INDEPENDENT CONTRACTOR'S AGREEMENT – Over $40,000 Page 1 of 10 \\Sandevsvs\Devsvs\Pln\SHARED\03_Advance Planning\01_Gpas\01_Active\2024\24-0514_10151 Wible Rd\09_EIR PROCESS\01_Contract\Firstcarbonsolutionsconsultantagreement READY.Docx AGREEMENT NO. ___________________
INDEPENDENT CONTRACTOR'S AGREEMENT
This INDEPENDENT CONTRACTOR’S AGREEMENT (“Agreement”) is made and entered into on _______________________, by and between the CITY OF BAKERSFIELD, a municipal corporation (referred to herein as “CITY”), and FIRSTCARBON SOLUTIONS INTERNATIONAL, INC., doing business as FIRSTCARBON SOLUTIONS (FCS), a Corporation authorized to do business in California (referred to herein as “CONSULTANT”).
R E C I T A L S
WHEREAS, CONSULTANT represents that CONSULTANT is experienced, well qualified and a specialist in the field of environmental compliance and processing per the California Environmental Quality Act (CEQA); and WHEREAS, CONSULTANT also represents that it has an adequate number of experienced employees on its staff to accomplish the scope of work, as defined below, and that it is competent to undertake the Scope of Work.
NOW, THEREFORE, incorporating the foregoing recitals herein, CITY and CONSULTANT mutually agree as follows:
1. SCOPE OF WORK. In exchange for the Compensation (defined below), CONSULTANT shall perform the attached scope of work presented in Exhibit “A” (“Scope of Work”). The Scope of Work shown in Exhibit “A” shall include all items and procedures necessary to properly complete the task CONSULTANT has been hired to perform, whether specifically included in the Scope of Work or not.
2. COMPENSATION/PAYMENT PROCEDURE. Subject to the conditions of this section, CITY will pay CONSULTANT as follows for performing the Scope of Work (“Compensation”): On a time/material basis in accordance with the hourly rates as shown on Exhibit B.
CITY will pay CONSULTANT within 30 days after CONSULTANT submits an itemized invoice for the portions of the Scope of Work completed and that invoice is approved by CITY. The Compensation will be the total amount paid to CONSULTANT for performing the Scope of Work and includes, but is INDEPENDENT CONTRACTOR'S AGREEMENT – Over $40,000 Page 2 of 10 \\Sandevsvs\Devsvs\Pln\SHARED\03_Advance Planning\01_Gpas\01_Active\2024\24-0514_10151 Wible Rd\09_EIR PROCESS\01_Contract\Firstcarbonsolutionsconsultantagreement READY.Docx not limited to, all out-of-pocket costs and taxes. CITY will pay no other compensation to CONSULTANT. In no case will CITY compensate CONSULTANT more than $276,787.00 for performing the Scope of Work.
3. TERM. Unless terminated sooner, as set forth herein, this Agreement shall terminate two years from its date of execution.
4. TERMINATION. Either party may terminate this Agreement after giving the other party written notice, as provided herein, ten days before the termination is effective.
5. COMPLIANCE WITH ALL LAWS. CONSULTANT shall, at CONSULTANT’s sole cost, comply with all of the requirements of Municipal, State, and Federal authorities now in force, or which may hereafter be in force, pertaining to this Agreement, and shall faithfully observe in all activities relating to or growing out of this Agreement all Municipal ordinances and State and Federal statutes, rules or regulations, and permitting requirements now in force or which may hereafter be in force including, without limitation, obtaining a City of Bakersfield business tax certificate (Bakersfield Municipal Code Chapter 5.02) where required.
6. INDEPENDENT CONTRACTOR. This Agreement calls for CONSULTANT’s performance of the Scope of Work as an independent contractor.
CONSULTANT is not an agent or employee of the CITY for any purpose and is not entitled to any of the benefits provided by CITY to its employees. This Agreement shall not be construed as forming a partnership or any other association with CONSULTANT other than that of an independent contractor.
7. DIRECTION. CONSULTANT retains the right to control or direct the manner in which the services described herein are performed.
8. EQUIPMENT. CONSULTANT will supply all equipment, tools, materials and supplies necessary to perform the services under this Agreement.
9. STARTING WORK. CONSULTANT shall not begin work until authorized to do so in writing by CITY. No work will be authorized before the date first written above.
10. KEY PERSONNEL. CONSULTANT shall name all key personnel to be assigned to perform the Scope of Work. All key personnel shall be properly licensed and have the experience to perform the work called for under this Agreement. CONSULTANT shall provide background for each of the key personnel including, without limitation, resumes and work experience INDEPENDENT CONTRACTOR'S AGREEMENT – Over $40,000 Page 3 of 10 \\Sandevsvs\Devsvs\Pln\SHARED\03_Advance Planning\01_Gpas\01_Active\2024\24-0514_10151 Wible Rd\09_EIR PROCESS\01_Contract\Firstcarbonsolutionsconsultantagreement READY.Docx performing work similar to the Scope of Work. CITY reserves the right to approve key personnel. Once the key personnel are approved, CONSULTANT shall not change such personnel without CITY’s written approval.
11. INCLUDED DOCUMENTS. Any bid documents, including, without limitation, special provisions and standard specifications and any Request for Proposals, Request for Qualifications and responses thereto relating to this Agreement are incorporated by reference as though fully set forth herein.
12. LICENSES. CONSULTANT shall, at its sole cost and expense, keep in effect or obtain at all times during the term of this Agreement any licenses, permits and approvals which are legally required for CONSULTANT to practice its profession and perform the Scope of Work. If CONSULTANT is a corporation, at least one officer or key employee shall hold the required licenses or professional degrees. If CONSULTANT is a partnership, at least one partner shall hold the required licensees or professional degrees.
13. STANDARD OF PERFORMANCE. The Scope of Work shall be performed in conformity with all legal requirements and industry standards observed by a specialist of CONSULTANT’s profession in California.
14. SB 854 COMPLIANCE. To the extent Labor Code Section 1771.1 applies to this Agreement, a contractor or subcontractor shall not be qualified to bid on, be listed in a bid proposal, be subject to the requirements of Section 4104 of the Public Contract Code, or engage in the performance of any contract for public work, as defined in this chapter, unless currently registered and qualified to perform public work pursuant to Section 1725.5.
It is not a violation of Labor Code Section 1771.1 for an unregistered contractor to submit a bid that is authorized by Section 7029.1 of the Business and Professions Code or by Section 10164 or 20103.5 of the Public Contract Code, provided the contractor is registered to perform public work pursuant to Section 1725.5 at the time the contract is awarded. The prime contractor is required to post job site notices in compliance with Title 8 California Code of Regulations Section 16451. This project is subject to compliance monitoring and enforcement by the Department of Industrial Relations.
