S:\03_Advance Planning\01_GPAs\01_Active\2024\24-0514_10151 Wible Rd\09_EIR PROCESS\01_Contract PAGE 1 OF 6 PAGES
AGREEMENT NO. ____________

APPLICANT/REIMBURSEMENT AGREEMENT
THIS APPLICANT/REIMBURSEMENT AGREEMENT is made and entered into on ___________________ by and between the CITY OF BAKERSFIELD, a municipal corporation (referred to herein as “CITY”), and BT DEVELOPMENT II, LLC, a Limited Liability Company authorized to do business in California (referred to herein as “APPLICANT” ).

RECITALS
WHEREAS, APPLICANT has filed an application with the CITY for a General Plan Amendment, Zone Change No. 24-0514 and Williamson Act Cancelation No. 26-0001, (the “Project” herein); and
WHEREAS, said Project is to develop approximately 118 acres of agricultural land;
WHEREAS, it has been determined that the preparation of an Environmental Impact Report (“EIR”) is required for the Project; and WHEREAS, it is CITY’S responsibility to prepare or cause the EIR to be prepared; and
WHEREAS, CITY intends to contract with a consultant to prepare the EIR; and
WHEREAS, CITY shall require APPLICANT to reimburse CITY for the costs of preparation and certification of the EIR, including both consultant’s costs and CITY staff costs; and
WHEREAS, APPLICANT desires CITY to contract with a consultant to prepare and present an EIR for the Project and agrees to reimburse CITY for all costs related to the preparation and certification of the EIR.

NOW, THEREFORE, CITY AND APPLICANT MUTUALLY AGREE AS FOLLOWS:

1. SCOPE OF WORK. CITY shall hire a consultant of its choice to prepare the EIR and any other work relating to the environmental evaluation of the Project. The work to be performed by the consultant and CITY staff includes all actions necessary to complete the task the consultant has been hired to perform, S:\03_Advance Planning\01_GPAs\01_Active\2024\24-0514_10151 Wible Rd\09_EIR PROCESS\01_Contract PAGE 2 OF 6 PAGES
whether specifically included in the scope of work or not. The work program for the consultant is attached hereto and incorporated herein as Exhibit “A”.

2. COMPENSATION. APPLICANT shall reimburse CITY for all costs related to the preparation and certification of the EIR by consultant and CITY staff as follows:

2.1. Consultant’s cost for preparation of the EIR is $276,787.00.

2.2. CITY’s cost associated with preparation of the EIR is estimated to be $55,357.00.

The initial amount of $332,144.00 (Consultant and CITY Cost) which constitutes a total of the estimated costs of services to be performed by consultant and CITY staff, shall be paid prior to City Council approving this Agreement. Applicant shall also pay any additional funds requested by CITY to pay costs associated with preparation of the EIR. Said additional payments shall be due and payable within 5 business days of CITY’s notification to APPLICANT.

3. RECORDS OF COSTS. At such time as CITY requires additional funds from APPLICANT, CITY shall provide APPLICANT with a record of the costs for which APPLICANT is being charged. After certification of the EIR and final consideration of the Project, CITY shall provide APPLICANT with a final accounting of the costs for which APPLICANT has been charged.

4. PREPARATION AND SUBMITTAL OF SPECIAL STUDIES. The APPLICANT has chosen to contract qualified professional consultants to prepare certain specialized environmental studies (herein referred to as “STUDIES”), as follows:

4.1. Air Quality/ Climate Change Analysis/Health Risk Assessment

4.2. Biological Resources Study

4.3. Archaeological/Cultural Resources Study;

4.4. Traffic Impact Study (including VMT analysis)

4.5. Phase I Environmental Site Assessment (at a minimum)

4.6. Water Supply Assessment

4.7. Acoustical Analysis

4.8. Agricultural Conversion Study
S:\03_Advance Planning\01_GPAs\01_Active\2024\24-0514_10151 Wible Rd\09_EIR PROCESS\01_Contract PAGE 3 OF 6 PAGES

4.9. Water Will-Serve or Availability Letter
APPLICANT agrees that the STUDIES shall be prepared in accordance with CEQA and in a format acceptable to the CITY. APPLICANT agrees that it shall be its responsibility to cover the costs of any additional information, analysis, corrections, and revision of the STUDIES deemed to be required by the Planning Director. APPLICANT understands they are fully responsible for managing consultants hired by them to prepare the special studies listed above and provide STUDIES and any required information in accordance with the Project schedule and associated deadlines provided by the CITY.

