Name Kevin Reisz, PE Gabriel Macias, PE Landon Wright TOTAL COST Classification
Project Manager Resident Engineer Inspector* Office Engineer / Labor Complaince Officer
Hourly Billing Rate (1) $397.62 $279.27 $257.89 $152.25

1.1 Kick-off Meeting 1 2 1

1.2 Pre-Construction Meeting 2 1 1

1.3 Pre-construction Photos 1 4
Man Hour Total 1 5 6 1
Total Fees $397.62 $1,396.35 $1,547.34 $152.25 $3,493.56 Task 2.1 Project Coordination and Correspondence

2.1.1 Interaction with City Staff 4 12

2.1.2 Progress Meetings 4 12 12 12
Task 2.2 Project Administration and Documentation

2.2.1 Document Control 12 4

2.2.2 Schedule Update Review 12

2.2.3 Statement of Working Days 8

2.2.4 Submittal Management 100

2.2.5 Request for Information Management 12

2.2.6 Change Order Management & Cost Control 2 8

2.2.7 Monthly Payment Review & Cost Control 12

2.2.8 Claims Management 1 8

2.2.9 Labor Compliance 0 48
Task 2.3 Construction Observation Services / Inspection Services

2.3.1 Field Inspection and Daily Reporting 24 576

2.3.2 Storm Water Pollution Prevention Plan(SWPPP) Monitoring 8 12 Task 2.4 Project Control Monument Staking

2.4.1 Project Control Monument Staking (Not Included)
Man Hour Total 11 228 600 64
Total Fees $4,373.82 $63,673.56 $154,734.00 $9,744.00 $232,531.38

3.1 Final Inspection & Notice of Completion 4 8

3.2 Prepare & Recommend Final Payment Request 4 1

3.3 Review & Submit As-Builts 4 4

3.4 Deliver Project Files 1 1
Man Hour Total 0 13 12 2
Total Fees $0.00 $3,630.51 $3,094.68 $304.50 $7,029.69
Man Hour Total Tasks 1 - 3 12 246 618 67
Total Fees Tasks 1 - 3 $4,771.44 $68,700.42 $159,376.02 $10,200.75 $243,054.63 Notes and Assumptions: Other Direct Costs

1. NV5 employees hourly rates include project-related overhead, profit, safety equipment, vehicles, laptops, and cell phones.

2. Cost proposal is based on 8-hour shifts according to the Caltrans 5-Day Working Calendar. Overtime hours will be paid in accordance with applicable labor law and prevailing wage rates. Office Expenses $0.00

3. Adjustments to this estimate may be required if the actual schedule requires more or less construction management services than proposed.

5. Time extensions to the project may result in additional Construction Managemnent services & fees. Total Proposal Costs $243,054.63

6. This estimate is based on the specific scope of work described for the Septage Receiving Station Project 24WDWW03, E3K30400 (Plant No. 2)

7. * Classifications requiring prevailing wage are subject to the provisions set forth in the latest DIR determination.

8. This cost estimate includes services for dispute resolution through project acceptance. Services for claims after acceptance will be provided at additional costs.

4. This cost estimate is based on the project being completed within 120 working days with a part time Resident Engineer.

Fee Proposal for CM and Inspection Services - Wastewater Treatment Plant No. 2 Septage - PROJECT NO. 25WDWW03, E3K30400 Prepared for The City of Bakersfield
TASK I: PRECONSTRUCTION SERVICES
TASK 2: CONSTRUCTION MANAGEMENT SERVICES DURING CONSTRUCTION TASK 3: POST CONSTRUCTION & PROJECT CLOSEOUT SERVICES