15. NO WAIVER OF DEFAULT. The failure of any party to enforce against another party any provision of this Agreement shall not constitute a waiver of that party's right to enforce such a provision at a later time and shall not serve to vary the terms of this Agreement.
INDEPENDENT CONTRACTOR'S AGREEMENT – Over $40,000 Page 4 of 10 \\Sandevsvs\Devsvs\Pln\SHARED\03_Advance Planning\01_Gpas\01_Active\2024\24-0514_10151 Wible Rd\09_EIR PROCESS\01_Contract\Firstcarbonsolutionsconsultantagreement READY.Docx
16. INSURANCE.
16.1 Types and Limits of Insurance. In addition to any other insurance or security required under this Agreement, CONSULTANT must procure and maintain, for the duration of this Agreement, the types and limits of insurance below ("Basic Insurance Requirements").
16.1.1 Automobile liability insurance, providing coverage for owned, non-owned, and hired autos on an occurrence
basis for bodily injury, including death, of one or more persons, property damage, and personal injury, with limits of not less than $1,000,000 per occurrence.
16.1.2 Commercial general liability insurance, unless otherwise approved by CITY’s Risk Manager, providing coverage on
an occurrence basis for bodily injury, including death, of one or more persons, property damage, and personal
injury, with limits of not less than $1,000,000 per occurrence.
The policy must:
16.1.2.1 Provide contractual liability coverage for the terms of this Agreement;
16.1.2.2 Provide products and completed operations
coverage;
16.1.2.3 Provide premises, operations, and mobile
equipment coverage; and
16.1.2.4 Contain an additional insured endorsement in
favor of CITY and its mayor, council, officers,
agents, employees, and designated volunteers.
16.1.3 Workers' compensation insurance with limits of not less than $1,000,000 per occurrence. In accordance with the
provisions of Labor Code Section 3700, every contractor will be required to secure the payment of compensation to his employees. Pursuant to Labor Code Section 1861,
CONSULTANT must submit to CITY the following certification before beginning any work on the Improvements:
I am aware of the provisions of Section 3700 of the
Labor Code which require every employer to be
INDEPENDENT CONTRACTOR'S AGREEMENT – Over $40,000 Page 5 of 10 \\Sandevsvs\Devsvs\Pln\SHARED\03_Advance Planning\01_Gpas\01_Active\2024\24-0514_10151 Wible Rd\09_EIR PROCESS\01_Contract\Firstcarbonsolutionsconsultantagreement READY.Docx insured against liability for worker’s compensation or
to undertake self-insurance in accordance with the
provisions of that code, and I will comply with such
provisions before commencing the performance of
the work of this contract.
By executing this Agreement, CONSULTANT is submitting the certification required above.
The policy must contain a waiver of subrogation in favor of CITY and its mayor, council, officers, agents, employees, and designated volunteers.
16.2 General Provisions Applying to All Insurance Types.
16.2.1 All policies required of CONSULTANT must be written on a first-dollar coverage basis, or contain a deductible
provision. Subject to CITY’s advance approval,
CONSULTANT may utilize a self-insured retention in any or all of the policies provided, but the policy or policies may not contain language, whether added by endorsement or
contained in the policy conditions, that prohibits
satisfaction of any self-insured provision or requirement by anyone other than the named insured or by any means
including other insurance or which is intended to defeat the intent or protection of an additional insured.
16.2.2 All policies required of CONSULTANT must be primary insurance as to CITY and its mayor, council, officers, agents, employees, or designated volunteers and any insurance or self-insurance maintained by CITY and its mayor, council, officers, agents, employees, and designated volunteers
must be excess of CONSULTANT’s insurance and must not
contribute with it.
16.2.3 The insurance required above, except for workers’ compensation insurance, must be placed with insurers with a Best’s rating as approved by CITY’s Risk Manager, but in no event less than A-:VII. Any deductibles, self-insured retentions, or insurance in lesser amounts, or lack of certain types of insurance otherwise required by this Agreement, or insurance rated below Best’s A-:VII, must be declared prior to execution of this Agreement and approved by CITY in
writing.
INDEPENDENT CONTRACTOR'S AGREEMENT – Over $40,000 Page 6 of 10 \\Sandevsvs\Devsvs\Pln\SHARED\03_Advance Planning\01_Gpas\01_Active\2024\24-0514_10151 Wible Rd\09_EIR PROCESS\01_Contract\Firstcarbonsolutionsconsultantagreement READY.Docx
16.2.4 The insurance required in this section must be maintained until the Scope of Work is satisfactorily completed as
evidenced by CITY’s written acceptance. All policies must provide that there will be continuing liability thereon, notwithstanding any recovery on any policy.
16.2.5 Full compensation for all premiums which the CONSULTANT is required to pay to satisfy the Basic Insurance
Requirements shall be considered as included in the prices paid for the performance of the Scope of Work, and no
additional allowance will be made therefor or for additional premiums which may be required by extensions of the
policies of insurance.
16.2.6 It is further understood and agreed by CONSULTANT that its liability to CITY will not in any way be limited to or affected by the amount of insurance obtained and carried by
CONSULTANT in connection with this Agreement.
16.2.7 Unless otherwise approved by CITY, if any part of the Scope of Work is subcontracted, the Basic Insurance Requirements must be provided by, or on behalf of, all subcontractors even if CITY has approved lesser insurance requirements for CONSULTANT, and all subcontractors must agree in writing to be bound by the provisions of this section.
17. THIRD PARTY CLAIMS. In the case of public works contracts, CITY will timely notify CONSULTANT of third party claims relating to this Agreement. CITY shall be allowed to recover from CONSULTANT, and CONSULTANT shall pay on demand, all costs of notification.
18. MUTUAL HOLD HARMLESS. Neither party shall be liable to the other party for any loss, damage, liability, claim or cause of action arising solely from any act or omission of the other party's officers, agents or employees. Subject to California Civil Code section 2782.8, CITY and CONSULTANT agree to hold each other harmless from any and all claims, demands, liabilities, losses or causes of action which arise by virtue of its own acts or omissions (either directly or through or by its agents, officers or employees) to such extent and in such part as the respective parties are found by reason of law to have proximately caused the injury or damage. The party against whom any claim arising from any subject matter of this Agreement is filed shall give prompt notice of the filing of the claim to the other party.