5. INDEMNITY. APPLICANT shall indemnify, defend and hold harmless CITY, its officers, agents and employees against any and all liability, claims, actions, causes of action or demands whatsoever against them, or any of them, before administrative or judicial tribunals of any kind whatsoever, arising out of, connected with or caused by APPLICANT or APPLICANT’S employees, agents or independent contractors or companies in the performance of, or in any way arising from, the terms and provisions of this Agreement whether or not caused in part by the party indemnified hereunder, except for City’s sole active negligence or willful misconduct.

6. TERMINATION. This Agreement may be terminated upon fourteen (14) calendar days written notice for any of the following reasons:

6.1. APPLICANT withdraws the application.

6.2. APPLICANT fails to provide adequate funds as requested by the CITY.

6.3. APPLICANT fails to cooperate with CITY or Consultant.

Any unexpended funds as of the date of termination shall be returned to APPLICANT.

7. WAIVER OF DEFAULT. The failure of any party to enforce against another provision of this Agreement shall not constitute a waiver of that party’s right to enforce such provision at a later time, and shall not serve to vary the terms of this Agreement.

8. FORUM. Any lawsuit pertaining to any matter arising under, or growing out of, this contract shall be instituted in Kern County, California.

9. NOTICES. All notices relative to this Agreement shall be given in writing and shall be personally served or sent by certified or registered mail and S:\03_Advance Planning\01_GPAs\01_Active\2024\24-0514_10151 Wible Rd\09_EIR PROCESS\01_Contract PAGE 4 OF 6 PAGES
be effective upon depositing in the United States mail. The parties shall be addressed as follows, or at any other address designated by notice:

CITY: CITY OF BAKERSFIELD
1600 Truxtun Avenue
Bakersfield, California 93301
Phillip Burns
Development Services Department
1715 Chester Avenue
Bakersfield, CA 93301
(661) 326-3733
APPLICANT: BT Development II, LLC
Attn: Nathan Bender
P.O. Box 1231
Bakersfield, CA 93302
(661) 343-5404

10. ASSIGNMENT. This contract shall not be assigned by any party, or any party substituted, without prior written consent of all the parties.

11. BINDING EFFECT. The rights and obligations of this Agreement shall inure to the benefit of, and be binding upon, the parties to the contract and their heirs, administrators, executors, personal representatives, successors and assigns, and whenever the context so requires, the masculine gender includes the feminine and neuter, and the singular number includes the plural. This Agreement may be executed in any number of counterparts, each of which shall be considered as an original and be effective as such.

12. MERGER AND MODIFICATION. This contract sets forth the entire Agreement between the parties and supersedes all other oral or written representations regarding the preparation of this Environmental Impact Report.

This contract may be modified only in a writing approved by the City Council and signed by all the parties.

13. CORPORATE AUTHORITY. Each individual executing this Agreement represents and warrants they are duly authorized to execute and deliver this Agreement on behalf of the corporation or organization, if any, named herein and this Agreement is binding upon said corporation or organization in accordance with its terms.

S:\03_Advance Planning\01_GPAs\01_Active\2024\24-0514_10151 Wible Rd\09_EIR PROCESS\01_Contract PAGE 5 OF 6 PAGES

14. EXECUTION. This Agreement is effective upon execution. It is the product of negotiation and all parties are equally responsible for authorship of this Agreement. Section 1654 of the California Civil Code shall not apply to the interpretation of this Agreement.

15. ACCOUNTING RECORDS. CITY shall maintain accurate accounting records and other written documentation pertaining to all costs incurred in performance of this Agreement. Such records and documentation shall be kept at City Hall during the term of this Agreement, and for a period of three years from the date of the final payment hereunder, and said records shall be made available to APPLICANT upon request at any time during regular business hours.

