Barstow Facilities Master Plan | Cover Letter
April 19, 2022
Domingo D. Gonzales
Engineering Services Administrator
City of Barstow
City Clerk’s Office
220 E. Mountain View Street, Suite A
Barstow, CA 92311
Subject: Amending the Citywide Wastewater and Sewage Facilities Master Plan | RFP Number: ENG-211101
Dear Mr. Gonzales and Members of the Selection Committee:

The Citywide Wastewater and Sewage Facilities Master Plan Update project will provide the City of Barstow (City) with strategic guidance for reliable and cost-effective wastewater service through ultimate build-out conditions. As demonstrated in our proposal, Carollo brings the depth and breadth of experience that is a direct match to your project needs, with the following benefits to the City:
• Success delivered through proven project leadership. Our team has proven their ability to develop dozens of master plans that not only meet our clients’ needs, but develop creative, cost-effective solutions that address challenges similar to your own. Our principal-in-charge, Jeff Weishaar, is intimately familiar with the City’s wastewater treatment facilities, and our proposed project manager and project engineer, Ryan Orgill and Joaquin Ramirez, have completed recent master plans for similar agencies throughout California, including the City of Visalia, Porterville, Lemoore, and Chino Hills.
• Acceptance through collaboration. We understand how important close coordination with the planning department and the development community will be to developing realistic wastewater flow projections, user rates, and connection fees. Ultimately, acceptance by community stakeholders will be a metric for success and a driver for easy project implementation. Carollo’s experience developing master plans that achieve acceptance sets us apart from our competitors. • Implementable, realistic solutions. We pride ourselves on developing realistic solutions that help you move forward to the next phase of the project or program recommendation. Whether it’s the assumptions that feed into growth projections, or the electronic capital improvement plan (CIP) tools that allow your plan to change and adjust over time, Carollo’s plan will help you move forward quickly and easily.

Our team is available and fully committed to delivering a master plan update that meets your current and future goals. In addition, we have reviewed the City’s Professional Services Agreement and have provided suggested changes in the Appendix. We are excited for the opportunity to continue our partnership with the City and look forward to discussing our proposal with you. If you have any questions about this proposal, please contact Ryan Orgill at 559-284-5451 or [email protected].

Sincerely,
CAROLLO ENGINEERS, INC.

Ryan Orgill, PE
Associate Vice President
Authorized Representative:

Ryan Orgill, PE, Associate Vice President
P: 559-284-5451
E: [email protected]
F: NA
Statement of Understanding
of the Project
The goal of theWastewater and Sewage Facilities Master Plan Update (WSFMP) is to update the recommendations of the
previous master plan and to provide an updated and prioritized CIP. THE CITY OF BARSTOW // CITYWIDE WASTEWATER AND SEWAGE FACILITIES MASTER PLAN CAROLLO // PROPOSAL // APRIL 2022
\\Io-bd-1\bd-data\Marketing\Pursuits\Client20(OCO)\Barstow\CitywideWW,Water&SewerFacilitiesMP\Prop0422\Indd\2-Statement of Understanding of the Project 1 STATEMENT OF UNDERSTANDING OF THE PROJECT
The City has requested proposals to update
your previous wastewater master plan.The
City has a strong growth potential, and has
received numerous development inquires in
recent years. The goal of theWSFMP is to
update the recommendations of the previous
master plan to include revised growth
assumptions within the planning area, and
to provide an updated and prioritized CIP to
provide reliable, cost-effective services for
existing and future customers.

In addition, the City would like to provide
integration with their hydraulic model and
geographic information systems (GIS), and
to conduct a planning level evaluation of the
wastewater treatment facilities, water reuse
potential, and funding options.

Development of thisWSFMP will require
addressing the following key challenges:
ƒ Coordination with the City’s planning
department and the development
community to develop realistic
growth assumptions.
ƒ Development of a prioritized CIP that is
flexible enough to accommodate future
changes in growth assumptions.

The challenge agencies encounter is how
to adapt their CIP to changes in growth
assumptions/timing. Change in the future is
a certainty, and that change will affect future
funding decisions.

Developing a master plan that provides the
ability to be nimble and respond to changes in
the timing and size of development projects is
key to project success. We will develop a new
CIP planning tool that is a complete summary
of your CIP projects. The projects are each detailed in separate worksheets, complete with a project summary, cost, and the growth triggers for the project. The project summary sheets are linked to an integrated CIP master summary table.

Our tool will update the timing of improvements/costs through a simple adjustment of the target completion date. All of these changes are seamlessly updated in the CIP summary table.