INDEPENDENT CONTRACTOR'S AGREEMENT – Over $40,000 Page 7 of 10 \\Sandevsvs\Devsvs\Pln\SHARED\03_Advance Planning\01_Gpas\01_Active\2024\24-0514_10151 Wible Rd\09_EIR PROCESS\01_Contract\Firstcarbonsolutionsconsultantagreement READY.Docx
19. ASSIGNMENT. Neither this Agreement nor any rights, interests, duties, liabilities, obligations or responsibilities arising out of, concerning or related in any way to this Agreement (including, but not limited to, accounts, actions, causes of action, claims, damages, demands, liabilities, losses, obligations, or reckonings of any kind or nature whatsoever, for compensatory or exemplary and punitive damages, or declaratory, equitable or injunctive relief, whether based on contract, equity, tort or other theories of recovery provided for by the common or statutory law) may be assigned or transferred by any party. Any such assignment is prohibited, and shall be unenforceable and otherwise null and void without the need for further action by the non-assigning party or parties.
20. ACCOUNTING RECORDS. CONSULTANT shall maintain accurate accounting records and other written documentation pertaining to all costs incurred in performance of this Agreement. Such records and documentation shall be kept at CONSULTANT's office during the term of this Agreement, and for a period of three years from the date of the final payment hereunder, and made available to CITY representatives upon request at any time during regular business hours.
21. BINDING EFFECT. The rights and obligations of this Agreement shall inure to the benefit of, and be binding upon, the parties to the Agreement and their heirs, administrators, executors, personal representatives, successors and assigns.
22. CORPORATE AUTHORITY. Each individual signing this Agreement on behalf of entities represents and warrants that they are, respectively, duly authorized to sign on behalf of the entities and to bind the entities fully to each and all of the obligations set forth in this Agreement.
23. COUNTERPARTS. This Agreement may be executed in any number of counterparts, each of which shall be considered as an original and be effective as such.
24. EXECUTION. This Agreement is effective upon execution. It is the product of negotiation and all parties are equally responsible for authorship of this Agreement. Section 1654 of the California Civil Code shall not apply to the interpretation of this Agreement.
25. EXHIBITS. In the event of a conflict between the terms, conditions or specifications set forth in this Agreement and those in exhibits attached hereto, the terms, conditions, or specifications set forth in this Agreement shall prevail. All exhibits to which reference is made in this Agreement are INDEPENDENT CONTRACTOR'S AGREEMENT – Over $40,000 Page 8 of 10 \\Sandevsvs\Devsvs\Pln\SHARED\03_Advance Planning\01_Gpas\01_Active\2024\24-0514_10151 Wible Rd\09_EIR PROCESS\01_Contract\Firstcarbonsolutionsconsultantagreement READY.Docx deemed incorporated in this Agreement, whether or not actually attached.
26. FURTHER ASSURANCES. Each party shall execute and deliver such papers, documents, and instruments, and perform such acts as are necessary or appropriate, to implement the terms of this Agreement and the intent of the parties to this Agreement.
27. GOVERNING LAW. The laws of the State of California will govern the validity of this Agreement and its interpretation and performance. Any litigation arising in any way from this Agreement shall be brought in Kern County, California.
28. INTERPRETATION. Whenever the context so requires, the masculine gender includes the feminine and neuter, and the singular number includes the plural.
29. MERGER AND MODIFICATION. This Agreement sets forth the entire agreement between the parties and supersedes all other oral or written representations. This Agreement may be modified only in a writing approved by the City Council and signed by all the parties.
30. NON-INTEREST. No CITY officer or employee shall hold any interest in this Agreement (California Government Code section 1090).
31. NOTICES. All notices relative to this Agreement shall be given in writing and shall be personally served or sent by certified or registered mail and be effective upon actual personal service or depositing in the United States mail. The parties shall be addressed as follows, or at any other address designated by notice:
CITY: CITY OF BAKERSFIELD
CITY HALL
1600 Truxtun Avenue
Bakersfield, California 93301
CONSULTANT: FirstCarbon Solutions
250 Commerce, Suite 210
Irvine, CA 92602
(714) 508-4100
INDEPENDENT CONTRACTOR'S AGREEMENT – Over $40,000 Page 9 of 10 \\Sandevsvs\Devsvs\Pln\SHARED\03_Advance Planning\01_Gpas\01_Active\2024\24-0514_10151 Wible Rd\09_EIR PROCESS\01_Contract\Firstcarbonsolutionsconsultantagreement READY.Docx
32. RESOURCE ALLOCATION. All CITY obligations under the terms of this Agreement are subject to the appropriation and allocation of resources by the City Council.
33. TITLE TO DOCUMENTS. All documents, plans, and drawings, maps, photographs, and other papers, or copies thereof prepared by CONSULTANT pursuant to the terms of this Agreement, shall, upon preparation, become CITY property.
34. TAX NUMBERS.
CONSULTANT’s Federal Tax ID Number 95-3782289
CONSULTANT is a corporation? Yes X No (Please check one.) IN WITNESS WHEREOF, the parties hereto have caused this Agreement to be executed as of the date first written above.
"CITY" “CONSULTANT”
CITY OF BAKERSFIELD FIRSTCARBON SOLUTIONS
By:________________________________ By:_________________________________
KAREN GOH JASON BRANDMAN
Mayor Sr. Vice President
APPROVED AS TO CONTENT:
DEVELOPMENT SERVICES DEPARTMENT
By:_______________________________
PHILLIP BURNS
Development Services Director
[Signatures on Following Page]
By:_________________________________
C. PATRICK SCHULTZ
COO
INDEPENDENT CONTRACTOR'S AGREEMENT – Over $40,000 Page 10 of 10 \\Sandevsvs\Devsvs\Pln\SHARED\03_Advance Planning\01_Gpas\01_Active\2024\24-0514_10151 Wible Rd\09_EIR PROCESS\01_Contract\Firstcarbonsolutionsconsultantagreement READY.Docx APPROVED AS TO FORM:
VIRGINIA GENNARO
City Attorney
By:___________________________
VIRIDIANA GALLARDO-KING
Deputy City Attorney II
Insurance:____________
COUNTERSIGNED:
By:_______________________________
RANDY MCKEEGAN
Finance Director
Attachment: Exhibit A – Scope of Work
Exhibit B – Compensation/Payment Procedure
Environmental Impact Report for the General Plan Amendment and Zone Change No. 24-0514 11 and Williamson Act Cancelation No. 26-0001 (Taft Highway and Wible Road) City of Bakersfield
Project Approach and Work Schedule
Project Understanding
FCS understands that the City is seeking a qualified consultant to prepare an EIR in compliance with CEQA for the General Plan Amendment (GPA) and Zone Change No. 24-0514, including the associated Williamson Act Cancellation No. 26-0001. The EIR will serve as the environmental document supporting the City’s review and consideration of the proposed land use and zoning changes, which will ultimately be evaluated by the Bakersfield Planning Commission and considered for final approval by the Bakersfield City Council. The approximately 118-acre site is located at 10161 Wible Road, situated at the southwest corner of Wible Road and Taft Highway (State Route 119). FCS understands and is prepared to start work within three weeks of the City’s authorization to proceed and will complete work within the allotted time specified in the Professional Services Agreement.