IN WITNESS WHEREOF, the parties hereto have caused this Agreement to be executed, the day and year first-above written.
“CITY” “APPLICANT”
CITY OF BAKERSFIELD BT Development II, LLC
By: _______________________ By: _______________________ KAREN K. GOH NATHAN BENDER
Mayor President

APPROVED AS TO FORM:

VIRGINIA GENNARO
City Attorney
By:

VIRIDIANA GALLARDO-KING
Deputy City Attorney II
[Signatures on Following Page]
S:\03_Advance Planning\01_GPAs\01_Active\2024\24-0514_10151 Wible Rd\09_EIR PROCESS\01_Contract PAGE 6 OF 6 PAGES
APPROVED AS TO CONTENT:

DEVELOPMENT SERVICES DEPARTMENT
By:

PHILLIP BURNS
Development Services Director
COUNTERSIGNED:

By:

RANDY McKEEGAN
Finance Director
Attachment: Exhibit A - Scope of Work
Environmental Impact Report for the General Plan Amendment and Zone Change No. 24-0514 11 and Williamson Act Cancelation No. 26-0001 (Taft Highway and Wible Road) City of Bakersfield
Project Approach and Work Schedule
Project Understanding
FCS understands that the City is seeking a qualified consultant to prepare an EIR in compliance with CEQA for the General Plan Amendment (GPA) and Zone Change No. 24-0514, including the associated Williamson Act Cancellation No. 26-0001. The EIR will serve as the environmental document supporting the City’s review and consideration of the proposed land use and zoning changes, which will ultimately be evaluated by the Bakersfield Planning Commission and considered for final approval by the Bakersfield City Council. The approximately 118-acre site is located at 10161 Wible Road, situated at the southwest corner of Wible Road and Taft Highway (State Route 119). FCS understands and is prepared to start work within three weeks of the City’s authorization to proceed and will complete work within the allotted time specified in the Professional Services Agreement.

Cornerstone Engineering, Inc. (applicant) is proposing to convert the existing agricultural land to a mixed-use development consisting of residential neighborhoods of varying densities and supporting commercial uses. The requested GPA would change the land use designation from a Resource-Intensive Agriculture designation to a combination of Low Density Residential, Low Medium Density Residential, High Medium Density Residential, and General Commercial. Corresponding zoning changes are proposed from Agricultural zoning to Single-unit Dwelling, Small Lot Single-unit Dwelling, Medium Density Multi-unit Dwelling, and Regional Commercial. The proposed residential development is anticipated to include approximately 78 residential duplexes totaling 156 residential units, 240 low-rise apartments including a recreation center, 356 single-family homes and approximately 150,000 square feet of commercial development.

The proposed project site consists of two contiguous agricultural parcels (Assessor’s Parcel Numbers 184-200-14 and 184-200-15) that are currently used for agricultural production, primarily almond cultivation, and contain two existing single-family residences. The project site is presently under a Williamson Act contract; however, a Williamson Act Contract Cancellation request (WAC 26-0001) has been submitted by the property owner. Adjacent land uses consist of vacant commercial land to the north, a convenience store and fuel station with nearby farmland to the east, and agricultural properties to the west and south.

FCS’s overall approach to the preparation of the EIR will ensure that the environmental documents and studies fulfill the requirements of the City and meet the analysis standards required under CEQA. Our approach to preparing EIRs has been developed through 43 years of experience working with cities and counties in California to prepare thoughtful, defensible environmental documents in a timely manner.

Scope of Work
The following tasks are proposed to complete the identified Scope of Work (Scope) for the City’s project:

Task 1: Kick-off Meeting and Background Review
FCS will review relevant background material, develop an initial data needs list, and coordinate with the City to schedule a kick-off meeting (it is anticipated that the kick-off meeting will be completed via teleconference). The intent of the kick-off meeting is to clarify and confirm the details of the Scope and schedule, obtain copies of the project plans and other relevant information, identify key points of contact, establish communication protocols and expectations, and discuss the project's objectives, which will help inform the development and evaluation of project alternatives in the EIR. It is typically helpful to have all relevant team members attend this call (i.e., applicant, civil engineering design team, and general contractor, if applicable). FCS will provide the City and the applicant with a kick-off meeting agenda, followed by a memorandum that summarizes the meeting, including agreed-upon action items, timing of the items, and who is responsible for completing each item.