The City’s General Plan identifies likely areas for future development. A key to the success of this project is close consultation with the City’s planning department to understand the latest information on likely development patterns within the City.

Trigger plots will help “right size” your CIP
refining project definition and schedule to
adapt to changing conditions.

City of Gresham
Wastewater Pump Station Master Plan
June 2008
1 All costs are in 2008 dollars
2 Engineering News Report (ENR) U.S. 20City Construction Cost Index for May 2008 is 8,141 3 Cost Estimates do not include Costs for Easements or ROW Acquisition 4 Pump Replacement Schedule is based on a 25year pump life Adjustment Factors
Contingency 30 %
General Conditions 15 %
General Contractor Overhead 15 %
Engineering/Legal/Admin 25 %
%
The cost estimate herein is based on our perception of current conditions at the project location.

This estimate reflects our professional opinion of accurate costs at this time and is subject to change as the project design matures. Carollo Engineers have no control over variances in the cost of labor, materials, equipment; nor services provided by others, contractor's means and methods of executing the work or of determining prices, competitive bidding or market conditions, practices or bidding strategies. Carollo Engineers cannot and does not warrant or guarantee that proposals, bids or actual construction costs will not vary form the costs presented as shown.

Level Four Cost Estimate Disclaimer:

Cost Estimate Assumptions
Table 10.2 Capital Improvements Plan
City of Gresham
Wastewater Pump Station Master Plan
2008/
2009
2009/
2010
2010/
2011
2011/
2012
2012/
2013
2013/
2014
2014/
2015
2018/
2019
2021/
2022
185th Street
Flow Monitoring $25,550
Upgrades $30,409
Pump Replacement Design $137,454
Pump Replacement Construction $549,816
Atherton
Replace w/Gravity $333,535
Cascade Glen 1
Upgrades $68,523
Pump Replacement $26,029
Cascade Glen 2
Upgrades $38,468
Pump Replacement $29,227
College
Upgrades & Pump Replacement Design $66,415
Upgrades & Pump Replacement Construction $265,659
Possible Full Replacement  Additional Design $48,999
Possible Full Replacement  Additional Const. $195,995
Hunters Highland
Flow Metering $24,070
Upgrades and Pump Replacement $139,233
OR
Replace by Gravity Design $202,227
Replace by Gravity Construction $808,907
Rockwood
Flow Metering $26,863
Upgrades $33,525
Pump Replacement $89,160
TOTAL COSTS ( $333,535 $191,896 $461,653 $0 $140,516 $276,687 $580,225 $115,190 $29,227 Cost for Hunters Highland Replace with Gravity $202,227 $808,907 TOTAL COSTS: Hunters Highland Replace w/Gravity $342,743 $1,085,595 Recommended Fiscal Year of Project Implementation

CAPITAL IMPROVEMENTS PLAN
Pump Station & Improvement Project
CIP.xls Final CIP
City of Gresham
Wastewater Pump Station Master Plan
June 2008
185th Street Pump Station
Current Pump Rated Design Capacity: 464 gpm
YEAR PIF (gpm)
Firm
Capacity
(gpm)
2008 109 464
2028 1075 464
Intersection between PIF and Firm Capacity:
(Intersection year and flow will change with graph output) Year: 2015 0
200
400
600
800
1000
1200
Flow (gpm)
185th Street Pump Station Trigger Plot
PIF (gpm)
Firm Capacity (gpm)
Linear (PIF (gpm))
Year: 2015
Flow: 464
Engineering/
Legal/ Admin
30% subtotal 15% subtotal 15% subtotal 25%
Flow Metering
8" Flow Meter 1 EA $ 3,456 3,456$
5'X5' Precast Meter Vault 1 EA $ 4,433 4,433$
Meter Piping & Appurtenances 1 LS $ 4,000 4,000$
$ 11,889 $ 3,567 $ 15,456 $2,318 17,774 $ $ 2,666 20,440$ $ 5,110 $ 25,550 Upgrades Flow Metering Cost Estimate Total: $ 25,550 2009 Minor
185th Street PS Improvements Quantity Units
Total
Capital
Cost
Year of
Improvement Cost/ Unit Cost Contingency General Conditions General Contractor Overhead
0 Year
Minor
O&M Manual 1 EA $ 4,500 4,500$
Fall Protection (Safety Nets) 1 EA $ 1,000 1,000$
Reorient Isolation Valves 1 LS $ 100 100$
Replace Valve Vault Fan (Optional) 1 LS $ 1,500 1,500$
Remove wet well fans & Install
steel plate 1 LS $ 950 950$
$ 8,050 $ 2,415 10,465$ $ 12,035 1,570 $ $ 1,805 13,840$ $ 3,460 $ 17,300 Major
Replace Pump Guide Rails 1 LS $ 1,200 1,200$
Site Lighting & Pole 1 EA $ 3,500 3,500$
Electrical Allowances 1 LS $ 1,400 1,400$
$ 6,100 $ 1,830 $ 7,930 $ 1,190 $ 9,120 $ 1,368 $ 10,487 $ 2,622 $ 13,109 Upgrades Cost Estimate Total: $ 30,409 2014
Replace Pumps/Increase Capacity
New Pumps (540 gpm @ 245') 3 EA 40,000$ 120,000 $
New Valve Vault for 3rd Pump 1 LS $ 3,000 3,000$
Piping & Appurtenances Piping & Appurtenances 1 LS $ 10,000 $ 10,000 Electrical Allowances 1 LS 21,200 $ 21,200$
New 8" FM extension 2300 LF $ 165,600$ 72
$ 319,800 95,940$ 415,740$ 62,361$ 478,101$ $ 71,715 $ 549,816 $ 137,454 $ 687,270 Pump Replacement ELA Estimate Total: $ 137,454 2013
Pump Replacement Construction Cost Estimate Total: $ 549,816 2014 CIP.xls 185th Street PS
Qualifications
Carollo is a water-focused full-service engineering firm with the ability to manage master planning projects of any size.