Cornerstone Engineering, Inc. (applicant) is proposing to convert the existing agricultural land to a mixed-use development consisting of residential neighborhoods of varying densities and supporting commercial uses. The requested GPA would change the land use designation from a Resource-Intensive Agriculture designation to a combination of Low Density Residential, Low Medium Density Residential, High Medium Density Residential, and General Commercial. Corresponding zoning changes are proposed from Agricultural zoning to Single-unit Dwelling, Small Lot Single-unit Dwelling, Medium Density Multi-unit Dwelling, and Regional Commercial. The proposed residential development is anticipated to include approximately 78 residential duplexes totaling 156 residential units, 240 low-rise apartments including a recreation center, 356 single-family homes and approximately 150,000 square feet of commercial development.
The proposed project site consists of two contiguous agricultural parcels (Assessor’s Parcel Numbers 184-200-14 and 184-200-15) that are currently used for agricultural production, primarily almond cultivation, and contain two existing single-family residences. The project site is presently under a Williamson Act contract; however, a Williamson Act Contract Cancellation request (WAC 26-0001) has been submitted by the property owner. Adjacent land uses consist of vacant commercial land to the north, a convenience store and fuel station with nearby farmland to the east, and agricultural properties to the west and south.
FCS’s overall approach to the preparation of the EIR will ensure that the environmental documents and studies fulfill the requirements of the City and meet the analysis standards required under CEQA. Our approach to preparing EIRs has been developed through 43 years of experience working with cities and counties in California to prepare thoughtful, defensible environmental documents in a timely manner.
Scope of Work
The following tasks are proposed to complete the identified Scope of Work (Scope) for the City’s project:
Task 1: Kick-off Meeting and Background Review
FCS will review relevant background material, develop an initial data needs list, and coordinate with the City to schedule a kick-off meeting (it is anticipated that the kick-off meeting will be completed via teleconference). The intent of the kick-off meeting is to clarify and confirm the details of the Scope and schedule, obtain copies of the project plans and other relevant information, identify key points of contact, establish communication protocols and expectations, and discuss the project's objectives, which will help inform the development and evaluation of project alternatives in the EIR. It is typically helpful to have all relevant team members attend this call (i.e., applicant, civil engineering design team, and general contractor, if applicable). FCS will provide the City and the applicant with a kick-off meeting agenda, followed by a memorandum that summarizes the meeting, including agreed-upon action items, timing of the items, and who is responsible for completing each item.
Following the kick-off meeting, FCS will mobilize and review relevant background documents provided by the City and applicant, as well as other available information pertinent to the project, to ensure project understanding. While reviewing this information, FCS will also provide a Request for Information (RFI), which will detail additional information needed to complete the EIR. FCS will also provide a full project schedule organized by task/milestone spanning from the kick-off meeting through Final EIR consideration by the City Planning Commission and, upon final approval by the City Council.
DELIVERABLES:
Electronic copy (via File Transfer Protocol [FTP] site in Microsoft Word format and PDF) of the kick-off meeting agenda to the City.
Electronic copy (via FTP site in Microsoft Word format and PDF) of the kick-off meeting memorandum to the City.
E X HIBIT A
Environmental Impact Report for the General Plan Amendment and Zone Change No. 24-0514 12 and Williamson Act Cancelation No. 26-0001 (Taft Highway and Wible Road) City of Bakersfield
Electronic copy (via FTP site in Microsoft Word format and PDF) of the information needs list (as needed) to the City. Electronic copy (via FTP site in Microsoft Word format and PDF) of the full project schedule organized by task/milestone to the City.
Task 2: Notice of Preparation and Circulation
Subtask 2.1: Notice of Preparation and Initial Study
FCS will prepare an Initial Study checklist for the proposed project. This task includes effort required to complete the checklist, associated research, and coordination amongst FCS staff and the City. FCS will utilize the applicant-prepared studies in support of the Initial Study:
Air Quality/Climate Change Analysis/Health Risk
Assessment (HRA)
Biological Resources Study
Archaeological/Cultural Resources Study
Traffic Impact Study (including VMT analysis)
Water Will-Serve or Availability Letter
Water Supply Assessment
Phase I ESA (at a minimum)
Acoustical Analysis
Agricultural Conversion Study
The Initial Study format will include separate sections for discussion of each CEQA Guidelines Appendix G Environmental Checklist impact category, and it will be adequately supported by figures (including color GIS mapping, as appropriate). The Initial Study will evaluate project impacts against each question on the Appendix G Environmental Checklist and determine whether a potentially significant impact could occur that requires mitigation or if impacts would be less than significant and would not require mitigation. FCS will submit the Draft Initial Study to the City for review. It is assumed that the City will coordinate review and will provide one set of consolidated, vetted comments (with tracked changes in the Word document) on the Draft Initial Study to FCS within two weeks of submittal.
FCS will prepare the Administrative draft NOP and associated documents, including an Initial Study, prepare the Final NOP for public distribution in electronic format, and submit the Final NOP and Notice of Completion (NOC) electronically to the State Clearinghouse (SCH). FCS will distribute the NOP and accompanying cover letter to agencies and interested parties identified on a mailing list provided by the City. For budgeting purposes, this Scope assumes distribution to up to 60 recipients via electronic delivery, overnight carrier, or certified US Mail, as directed by the City.
Additional recipients may require an amendment to this Scope and fee. FCS will attend the City’s Scoping Meeting during the 30-day public review period.
FCS will review and assess all comments received during the NOP review period and will prepare responses to those comments for inclusion in the Draft EIR. Responses will be coordinated with the City and incorporated, as appropriate, into the environmental analysis, project description, and other relevant sections of the Draft EIR.
DELIVERABLES:
Electronic copy (via USB flash drive/FTP site/other alternative in Microsoft Word format and PDF) of the Final NOP and NOC to SCH.