Following the kick-off meeting, FCS will mobilize and review relevant background documents provided by the City and applicant, as well as other available information pertinent to the project, to ensure project understanding. While reviewing this information, FCS will also provide a Request for Information (RFI), which will detail additional information needed to complete the EIR. FCS will also provide a full project schedule organized by task/milestone spanning from the kick-off meeting through Final EIR consideration by the City Planning Commission and, upon final approval by the City Council.

DELIVERABLES:
 Electronic copy (via File Transfer Protocol [FTP] site in Microsoft Word format and PDF) of the kick-off meeting agenda to the City.
 Electronic copy (via FTP site in Microsoft Word format and PDF) of the kick-off meeting memorandum to the City.

E X HIBIT A
Environmental Impact Report for the General Plan Amendment and Zone Change No. 24-0514 12 and Williamson Act Cancelation No. 26-0001 (Taft Highway and Wible Road) City of Bakersfield
 Electronic copy (via FTP site in Microsoft Word format and PDF) of the information needs list (as needed) to the City.  Electronic copy (via FTP site in Microsoft Word format and PDF) of the full project schedule organized by task/milestone to the City.

Task 2: Notice of Preparation and Circulation
Subtask 2.1: Notice of Preparation and Initial Study
FCS will prepare an Initial Study checklist for the proposed project. This task includes effort required to complete the checklist, associated research, and coordination amongst FCS staff and the City. FCS will utilize the applicant-prepared studies in support of the Initial Study:
 Air Quality/Climate Change Analysis/Health Risk
Assessment (HRA)
 Biological Resources Study
 Archaeological/Cultural Resources Study
 Traffic Impact Study (including VMT analysis)
 Water Will-Serve or Availability Letter
 Water Supply Assessment
 Phase I ESA (at a minimum)
 Acoustical Analysis
 Agricultural Conversion Study
The Initial Study format will include separate sections for discussion of each CEQA Guidelines Appendix G Environmental Checklist impact category, and it will be adequately supported by figures (including color GIS mapping, as appropriate). The Initial Study will evaluate project impacts against each question on the Appendix G Environmental Checklist and determine whether a potentially significant impact could occur that requires mitigation or if impacts would be less than significant and would not require mitigation. FCS will submit the Draft Initial Study to the City for review. It is assumed that the City will coordinate review and will provide one set of consolidated, vetted comments (with tracked changes in the Word document) on the Draft Initial Study to FCS within two weeks of submittal.

FCS will prepare the Administrative draft NOP and associated documents, including an Initial Study, prepare the Final NOP for public distribution in electronic format, and submit the Final NOP and Notice of Completion (NOC) electronically to the State Clearinghouse (SCH). FCS will distribute the NOP and accompanying cover letter to agencies and interested parties identified on a mailing list provided by the City. For budgeting purposes, this Scope assumes distribution to up to 60 recipients via electronic delivery, overnight carrier, or certified US Mail, as directed by the City.

Additional recipients may require an amendment to this Scope and fee. FCS will attend the City’s Scoping Meeting during the 30-day public review period.

FCS will review and assess all comments received during the NOP review period and will prepare responses to those comments for inclusion in the Draft EIR. Responses will be coordinated with the City and incorporated, as appropriate, into the environmental analysis, project description, and other relevant sections of the Draft EIR.

DELIVERABLES:
 Electronic copy (via USB flash drive/FTP site/other alternative in Microsoft Word format and PDF) of the Final NOP and NOC to SCH.
 Electronic copy (via one USB/flash drive in Microsoft Word format and PDF) of the Final NOP, set of NOP figures, and all documents cited in the Final NOP to the City.
 Two hard copies of the Final NOP to the City.
 Up to 60 to be mailed via certified US mail of the Final NOP to the City-provided mailing list.  FCS attendance at City’s Scoping Meeting.

Subtask 2.2: Scoping Meeting Attendance
FCS will attend the City’s Scoping Meeting during the 30-day public review period and will assess all comments received on the NOP and prepare responses through the Draft EIR. It is assumed that the City will be responsible for conducting the Scoping Meeting.

