ADMINISTRATIVE REPORT

MEETING DATE: July 15, 2026 AGENDA CATEGORY: Consent – Agreements TO: Honorable Mayor and City Council
FROM: Zachary Meyer, Public Works Director
DATE: June 20, 2026
SUBJECT: Contract Change Order No. 4 to Agreement No. 2022-278 with Day’s Generator Service, Inc. ($45,161.89; revised not to exceed $1,013,314.92) for the Backup Generator City Hall North.

RECOMMENDATION:

Staff recommends approval of the change order.

BACKGROUND:

The work to be performed consists, in general of procuring and installing one diesel powered generator at the City Hall North parking lot. Other work items include construction of concrete pad for the generator, block wall enclosure, solid steel gate, electrical connections, appurtenances, permitting (Building and Air Pollution Control Boards) and other items as necessary to have a full turnkey operation.

Change Order No.4 provides for supplying a temporary backup generator to provide power to City Hall North during the time PG&E will transfer from the existing service to the new service location. The contractor agrees to do the above-mentioned work for the lump sum price of $24,708.00.

In addition, during construction it was necessary to maintain vehicular access to the alley behind City Hall North. The contractor agrees to provide the necessary steel plates to provide alley access for the lump sum price of $11,778.68

Finally, during a rainstorm, heavy flow from the adjacent gutter caused the partial collapse of the trench which destabilized the steel plates covering the trench. In order to maintain safe passage through the alley behind City Hall, the trench must be backfilled and compacted, graded to a smooth surface and then covered with steel plates. The contractor agrees to do the above-mentioned work for the lump sum price of $8,675,21.

FISCAL IMPACT:

Project P1K319 is funded through the General Fund.

The total cost increase for Contract Change Order No. 4 is $45,161.89. This is the fourth and final change order on the project and reflects a total project cost increase of $123,543.92 (13.88 percent increase of the original contract amount) as illustrated below.

Original Contract Amount

=

$ 889,771.00
Total of Previous Change Order approved by council = $ 78,382.03 Current Contract Change Order # 4 = $ 45,161.89 Amended Contract Amount after Change Order = $ 1,013,314.92 Net Increase to Date = $ 123,543.92