Electronic copy (via one USB/flash drive in Microsoft Word format and PDF) of the Final NOP, set of NOP figures, and all documents cited in the Final NOP to the City.
Two hard copies of the Final NOP to the City.
Up to 60 to be mailed via certified US mail of the Final NOP to the City-provided mailing list. FCS attendance at City’s Scoping Meeting.
Subtask 2.2: Scoping Meeting Attendance
FCS will attend the City’s Scoping Meeting during the 30-day public review period and will assess all comments received on the NOP and prepare responses through the Draft EIR. It is assumed that the City will be responsible for conducting the Scoping Meeting.
Task 3: Expanded Project Description Preparation
FCS will augment the NOP project description with the most current information and comments from the NOP public review period (discussed in Task 2 above) and develop an expanded draft project description. FCS will conduct a field reconnaissance of the project site and surrounding area to get a better understanding of the site in anticipation of preparing the expanded project description. FCS will review the applicant-provided technical reports (discussed in Task 4 below) to enhance our understanding of the existing project setting and will supplement our review with in-house
EXHIBIT A
Environmental Impact Report for the General Plan Amendment and Zone Change No. 24-0514 13 and Williamson Act Cancelation No. 26-0001 (Taft Highway and Wible Road) City of Bakersfield
resources and additional research. FCS will prepare and submit an RFI memorandum (if necessary) to the City to further refine and clarify the Project Description (discussed above in Task 1). FCS will then use the information from field reconnaissance, technical reports, in-house resources, additional research, and other provided information to prepare a project description (within 60 days of the authorization to proceed) to be used for the subsequent environmental documentation.
The Project Description will include a detailed narrative of the project components, with graphics and maps to highlight the project location, project elements, current land-use designations and zoning classifications, and surroundings. As discussed in Task 1, FCS will work closely with the City and the applicant to develop an agreed-upon list of project objectives. FCS assumes one round of review of the administrative draft Project Description and a two-week review period for City review.
DELIVERABLES:
Electronic copy (via USB flash drive/FTP site/other alternative in Microsoft Word format) of the Administrative draft Project Description to the City.
Electronic copy (via USB flash drive/FTP site/other alternative in Microsoft Word format) of the Draft Project Description to the City.
Task 4: Applicant-prepared Technical Report Peer Review FCS will peer review the technical studies provided by the applicant to verify their completeness accuracy for purposes of CEQA; ensure consistency with the City’s General Plan and Development Code; ensure compliance with all applicable environmental laws, regulations, rules, and requirements; and ensure legal defensibility and accuracy in the representation of project-related information from the City.
FCS’s team of in-house experts includes a Senior Vice President, Senior Biologist, Director of Cultural Resources, Director of Noise and Air Quality Services, Project Managers, and expert in-house legal counsel. Our teaming partners, Cameron-Cole, P&P, and West Yost will peer review the Phase I ESA, Traffic Impact Study (including VMT analysis), and Water Will-Serve/Availability Letter and Water Supply Assessment, respectively.
The team will perform a thorough review of study methodology, modeling, calculations, findings, and results to identify inaccuracies, inconsistencies, or incompleteness, with a focus on ensuring the studies are legally defensible and adequate for purposes of CEQA. FCS will conduct a review and prepare a peer review memorandum for each technical report to make the City aware of concerns associated with CEQA adequacy and to provide feedback that a report is sufficient for the purposes of the CEQA analysis. Any additional analysis (including site visit) would be addressed in a separate scope and fee. The following technical studies will be peer reviewed:
1. Air Quality/Climate Change Analysis/HRA
2. Biological Resources Study
3. Archaeological/Cultural Resources Study
4. Traffic Impact Study (including VMT analysis)
5. Water Will-Serve or Availability Letter
6. Water Supply Assessment
7. Phase I ESA (at a minimum)
8. Acoustical Analysis
9. Agricultural Conversion Study
Following the City’s initial review, it is assumed that the applicant will revise the technical reports as necessary to address comments, and that only one subsequent review for confirmation of adequacy will be required. Should additional rounds of revisions be necessary, a separate work authorization will be required.
DELIVERABLE:
Electronic copy (via USB flash drive/FTP site/other alternative in PDF) of the technical report sufficiency memoranda for each of the above-listed technical studies to the City.
Task 5: Administrative Draft EIR Preparation
FCS will prepare the Administrative Draft EIR in accordance with the City’s CEQA Implementation Procedures. The project will be analyzed at the project level, providing sufficient study to conclude that additional CEQA compliance will not be required if the City’s decision-making bodies approve the project and certify the EIR. The Administrative Draft EIR will include all the required contents per CEQA and will include a detailed inventory of existing conditions, thresholds of significance used for the evaluation of impacts, and an analysis of the environmental impacts and levels of significance. Appropriate mitigation measures will be provided for potential impacts identified in each environmental issue area shown in the City’s Initial Study Environmental Analysis checklist (i.e., Aesthetics, Agriculture and Forest Resources, Air Quality, etc.) for which a potentially significant impact may occur.
EXHIBIT A
Environmental Impact Report for the General Plan Amendment and Zone Change No. 24-0514 14 and Williamson Act Cancelation No. 26-0001 (Taft Highway and Wible Road) City of Bakersfield
FCS assumes that two rounds of review of the Administrative Draft EIR by the City and 20 days for our review of the City changes will be required, with an estimated target date of six to eight months to get the Draft EIR circulated from the time FCS is awarded the contract. FCS will provide revisions to the Administrative Draft EIR in underline/strikeout format.
Technical Issues
The EIR will focus on the potentially significant environmental impacts identified in the NOP.
Alternatives
FCS will work closely with the City to identify and screen a reasonable range of alternatives for analysis in the EIR.
These alternatives will be based on our ability to feasibly attain most of the project objectives while avoiding or substantially lessening any of the significant environmental impacts of the project. As allowed by CEQA, the alternatives will be analyzed at a reduced level of detail in comparison to the project.
Consequences of Project Implementation
Cumulative Impacts: FCS will prepare a cumulative impacts analysis, which will focus on the potential for environmental impacts from this project, along with other proposed and reasonably foreseeable projects in the area.
The list of cumulative projects will be developed in coordination with the City. The project’s contribution to the overall cumulative baseline will be evaluated and “cumulatively considerable” impacts will be identified. Mitigation measures will be developed for any cumulatively considerable impacts, if applicable and feasible. Growth-inducing Impacts: As required by CEQA, the EIR will evaluate whether the project has the potential to directly or indirectly foster economic or population growth. This analysis will include an assessment of whether the project would directly contribute to growth or remove obstacles to population growth, such as through the extension of infrastructure. The City will evaluate whether any projected increase in population as a result of the project would result in additional impacts to existing community resources or encourage and facilitate other activities that could significantly affect the environment.