Task 3: Expanded Project Description Preparation
FCS will augment the NOP project description with the most current information and comments from the NOP public review period (discussed in Task 2 above) and develop an expanded draft project description. FCS will conduct a field reconnaissance of the project site and surrounding area to get a better understanding of the site in anticipation of preparing the expanded project description. FCS will review the applicant-provided technical reports (discussed in Task 4 below) to enhance our understanding of the existing project setting and will supplement our review with in-house

EXHIBIT A
Environmental Impact Report for the General Plan Amendment and Zone Change No. 24-0514 13 and Williamson Act Cancelation No. 26-0001 (Taft Highway and Wible Road) City of Bakersfield
resources and additional research. FCS will prepare and submit an RFI memorandum (if necessary) to the City to further refine and clarify the Project Description (discussed above in Task 1). FCS will then use the information from field reconnaissance, technical reports, in-house resources, additional research, and other provided information to prepare a project description (within 60 days of the authorization to proceed) to be used for the subsequent environmental documentation.

The Project Description will include a detailed narrative of the project components, with graphics and maps to highlight the project location, project elements, current land-use designations and zoning classifications, and surroundings. As discussed in Task 1, FCS will work closely with the City and the applicant to develop an agreed-upon list of project objectives. FCS assumes one round of review of the administrative draft Project Description and a two-week review period for City review.

DELIVERABLES:
 Electronic copy (via USB flash drive/FTP site/other alternative in Microsoft Word format) of the Administrative draft Project Description to the City.
 Electronic copy (via USB flash drive/FTP site/other alternative in Microsoft Word format) of the Draft Project Description to the City.

Task 4: Applicant-prepared Technical Report Peer Review FCS will peer review the technical studies provided by the applicant to verify their completeness accuracy for purposes of CEQA; ensure consistency with the City’s General Plan and Development Code; ensure compliance with all applicable environmental laws, regulations, rules, and requirements; and ensure legal defensibility and accuracy in the representation of project-related information from the City.

FCS’s team of in-house experts includes a Senior Vice President, Senior Biologist, Director of Cultural Resources, Director of Noise and Air Quality Services, Project Managers, and expert in-house legal counsel. Our teaming partners, Cameron-Cole, P&P, and West Yost will peer review the Phase I ESA, Traffic Impact Study (including VMT analysis), and Water Will-Serve/Availability Letter and Water Supply Assessment, respectively.

The team will perform a thorough review of study methodology, modeling, calculations, findings, and results to identify inaccuracies, inconsistencies, or incompleteness, with a focus on ensuring the studies are legally defensible and adequate for purposes of CEQA. FCS will conduct a review and prepare a peer review memorandum for each technical report to make the City aware of concerns associated with CEQA adequacy and to provide feedback that a report is sufficient for the purposes of the CEQA analysis. Any additional analysis (including site visit) would be addressed in a separate scope and fee. The following technical studies will be peer reviewed:

1. Air Quality/Climate Change Analysis/HRA

2. Biological Resources Study

3. Archaeological/Cultural Resources Study

4. Traffic Impact Study (including VMT analysis)

5. Water Will-Serve or Availability Letter

6. Water Supply Assessment

7. Phase I ESA (at a minimum)

8. Acoustical Analysis

9. Agricultural Conversion Study
Following the City’s initial review, it is assumed that the applicant will revise the technical reports as necessary to address comments, and that only one subsequent review for confirmation of adequacy will be required. Should additional rounds of revisions be necessary, a separate work authorization will be required.

DELIVERABLE:
 Electronic copy (via USB flash drive/FTP site/other alternative in PDF) of the technical report sufficiency memoranda for each of the above-listed technical studies to the City.

Task 5: Administrative Draft EIR Preparation
FCS will prepare the Administrative Draft EIR in accordance with the City’s CEQA Implementation Procedures. The project will be analyzed at the project level, providing sufficient study to conclude that additional CEQA compliance will not be required if the City’s decision-making bodies approve the project and certify the EIR. The Administrative Draft EIR will include all the required contents per CEQA and will include a detailed inventory of existing conditions, thresholds of significance used for the evaluation of impacts, and an analysis of the environmental impacts and levels of significance. Appropriate mitigation measures will be provided for potential impacts identified in each environmental issue area shown in the City’s Initial Study Environmental Analysis checklist (i.e., Aesthetics, Agriculture and Forest Resources, Air Quality, etc.) for which a potentially significant impact may occur.