FIRM HISTORY AND SERVICES

PROVIDED BY CAROLLO
Carollo was founded in 1933. We are a full-service
company with the right experience and qualified
professionals needed to successfully manage projects
of any size. Carollo offers a diverse range of water and wastewater-related services, from planning studies,
design, and construction management. Our proposed
project team is made up of experienced professional
engineers that will bring high-level technical expertise to your project. Cities, utilities, and municipalities time and time again trust Carollo to help navigate increasingly complex challenges.

Shasta Lake
Redding
Chico
Oroville
Yuba City
Elk Grove
Truckee Sanitary District
South Tahoe Public Utility District
Madera County Los
Banos
Fresno
Selma-Kingsburg-Fowler County Sanitation District
Visalia
Tulare Porterville
Lost Hills Utility District
Bakerseld Taft
Moorpark
Santa Barbara
Camrosa Water District
Oxnard
Simi
Valley
Los Angeles World Airport
Victorville
Hesperia
Cucamonga Valley Water District
Upland
Indio
El Centro
Torrance
Santa Maria
California Department of Corrections
Morro Bay
Modesto
Turlock
Livingston
Atwater
Galt
Napa
Sanitation
District Cotati
Sacramento Regional County Sanitation District
Riverside
Eastern Municipal Water District
Elsinore Valley Municipal Water District
Hanford
Lemoore
King City
West County Wastewater District
Oakland
San Francisco
East Bay Dischargers Authority
Pacica
San Bruno
Millbrae
Hayward
Foster City
Mid-Peninsula Water District
Sewer Authirity Mid-Coastside
Union Sanitary District
San Jose
Mountain View
West Valley Sanitation District
Santa Cruz
Morgan Hill
Watsonville
Gilroy
Orange County Sanitation District
Inland Empire Utilities Agency
Anaheim
Garden Grove
Yorba Linda Water District
Chino Hills
UC Irvine
Mesa Water
El Toro Water District
Moulton Niquel Water District
San Clements
Oceanside
Carlsbad
Encina Wastewater Authority
San Diego
Padre Dam Municipal Water District
Los Angeles
Glendale
Pasadena
San Bernardino
Colton
Redlands
Yucaipa
Banning

MASTER PLANNING EXPERTS
Our proposed project team has extensive experience in
wastewater planning projects that span a vast spectrum
of services, from small specific planning studies to
large regional programmatic planning efforts. In the
long run, it’s that experience that provides you with the knowledge that by selecting Carollo, you have a trusted advisor who can tap into a wealth of experience tackling similar challenges to yours. We look forward to adding
the City to our list of happy master plan clients.

PRIMARY MARKETS SERVED
Carollo provides water and wastewater services for
agencies throughout the country. If we look at California, there aren’t many areas where Carollo hasn’t completed
a planning study.

There aren’t many areas in
California where Carollo hasn’t
completed a planning study. While
not all the projects listed on the
adjacent map were completed by
our proposed team, a significant
number of them were.