Significant Irreversible Environmental Changes: FCS will summarize the significant and unavoidable impacts resulting from the project and will identify any significant irreversible changes and irretrievable commitments of the environment. This will include a discussion of nonrenewable resources, permanent conversion of land uses, improvements to areas previously inaccessible, and other factors that would commit future generations to similar environmental impacts.
Effects Found Not To Be Significant: FCS will provide a qualitative explanation of issues found not to be significant during the NOP process as well as impacts that were studied in the EIR and determined to be less than significant.
Organizations and Persons Consulted
FCS will prepare this section to document any federal, State, or local agencies, other organizations and private individuals consulted in preparing the EIR.
Preparers
FCS will prepare this section to document all preparers of the EIR and their contribution.
Acronyms
FCS will prepare this section to define all acronyms used in the EIR.
Bibliography
FCS will prepare this section to Modern Language Association or Chicago Manual of Style standards and include all personal communications. FCS will also keep electronic copies of all reference materials for the administrative record (see Task 11).
DELIVERABLES:
Electronic copy (via USB flash drive/FTP site/other alternative in Microsoft Word File) of the Administrative Draft EIR to the City.
Electronic copy (via USB flash drive/FTP site/other alternative in Microsoft Word File) of the Revised Administrative Draft EIR to the City.
EXHIBIT A
Environmental Impact Report for the General Plan Amendment and Zone Change No. 24-0514 15 and Williamson Act Cancelation No. 26-0001 (Taft Highway and Wible Road) City of Bakersfield
Task 6: Screencheck Draft EIR Preparation
After the two rounds of review of the Administrative Draft EIR, FCS will then revise and prepare a Screencheck Draft EIR and technical appendices for approval by the City within two weeks of receiving comments from the City, before distributing the Draft EIR for the required 45-day public review period.
DELIVERABLE:
Electronic copy (via USB flash drive/FTP site/other alternative in PDF) of the Screencheck Draft EIR to the City.
Task 7: Draft EIR and Technical Appendices Circulation
Following approval of the Screencheck Draft EIR, FCS will prepare, print (as needed), and distribute the Draft EIR (with appendices on USB flash drive). FCS will submit the Draft EIR and NOC to SCH following in accordance with current electronic filing requirements and will coordinate circulation of the Notice of Availability (NOA) and Draft EIR to agencies, organizations, and interested parties included on the City-provided mailing list. For budgeting purposes, this Scope assumes distribution to up to 60 recipients via electronic delivery, overnight carrier, or certified US Mail, as directed by the City. Additional recipients may require an amendment to this Scope and fee.
DELIVERABLES:
Electronic Copy (via CEQAnet) of the Draft EIR and appendices, NOC, NOA, and Governor’s Office of Land Use and Climate Innovation Summary Form to the SCH.
Electronic copy (via USB flash drive/FTP site/other alternative in PDF) of the Draft EIR (including PDF, Microsoft Word versions, and figures) and NOC to the City.
Up to 60 electronic copies to be emailed of the NOA, to the City-provided mailing list. Five hard copies of the Draft EIR (with Draft EIR and appendices on USB flash drive) to the City. Two hard copies of the Draft EIR including tabbed technical appendices to the City.
Task 8: Draft and Screencheck Final EIR and Technical Appendices Preparation and Circulation
Subtask 8.1: Draft Final EIR
FCS will prepare the Draft Final EIR based on comments received during the 45-day public review period. FCS will evaluate and annotate comments received and prepare written responses to all comments as required by CEQA. FCS assumes that only one round of review of the Draft Final EIR by the City will suffice, and that it will take FCS approximately one month from the end of the 45-day public review period to prepare the Screencheck Final EIR.
This Scope assumes a typical level of public and agency comment on the Draft EIR, including up to 50 unique comment letters. Receipt of an unusually large volume of comments, comment letters of exceptional length or complexity, or comments requiring substantial new environmental analysis, additional technical studies, or extensive revisions to the Draft EIR shall be considered outside the Scope and may require separate work authorization.
Subtask 8.2: Screencheck and Final EIR
The City will provide revisions to FCS based on the Draft Final EIR, and FCS will then revise and provide a Screencheck Final EIR for approval. After the Screencheck Final EIR has been approved, FCS will print and distribute the Final EIR at least three weeks (21 days) prior to the Planning Commission hearing on the project. FCS will deliver all copies of the Final EIR via overnight carrier (for time-sensitive deliveries) and certified US Mail. For budgeting purposes, this Scope assumes distribution to up to 60 recipients via electronic delivery, overnight carrier, or certified US Mail, as directed by the City. Additional recipients may require an amendment to this Scope and fee.
Subtask 8.3: MMRP
As part of the Final EIR preparations, FCS will prepare the MMRP to be appended to the Final EIR. The MMRP will contain all accepted mitigation measures. The MMRP will include, but is not necessarily limited to, the following: project time period to which the measure applies (i.e., during construction, prior to obtaining grading permit, prior to operation, etc.); future review and reporting requirements; responsible party for the cost of mitigation; responsible party for implementing and enforcing mitigation; requirements for monitoring by outside agency; and monitoring and reporting frequency.
EXHIBIT A
Environmental Impact Report for the General Plan Amendment and Zone Change No. 24-0514 16 and Williamson Act Cancelation No. 26-0001 (Taft Highway and Wible Road) City of Bakersfield
DELIVERABLES:
Electronic copy (via USB flash drive/FTP site/other alternative in Microsoft Word Format) of the Draft Final EIR to the City. Electronic copy (via USB flash drive/FTP site/other alternative in PDF) of the Screencheck Final EIR to the City. Electronic copy (via USB flash drive/FTP site/other alternative in PDF) of the Final EIR and MMRP to the City. Up to 60 hard copies of the Final EIR and MMRP, to the City-provided mailing list via overnight carrier or Certified US Mail.
Task 9: Draft Findings of Fact and Statement of Overriding Considerations Preparation FCS will prepare the draft Findings of Fact and, if necessary, Statement of Overriding Considerations in accordance with Sections 15091 and 15093 of the CEQA Guidelines for the City’s use. FCS assumes one round of review of the draft documents by the City and that the City will finalize these documents in consultation with the City Attorney.
DELIVERABLE:
Electronic copy (via USB flash drive/FTP site/other alternative in Microsoft Word format) of the draft Findings of Fact and Statement of Overriding Considerations to the City. Electronic copy (via USB flash drive/FTP site/other alternative in Microsoft Word format) of the updated draft Findings of Fact and Statement of Overriding Considerations to the City.