EXHIBIT A
Environmental Impact Report for the General Plan Amendment and Zone Change No. 24-0514 14 and Williamson Act Cancelation No. 26-0001 (Taft Highway and Wible Road) City of Bakersfield
FCS assumes that two rounds of review of the Administrative Draft EIR by the City and 20 days for our review of the City changes will be required, with an estimated target date of six to eight months to get the Draft EIR circulated from the time FCS is awarded the contract. FCS will provide revisions to the Administrative Draft EIR in underline/strikeout format.

Technical Issues
The EIR will focus on the potentially significant environmental impacts identified in the NOP.

Alternatives
FCS will work closely with the City to identify and screen a reasonable range of alternatives for analysis in the EIR.

These alternatives will be based on our ability to feasibly attain most of the project objectives while avoiding or substantially lessening any of the significant environmental impacts of the project. As allowed by CEQA, the alternatives will be analyzed at a reduced level of detail in comparison to the project.

Consequences of Project Implementation
 Cumulative Impacts: FCS will prepare a cumulative impacts analysis, which will focus on the potential for environmental impacts from this project, along with other proposed and reasonably foreseeable projects in the area.

The list of cumulative projects will be developed in coordination with the City. The project’s contribution to the overall cumulative baseline will be evaluated and “cumulatively considerable” impacts will be identified. Mitigation measures will be developed for any cumulatively considerable impacts, if applicable and feasible.  Growth-inducing Impacts: As required by CEQA, the EIR will evaluate whether the project has the potential to directly or indirectly foster economic or population growth. This analysis will include an assessment of whether the project would directly contribute to growth or remove obstacles to population growth, such as through the extension of infrastructure. The City will evaluate whether any projected increase in population as a result of the project would result in additional impacts to existing community resources or encourage and facilitate other activities that could significantly affect the environment.
 Significant Irreversible Environmental Changes: FCS will summarize the significant and unavoidable impacts resulting from the project and will identify any significant irreversible changes and irretrievable commitments of the environment. This will include a discussion of nonrenewable resources, permanent conversion of land uses, improvements to areas previously inaccessible, and other factors that would commit future generations to similar environmental impacts.
 Effects Found Not To Be Significant: FCS will provide a qualitative explanation of issues found not to be significant during the NOP process as well as impacts that were studied in the EIR and determined to be less than significant.

Organizations and Persons Consulted
FCS will prepare this section to document any federal, State, or local agencies, other organizations and private individuals consulted in preparing the EIR.

Preparers
FCS will prepare this section to document all preparers of the EIR and their contribution.

Acronyms
FCS will prepare this section to define all acronyms used in the EIR.

Bibliography
FCS will prepare this section to Modern Language Association or Chicago Manual of Style standards and include all personal communications. FCS will also keep electronic copies of all reference materials for the administrative record (see Task 11).

DELIVERABLES:
 Electronic copy (via USB flash drive/FTP site/other alternative in Microsoft Word File) of the Administrative Draft EIR to the City.
 Electronic copy (via USB flash drive/FTP site/other alternative in Microsoft Word File) of the Revised Administrative Draft EIR to the City.

EXHIBIT A
Environmental Impact Report for the General Plan Amendment and Zone Change No. 24-0514 15 and Williamson Act Cancelation No. 26-0001 (Taft Highway and Wible Road) City of Bakersfield
Task 6: Screencheck Draft EIR Preparation
After the two rounds of review of the Administrative Draft EIR, FCS will then revise and prepare a Screencheck Draft EIR and technical appendices for approval by the City within two weeks of receiving comments from the City, before distributing the Draft EIR for the required 45-day public review period.

DELIVERABLE:
 Electronic copy (via USB flash drive/FTP site/other alternative in PDF) of the Screencheck Draft EIR to the City.

Task 7: Draft EIR and Technical Appendices Circulation
Following approval of the Screencheck Draft EIR, FCS will prepare, print (as needed), and distribute the Draft EIR (with appendices on USB flash drive). FCS will submit the Draft EIR and NOC to SCH following in accordance with current electronic filing requirements and will coordinate circulation of the Notice of Availability (NOA) and Draft EIR to agencies, organizations, and interested parties included on the City-provided mailing list. For budgeting purposes, this Scope assumes distribution to up to 60 recipients via electronic delivery, overnight carrier, or certified US Mail, as directed by the City. Additional recipients may require an amendment to this Scope and fee.