THE CITY OF BARSTOW // CITYWIDE WASTEWATER AND SEWAGE FACILITIES MASTER PLAN CAROLLO // PROPOSAL // APRIL 2022
\\Io-bd-1\bd-data\Marketing\Pursuits\Client20(OCO)\Barstow\CitywideWW,Water&SewerFacilitiesMP\Prop0422\Indd\3-Qualifications 2 QUALIFICATIONS

RELEVANT EXPERIENCE

CITYWIDE WASTEWATER MASTER PLAN UPDATE
City of Chino Hills, California
The Carollo team was selected to prepare and deliver a sustainable and affordable update to the City of Chino Hills’ (Chino Hills) Citywide Wastewater Master Plan that establishes baseline system condition and hydraulic capacity, as well as establishes CIP needs, and meets the City’s requirements for operational reliability and future growth. As part of this ongoing effort, Carollo developed a new wastewater model using Chino Hills’ latest GIS, developed a flow monitoring plan with detailed maps, installed 13 flow meters at key locations, calibrated the model to provide an accurate representation of the current system, and performed quality assurance and quality control (QA/QC) at key milestones.

The flow factors will be updated as part of this effort and will consider the ongoing water master plan so that planning assumptions align between reports. In addition, Carollo completed CCTV on 20 miles of pipeline and performed condition assessments of the City’s sewer system to develop a comprehensive understanding of system condition and propose a rehabilitation approach to increase the useful life of the current assets.

REFERENCE
Fe M. Rama
Senior Engineer
P: 909.364.2776
E: [email protected]

TEAM MEMBERS
T. Loper, R. Orgill, M. Wetterau,
J. Silber
DATES
9/2020 - Ongoing
Last Revised:July 06, 2020 [ENTER PROJECTWISE PATH NAMETO MXD] For Example: pw://Carollo/Documents/Client/CA/ClientName/10265A00/Data/GIS/Figure_01_01.mxd PROJECT NAME | TM | CITY OF CHINO HILLS
Figure # Existing Pipelines

WATER, SEWER, AND WASTEWATER TREATMENT PLANT

MASTER PLANS
City of Lemoore, CA
In 2017, the City of Lemoore worked with Carollo to
prepare a combined water distribution, wastewater
collection, and wastewater treatment master plan.

The City had never completed a master plan for this
infrastructure. The water distribution system consists of 115 miles of active water pipelines, ranging from 1 to 18 inches in diameter; 10 active wells; 5 tanks; and 4 pump stations. The wastewater collection system includes 82 miles of active gravity sewer lines, ranging from 6 to 21 inches in diameter; 17 lift stations; and associated force mains. The WWTP has a capacity of 2 mgd and consists of four ponds.

Carollo constructed a hydraulic model of the City’s wastewater collection system, which was calibrated against temporary flow monitoring data collected as part of the project. The findings of the collection system analysis were used to develop a set of recommended pipeline and lift stations upgrades and a staged capital improvement program for the City’s collection system.

REFERENCE
Frank Rivera
Public Works Director
P: 559.924.6744
E: [email protected]

TEAM MEMBERS
T. Loper, R. Orgill, J. Ramirez,
G. Mitzel, J. Silber
DATES
3/2017 - 9/2020

KING CITY WASTEWATER FACILITIES PLAN AND

COLLECTION SYSTEM MASTER PLAN
City of King City, CA
In 2016, to determine the overall impact on future sewer rate increases, the City of King City retained Carollo to complete an evaluation of its collection system and wastewater
treatment facilities. Faced with mounting maintenance
requirements for the domestic pond-based system, potential for future regulations, difficulty meeting existing treatment requirements, and the desire to produce recycled water, the City decided it was time to upgrade its existing system to a modern, tertiary treatment facility.

Carollo developed a collection system hydraulic model for the City’s collection system, which was calibrated to dry and wet weather flow monitoring data collected as part of the project. The Wastewater Facilities Plan and Collection System Master Plan resulted in a capital improvement program that was used as the basis for a rate study. The resulting rate increases will fund the first phase of treatment plant improvements and the various collection system improvements.

REFERENCE
Steve Adams
City Manager
P: 831.385.3281
E: [email protected]

TEAM MEMBERS
T. Loper, R. Orgill, J. Silber
DATES
9/2016 - 5/2018
FINAL • APRIL 2019
King City
Recycled Water Feasibility Study

THE CITY OF BARSTOW // CITYWIDE WASTEWATER AND SEWAGE FACILITIES MASTER PLAN CAROLLO // PROPOSAL // APRIL 2022
\\Io-bd-1\bd-data\Marketing\Pursuits\Client20(OCO)\Barstow\CitywideWW,Water&SewerFacilitiesMP\Prop0422\Indd\3-Qualifications 3 QUALIFICATIONS
Personnel
Carollo will provide a team of experts in each area of the project. These team members have relevant experience and an understanding of your project that will make it successful.