Task 10: Hearing Attendance
This Scope assumes that FCS’s Project Manager will prepare for and attend up to one Planning Commission hearing and one City Council hearing. A time budget of four hours per meeting (including preparation and coordination) is assumed in addition to travel time. If the City staff requests additional meeting attendance by FCS staff, or if the amount of time involved in these meetings exceeds the initial budget allocation, FCS will notify the City of the additional costs and obtain authorization for the extra meeting time.
If the project is approved and the EIR is certified, the City will be responsible for preparing and filing the Notice of Determination to be filed with the SCH and County Clerk.
DELIVERABLES:
Attendance at one Planning Commission hearing.
Attendance at one City Council hearing.
Task 11: Administrative Record Preparation
FCS will provide the City with the Administrative Record within 30 days of the Planning Commission hearing or City Council making a determination about the project. The Administrative Record will include all documents referenced in the EIR and technical appendices.
DELIVERABLE:
Electronic copy (via USB flash drive/FTP site/other alternative in PDF) Administrative Record to the City.
Task 12: Project Management and Coordination Meetings
In addition to the research, analysis, communication, and report writing tasks described above, FCS will perform a variety of project management duties to ensure that the CEQA document meets City’s standards of quality and that it is delivered on time and within budget. These duties will include team supervision and coordination, oral and written communication with City staff and the applicant, project accounting, and quality assurance review of all deliverable products by FCS’s Project Director. These services will also include ongoing support to City staff, such as regular schedule updates and discussions of technical issues. FCS’s Project Director or Project Manager will attend up to twenty 30-minute coordination meetings with City staff and/or the applicant team. A not-to-exceed budget has been established to cover attendance at these meetings. If City staff requests additional meeting attendance by FCS staff, or if the amount of time involved in these meetings exceeds the initial budget allocation, FCS will notify the City of the additional costs and obtain authorization for the extra meeting time.
EXHIBIT A
Environmental Impact Report for the General Plan Amendment and Zone Change No. 24-0514 17 and Williamson Act Cancelation No. 26-0001 (Taft Highway and Wible Road) City of Bakersfield
Work Schedule
FCS has prepared the following schedule outlining the anticipated timing of each task.
Task Turnaround Time
(Weeks)
Task 1 Kick-off Meeting and Background Review 1
Task 2 Notice of Preparation and Circulation
Subtask 2.1 Notice of Preparation and Initial Study
– Submit Draft NOP and Initial Study Checklist to the City 8 – Receive Comments on NOP and Initial Study 10
– Submit Final NOP and Initial Study Checklist to the City 12 Subtask 2.2 Scoping Meeting Attendance To Be Determined Task 3 Expanded Project Description Preparation 12
Task 4 Applicant-prepared Technical Report Peer Review 10 Task 5 Administrative Draft EIR Preparation
– Submit Administrative Draft EIR to the City 18
– Receive First Round of Comments on Administrative Draft EIR 22 – Resubmit Administrative Draft EIR to the City 25
– Receive Second Round of Comments on Administrative Draft EIR 27 Task 6 Screencheck Draft EIR Preparation
– Submit Screencheck Draft EIR to the City 28
– Receive Comments on Screencheck Draft EIR 30
Task 7 Draft EIR and Technical Appendices Circulation
– Begin 45-day Public Review Period 32
– 45-day Comment Period Ends 38
Task 8 Draft and Screencheck Final EIR and Technical Appendices Preparation and Circulation Subtask 8.1 Draft Final EIR
– Submit Draft Final EIR to the City 42
– Receive Comments on Draft Final EIR 46
Subtask 8.2 Screencheck Final EIR
– Submit Screencheck Final EIR to the City 48
– Receive Comments on Screencheck Final EIR 50
Subtask 8.3 MMRP
– Submit Draft MMRP to the City 48
– Receive Comments on the Draft MMRP 50
– Submit Final EIR and MMRP to the City 52
Task 9 Draft Findings of Fact and Statement of Overriding Considerations Preparation 48 Task 10 Hearing Attendance1 55
Task 11 Administrative Record Preparation 54
Task 12 Project Management and Coordination Meetings Ongoing 1 At least 21 days after the distribution of the FEIR.
EXHIBIT A
Environmental Impact Report for the General Plan Amendment and Zone Change No. 24-0514 18 and Williamson Act Cancelation No. 26-0001 (Taft Highway and Wible Road) City of Bakersfield Cost of Services
Key Project Role Project Director
Senior Project
Manager Project Manager Analyst Legal Counsel GIS Publications Publications Air Quality/GHG
Emissions and
Energy
Specialist
Agricultural
Specialist
Biological
Resources and
Regulatory
Compliance
Specialist
Cultural
Resources
Specialist
AQ/Noise
Specialist AQ AQ/Noise CUL PALEO
Employee Name
Hudson
(Waligorski), J. Wolfe, A.
Perez (Hagen),
B. Landucci, Z. Starr, M. McCracken, K. Harris, S. Ramirez, M. Li, T. Campion, L. Tuma, M. DePietro, D. Ault, P.
McLaughli
n, E. Landucci, Z. Griffin, S. Stewart, J.