DELIVERABLES:
 Electronic Copy (via CEQAnet) of the Draft EIR and appendices, NOC, NOA, and Governor’s Office of Land Use and Climate Innovation Summary Form to the SCH.
 Electronic copy (via USB flash drive/FTP site/other alternative in PDF) of the Draft EIR (including PDF, Microsoft Word versions, and figures) and NOC to the City.
 Up to 60 electronic copies to be emailed of the NOA, to the City-provided mailing list.  Five hard copies of the Draft EIR (with Draft EIR and appendices on USB flash drive) to the City.  Two hard copies of the Draft EIR including tabbed technical appendices to the City.

Task 8: Draft and Screencheck Final EIR and Technical Appendices Preparation and Circulation
Subtask 8.1: Draft Final EIR
FCS will prepare the Draft Final EIR based on comments received during the 45-day public review period. FCS will evaluate and annotate comments received and prepare written responses to all comments as required by CEQA. FCS assumes that only one round of review of the Draft Final EIR by the City will suffice, and that it will take FCS approximately one month from the end of the 45-day public review period to prepare the Screencheck Final EIR.

This Scope assumes a typical level of public and agency comment on the Draft EIR, including up to 50 unique comment letters. Receipt of an unusually large volume of comments, comment letters of exceptional length or complexity, or comments requiring substantial new environmental analysis, additional technical studies, or extensive revisions to the Draft EIR shall be considered outside the Scope and may require separate work authorization.

Subtask 8.2: Screencheck and Final EIR
The City will provide revisions to FCS based on the Draft Final EIR, and FCS will then revise and provide a Screencheck Final EIR for approval. After the Screencheck Final EIR has been approved, FCS will print and distribute the Final EIR at least three weeks (21 days) prior to the Planning Commission hearing on the project. FCS will deliver all copies of the Final EIR via overnight carrier (for time-sensitive deliveries) and certified US Mail. For budgeting purposes, this Scope assumes distribution to up to 60 recipients via electronic delivery, overnight carrier, or certified US Mail, as directed by the City. Additional recipients may require an amendment to this Scope and fee.

Subtask 8.3: MMRP
As part of the Final EIR preparations, FCS will prepare the MMRP to be appended to the Final EIR. The MMRP will contain all accepted mitigation measures. The MMRP will include, but is not necessarily limited to, the following: project time period to which the measure applies (i.e., during construction, prior to obtaining grading permit, prior to operation, etc.); future review and reporting requirements; responsible party for the cost of mitigation; responsible party for implementing and enforcing mitigation; requirements for monitoring by outside agency; and monitoring and reporting frequency.

EXHIBIT A
Environmental Impact Report for the General Plan Amendment and Zone Change No. 24-0514 16 and Williamson Act Cancelation No. 26-0001 (Taft Highway and Wible Road) City of Bakersfield
DELIVERABLES:
 Electronic copy (via USB flash drive/FTP site/other alternative in Microsoft Word Format) of the Draft Final EIR to the City.  Electronic copy (via USB flash drive/FTP site/other alternative in PDF) of the Screencheck Final EIR to the City.  Electronic copy (via USB flash drive/FTP site/other alternative in PDF) of the Final EIR and MMRP to the City.  Up to 60 hard copies of the Final EIR and MMRP, to the City-provided mailing list via overnight carrier or Certified US Mail.

Task 9: Draft Findings of Fact and Statement of Overriding Considerations Preparation FCS will prepare the draft Findings of Fact and, if necessary, Statement of Overriding Considerations in accordance with Sections 15091 and 15093 of the CEQA Guidelines for the City’s use. FCS assumes one round of review of the draft documents by the City and that the City will finalize these documents in consultation with the City Attorney.

DELIVERABLE:
 Electronic copy (via USB flash drive/FTP site/other alternative in Microsoft Word format) of the draft Findings of Fact and Statement of Overriding Considerations to the City.  Electronic copy (via USB flash drive/FTP site/other alternative in Microsoft Word format) of the updated draft Findings of Fact and Statement of Overriding Considerations to the City.

