitled
“COMPENSATION/PAYMENT PROCEDURE” is hereby amended to read as follows:

2. COMPENSATION/PAYMENT PROCEDURE. Subject to the conditions of this section, CITY will pay CONSULTANT as follows for performing the Scope of Work (“Compensation”): On a
time/material basis in accordance with the hourly rates as shown on Exhibit “D”.

Amendment No. 1 to Agreement No. 2025-011 – IMPACT SCIENCES. Page 2 Updated – June 2026

CITY will pay CONSULTANT within 30 days after CONSULTANT submits an itemized invoice for the portions of the Scope of Work completed and that invoice is approved by CITY. The
Compensation will be the total amount paid to CONSULTANT for performing the Scope of Work and includes, but is not limited to, all out-of-pocket costs and taxes. CITY will pay no other compensation to CONSULTANT. In no case will CITY compensate CONSULTANT more than $228,604.00 for performing the Scope of Work

3. Except as amended herein, all provisions of Agreement No. 2025 - 011 shall remain in full force and effect.

IN WITNESS WHEREOF, the parties hereto have caused this Amendment No. 1 to Agreement No. 2025- 011 to be executed the day and year first above written.

“CITY” “CONSULTANT”

CITY OF BAKERSFIELD IMPACT SCIENCES

By:____________________________ By:_________________________________

KAREN GOH JESSICA KIRCHNER
Mayor CEO & Managing Principal

APPROVED AS TO CONTENT:

DEVELOPMENT SERVICES DEPARTMENT

By:____________________________

PHILLIP BURNS
Development Services Director

APPROVED AS TO FORM: COUNTERSIGNED:

Deputy City Attorney II:_______________________________ Finance Director: _____________________

VIRIDIANA GALLARDO-KING RANDY MCKEEGAN

Insurance:____________

VGK/pt
Attachments: Exhibit C - Scope of Work
Exhibit D - Compensation

S:\Planning\Agrs\25-26\Amend 1 To Agreement 2025-011 IMPACT SCIENCES.doc

445 S. Figueroa Street, Suite 2550
Los Angeles, CA 90071
(213) 935-1901
www.impactsciences.com
Impact Sciences, Inc. 1 Ba kersfield Temple Budget Augment Request 0859.004 March 31, 2026

MEMORANDUM
To: Roque Nino, Principal Planner, City of Bakersfield Job No. 0859.004 From: Jessica Kirchner, AICP, CEO & Managing Principal, Impact Sciences, Inc.

Subject: Bakersfield Temple Budget Augment Request
Date: March 31, 2026

1. JUSTIFICATION FOR BUDGET AUGMENT
Impact Sciences is currently completing the EIR for the proposed Stockdale church project. As part of our work completing the draft EIR, we have identified areas that required a level beyond our contracted scope of work. We have identified these level of effort adjustments within two distinct phases of the project: Phase 04 (Technical Report Peer Review) and Phase 05 (Admin Draft Preparation). • Phase 04 Out -of-Scope Peer Review (Billed to Phase 05): The approved scope of work assumed a standard peer review process for six specific applicant -provided technical reports. However, additional effort in developing a standardized approach across technical sections was necessary. Further, in the Air Quality / Climate Change / Health Risk Assessment and the Acoustical Analysis multiple, iterative rounds of review and unbudgeted coordination meetings with the applicant’s team were necessary. Furthermore, a previously unidentified study , a Visual Impact Assessment , was added to the project, requiring additional unbudgeted meetings and a detailed review of the report. • Phase 05 Applicant and Lead Agency Review: Compounding the technical review effort, the original budget assumed two standard rounds of concurrent review by the Lead Agency and the applicant before finalizing a publication-ready Draft EIR. However, the intended concurrent review did not materialize.

Consequently, an unanticipated round of review without consolidated comments was required, resulting in extended revision cycles of the draft sections to prepare the document for publication. • Project Meetings. Due to circumstances beyond the consultant’s control, including the addition of new technical studies, and the multiple rounds of review , the overall schedule was pushed resulting in additional meetings. Meetings were attended by both the project manager and the principal in charge.

2. SCOPE OF ADDITIONAL SERVICES
• Task A: Additional Draft Review Cycles and Finalization This task covers the unbilled effort already expended to facilitate the added review cycles. It also provides the necessary hours for the project team to review the City’s upcoming comments, execute the required text revisions, perform final QA/QC, and format the final Screencheck document for publication. • Task B: Direct Expenses Adjustment
This task provides additional direct expense funding (Phase 88) to cover physical production of the 5 hardcopy Draft EIRs and accompanying USB flash drives, standard First -Class postage for the 85 NOA mailings (which is greater than originally scoped), and future mileage/travel expenses for two staff members to attend the Planning Commission and City Council hearings in Bakersfield.

EXHIBIT C
Impact Sciences, Inc. 2 B akersfield Temple Budget Augment Request 0859.004 March 31, 2026

3. COST ESTIMATE
We request a total budget augment of $54,000 on a time -and-materials basis to cover the incurred overages from the expanded review cycles in Phases 04 and 05 and to complete the remaining Scope of Additional Services.

A summary of this budget augment request is provided in Table 1 below, and the estimated hourly breakdown to complete the remaining tasks is detailed in Table 2.

Table 1
Budget Augment Cost Summary
Scope Task/Phase Justification Incurred Cost
(Overage)
Estimated
Cost to
Complete
Total
Requested
Augment
Task A: Additional
Draft Review Cycles
and Finalization
(Phases 05 & 06)
Out-of-scope, expanded technical report reviews
Unanticipated additional rounds of review and
final Screencheck QA/QC.
$47,118.00 $6,632.00 $53,750.00
Task B: Direct
Expenses Adjustment
(Phase 88)
NOA mailing to higher-than-estimated number
of addresses and postage, and adjusted buffer
for Hardcopy/USB printing and forthcoming
travel to Bakersfield.
$0.00 $250.00 $250.00
Total $47,118.00 $6,882.00 $54,000.00
Table 2
Hourly Breakdown for the Estimated Cost to Complete
Scope Task/Phase Personnel Rate Hours Extended Cost
Task A: Additional Draft Review Cycles and Finalization (Phases 05 & 06)
Principal $295/hour 4.0 $1,180.00
Senior Project Manager $200/hour 22.0 $4,400.00
Planner $140/hour 6.0 $840.00
Publications $125/hour ~1.7 $212.00
Task A Subtotal $6,632.00
Task B: Direct Expenses Adjustment
(Phase 88) -- -- -- $250.00
Task B Subtotal $250.00
Total Estimated Cost to Complete $6,882.00
P
lease let me know if you have any questions regarding this scope or fee. If acceptable, please sign and return the signature pages that follow.