Task Career Role
Associate
Director
Senior
Environmental
Services Project
Manager III
ES Project
Manager
Air Quality
Analyst I Principal Attorney Sr. GIS Scientist I
Senior Managing
Editor
Technical
Document
Manager
Senior Air Quality
Scientist III
Environmental
Services Project
Manager II
Senior Biologist
III Director
Associate
Director
Air Quality
Scientist
Air Quality
Analyst I
Senior
Archaeologist II
Senior
Paleontologist I
Hours 1234 0 4431 0 111 00 0 0 25.00 $4,395.00 $0.00 $0.00 $0.00 $0.00 $4,395.00 Hours 0 0 0 0 0 0 0 0 0 0 0 0 000 0 0 0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Hours 11261632 0 0 0 0 000 0 0 22.00 $3,475.00 $0.00 $0.00 $0.00 $0.00 $3,475.00 Hours 4 8 20 40 5 0 86 0 0 0 0 000 0 0 91.00 $13,030.00 $0.00 $0.00 $0.00 $0.00 $13,030.00 Hours 0 8 0 0 0 0 0 0 0 0 0 0 000 0 0 8.00 $1,800.00 $0.00 $0.00 $0.00 $0.00 $1,800.00 Hours 2 4 6102 4 4 2 0 0 0 0 000 0 0 34.00 $5,440.00 $0.00 $0.00 $0.00 $0.00 $5,440.00 Hours 1 6 812 4 0 8 6 8 6 10 5 6 10 6 9 1 106.00 $19,840.00 $1,725.00 $5,750.00 $11,500.00 $18,975.00 $38,815.00 Hours 20 36 60 120 20 8 00 5 4 12 5 9 10 24 9 1 343.00 $54,880.00 $0.00 $0.00 $0.00 $0.00 $54,880.00 Hours 12 20 30 60 18430 282 2 3 2 2 0 44 0 221.00 $35,620.00 $0.00 $0.00 $0.00 $0.00 $35,620.00Hours 6 101640 6 0 24 18 1 1 0 12 0 32 0 130.00 $19,645.00 $0.00 $0.00 $0.00 $0.00 $19,645.00 Hours 4 8 12 20 4 0 16 12 0 0 0 0 000 0 0 76.00 $11,720.00 $0.00 $0.00 $0.00 $0.00 $11,720.00 Hours 0 0 0 0 0 0 0 0 0 0 0 0 000 0 0 0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Hours 6 102048 8 0 423 0 211 0 22 0 109.00 $16,675.00 $0.00 $0.00 $0.00 $0.00 $16,675.00Hours 3 8 10 30 4 0 10 8 1 0 111 0 11 0 79.00 $11,925.00 $0.00 $0.00 $0.00 $0.00 $11,925.00 Hours 1 6 812 1 0 64 0 0 0 0 000 0 0 38.00 $5,730.00 $0.00 $0.00 $0.00 $0.00 $5,730.00 Hours 12482 0 44 0 0 0 0 000 0 0 25.00 $3,770.00 $0.00 $0.00 $0.00 $0.00 $3,770.00 Hours 12 00 24 0 22 0 0 0 0 000 0 0 31.00 $7,520.00 $0.00 $0.00 $0.00 $0.00 $7,520.00 Hours 0 26 0 0 0 0 0 0 0 0 0 0 000 0 0 26.00 $5,850.00 $0.00 $0.00 $0.00 $0.00 $5,850.00 Hours 1 1 225 1 0 21 0 0 0 0 000 0 0 33.00 $3,750.00 $0.00 $0.00 $0.00 $0.00 $3,750.00 Hours 0 0 0 0 0 0 0 0 0 0 0 0 000 0 0 0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00Hours 12 30 34 0 6 0 0 0 0 0 0 0 000 0 0 82.00 $16,800.00 $0.00 $0.00 $0.00 $0.00 $16,800.00 Hours 10 10 16 0 0 0 0 0 0 0 0 0 000 0 0 36.00 $7,290.00 $0.00 $0.00 $0.00 $0.00 $7,290.00 Total hours 86 198 251 435 106 26 125 98 21 13 29 16 22 20 40 27 2 $240.00 $225.00 $165.00 $90.00 $260.00 $190.00 $150.00 $145.00 $250.00 $170.00 $240.00 $295.00 $270.00 $160.00 $90.00 $210.00 $195.00 Labor and Subconsultant Subtotals $20,640.00 $44,550.00 $41,415.00 $39,150.00 $27,560.00 $4,940.00 $18,750.00 $14,210.00 $5,250.00 $2,210.00 $6,960.00 $4,720.00 $5,940.00 $3,200.00 $3,600.00 $5,670.00 $390.00 1,515.00 $249,155.00 $1,725.00 $5,750.00 $11,500.00 $18,975.00 $268,130.00Direct Expenses Meals, and Lodging $1,320.00Reproductions $3,520.00Postage and Delivery $2,552.00Travel, Auto, incld. Mileage at current IRS rate (.76/mile) $1,265.00 Direct Expenses Subtotal $8,657.00Total Price $276,787.00 Labor and
Subconsultant
FCS Labor Total Task Total
Cameron-Cole,
LLC
Provost &
Pritchard
Consulting
Group
West Yost &
Associates, Inc.
Subconsultant
Total
FCS Staff Subconsultant
Total Hours
Task 8: Draft and Screencheck Final EIR and Technical Appendices Preparation and Circulation Subtask 8.1: Draft Final EIR Subtask 8.2: Screencheck Final EIR Subtask 8.2.1: Final EIR Subtask 8.3: MMRP Task 9: Draft Findings of Fact and Statement of Overriding Considerations PreparationTask 10: Hearing AttendanceTask 11: Administrative Record PreparationTask 12: Project Management and Coordination Meetings Subtask 12.1: Project Management Subtask 12.2: Coordination Meetings FCS 2026 Billing Rates
Task 1: Kick-off Meeting and Background ReviewTask 2: Notice of Preparation and Circulation Subtask 2.1: Notice of Preparation Subtask 2.2: Intitial Study Checklist Subtask 3.3: Scoping Meeting Task 3: Expanded Project Description PreparationTask 4: Applicant-prepared Technical Report Peer ReviewTask 5: Administrative Draft EIR Preparation Subtask 5.1: Addressing CIty Comments on Revised ADEIR
Task 6: Screencheck Draft EIR PreparationTask 7: Draft EIR and Technical Appendices Circulation
EXHIBIT B
Environmental Impact Report for the General Plan Amendment and Zone Change No. 24-0514 19 and Williamson Act Cancelation No. 26-0001 (Taft Highway and Wible Road) City of Bakersfield
Payment Schedule
Compensation shall be based on the fixed fee provided in the Cost Proposal. Invoices will be submitted monthly based on the percentage of completion of each task. The invoice will identify the task budget, percentage complete, amount previously billed, current amount due, and remaining budget. Payment is due in accordance with the terms of the agreement.
Assumptions
The assumptions used in calculating the above fees are:
Reimbursable expenses have been included in cost of services above. Should additional reimbursable expenses such as mileage or additional copies be required, an additional services agreement will be provided. There will be no significant revisions to the submitted development application. If there is a change in the Project Description by the applicant, a budget adjustment will be required to account for the project revisions. This price is based on completion of the work within the proposed schedule. If delays occur, an amendment of the price would be warranted to accommodate additional project management and other costs and to reflect adjustments for updated billing rates.
The fee is valid for up to 30 days from the date of this Scope, after which it may be subject to revision. Costs have been allocated to tasks based upon FCS’s proposed approach. During the work, FCS may, on its sole authority, re-allocate costs among tasks and/or direct costs, as circumstances warrant, so long as the adjustments maintain the total price within its authorized amount.
The FCS Project Manager will be the primary representative at the project meeting and public hearing.
EXHIBIT B