Task 10: Hearing Attendance
This Scope assumes that FCS’s Project Manager will prepare for and attend up to one Planning Commission hearing and one City Council hearing. A time budget of four hours per meeting (including preparation and coordination) is assumed in addition to travel time. If the City staff requests additional meeting attendance by FCS staff, or if the amount of time involved in these meetings exceeds the initial budget allocation, FCS will notify the City of the additional costs and obtain authorization for the extra meeting time.

If the project is approved and the EIR is certified, the City will be responsible for preparing and filing the Notice of Determination to be filed with the SCH and County Clerk.

DELIVERABLES:
 Attendance at one Planning Commission hearing.
 Attendance at one City Council hearing.

Task 11: Administrative Record Preparation
FCS will provide the City with the Administrative Record within 30 days of the Planning Commission hearing or City Council making a determination about the project. The Administrative Record will include all documents referenced in the EIR and technical appendices.

DELIVERABLE:
 Electronic copy (via USB flash drive/FTP site/other alternative in PDF) Administrative Record to the City.

Task 12: Project Management and Coordination Meetings
In addition to the research, analysis, communication, and report writing tasks described above, FCS will perform a variety of project management duties to ensure that the CEQA document meets City’s standards of quality and that it is delivered on time and within budget. These duties will include team supervision and coordination, oral and written communication with City staff and the applicant, project accounting, and quality assurance review of all deliverable products by FCS’s Project Director. These services will also include ongoing support to City staff, such as regular schedule updates and discussions of technical issues. FCS’s Project Director or Project Manager will attend up to twenty 30-minute coordination meetings with City staff and/or the applicant team. A not-to-exceed budget has been established to cover attendance at these meetings. If City staff requests additional meeting attendance by FCS staff, or if the amount of time involved in these meetings exceeds the initial budget allocation, FCS will notify the City of the additional costs and obtain authorization for the extra meeting time.

EXHIBIT A
Environmental Impact Report for the General Plan Amendment and Zone Change No. 24-0514 17 and Williamson Act Cancelation No. 26-0001 (Taft Highway and Wible Road) City of Bakersfield
Work Schedule
FCS has prepared the following schedule outlining the anticipated timing of each task.

Task Turnaround Time
(Weeks)
Task 1 Kick-off Meeting and Background Review 1
Task 2 Notice of Preparation and Circulation
Subtask 2.1 Notice of Preparation and Initial Study
– Submit Draft NOP and Initial Study Checklist to the City 8 – Receive Comments on NOP and Initial Study 10
– Submit Final NOP and Initial Study Checklist to the City 12 Subtask 2.2 Scoping Meeting Attendance To Be Determined Task 3 Expanded Project Description Preparation 12
Task 4 Applicant-prepared Technical Report Peer Review 10 Task 5 Administrative Draft EIR Preparation
– Submit Administrative Draft EIR to the City 18
– Receive First Round of Comments on Administrative Draft EIR 22 – Resubmit Administrative Draft EIR to the City 25
– Receive Second Round of Comments on Administrative Draft EIR 27 Task 6 Screencheck Draft EIR Preparation
– Submit Screencheck Draft EIR to the City 28
– Receive Comments on Screencheck Draft EIR 30
Task 7 Draft EIR and Technical Appendices Circulation
– Begin 45-day Public Review Period 32
– 45-day Comment Period Ends 38
Task 8 Draft and Screencheck Final EIR and Technical Appendices Preparation and Circulation Subtask 8.1 Draft Final EIR
– Submit Draft Final EIR to the City 42
– Receive Comments on Draft Final EIR 46
Subtask 8.2 Screencheck Final EIR
– Submit Screencheck Final EIR to the City 48
– Receive Comments on Screencheck Final EIR 50
Subtask 8.3 MMRP
– Submit Draft MMRP to the City 48
– Receive Comments on the Draft MMRP 50
– Submit Final EIR and MMRP to the City 52
Task 9 Draft Findings of Fact and Statement of Overriding Considerations Preparation 48 Task 10 Hearing Attendance1 55
Task 11 Administrative Record Preparation 54
Task 12 Project Management and Coordination Meetings Ongoing 1 At least 21 days after the distribution of the FEIR.