Resumes for all personnel are provided in the Appendix.

Ryan Orgill, PE

PROJECT MANAGER
Ryan brings 18 years of experience dedicated specifically to infrastructure master planning projects and is Carollo’s company-wide lead for sewer system modeling, calibration, and system analysis. He developed Carollo’s means and methods for sewer system planning that have been adopted company-wide and is an expert in delivering projects that incorporate all critical elements of collection system capital program needs. ƒ Project manager for the City of Scotts Valley, CA, Sewer Master Plan and Sewer System Master Plan (SSMP).
ƒ Project manager for the City of Chino Hills, CA, Citywide Wastewater Master Plan. ƒ Project engineer for the City of Torrance, CA, Sewer Master Plan and SSMP.

Title
Ryan Orgill, PE
Project Manager
Joaquin Ramirez, PE
Project Engineer
Jeff Weishaar, PE
Principal-in-Charge
Tim Loper, PE
Technical Advisor
Technical Leads
Jeff Weishaar, PE
Grace Mitzel, PE*
Rachel Duncan, PE, ENV SP
Jackie Silber, GISP
ADS Environmental Services, LLC
National Plant Services, Inc.

Mike Wetterau, PE*
Seema Chavan, PE
Zanjero, Inc.

WWTP Evaluation
Hydraulic Modeling
Water Reuse Analysis
GIS
Flow Monitoring
CCTV Inspection
CCTV Review
Funding
Water Rights
LEGEND
* Licensed in
Nevada only
Title
Ryan Orgill, PE
Project Manager
Joaquin Ramirez, PE
Project Engineer
Tim Loper, PE
Technical Advisor
Technical Leads
Jeff Weishaar, PE
Grace Mitzel, PE*
Rachel Duncan, PE, ENV SP
Jackie Silber, GISP
ADS Environmental Services, LLC
National Plant Services, Inc.

Mike Wetterau, PE*
Seema Chavan, PE
Zanjero, Inc.

WWTP Eva
Hydraulic M
Water Reus
GIS
Flow Monit
CCTV Inspe
CCTV Revie
Funding
Water Right
LEGEND
* Licensed in
Nevada only

THE CITY OF BARSTOW // CITYWIDE WASTEWATER AND SEWAGE FACILITIES MASTER PLAN CAROLLO // PROPOSAL // APRIL 2022
\\Io-bd-1\bd-data\Marketing\Pursuits\Client20(OCO)\Barstow\CitywideWW,Water&SewerFacilitiesMP\Prop0422\Indd\4-Personnel 4 PERSONNEL
Jeff Weishaar, PE

PRINCIPAL-IN-CHARGE, WASTEWATER TREATMENT PLANT (WWTP) EVALUATION Jeff is a vice president with 16 years of extensive experience in water and wastewater treatment. He has held leadership roles in the design and construction of projects involving nearly all aspects of water treatment. Jeff has completed multiple master plan projects.

From pipelines to biosolids facilities, Jeff has been instrumental in the development of several secondary water reclamation plants in southern California. Jeff has worked on planning through preliminary and final design, with a focus on condition assessments of existing wastewater facilities, including the City of Barstow. He is able to effectively assess and provide an estimated remaining service life of major mechanical equipment, provide information to prioritize rehabilitation or replacement needs, and recommend cost efficient design solutions that save money and time.
ƒ Project engineer for the City of Oceanside, CA, San Luis Rey Water Reclamation Plant. ƒ Project manager for the Encina Wastewater Authority, CA, Process Master Plan for the Encina Water Pollution Control Facility.
ƒ Project engineer for the City of Oceanside, CA, Weese Water Reclamation Plant Facility Needs Assessment.

Tim Loper, PE

TECHNICAL ADVISOR
Tim is Carollo’s Infrastructure Master Planning Services Lead and has been working for the past 20 years in wastewater collection system modeling and infrastructure master planning. Tim has served as project manager and/or project engineer for more than 90 water, wastewater, stormwater and/or recycled water master plans and modeling projects, with a focus on helping agencies develop capital improvement programs that help prioritize rehabilitation and replacement projects, as well as integrate capital with inspection and funding prioritization.
ƒ Collection system lead for the City of Riverside, CA, Comprehensive Wastewater Master Plan.
ƒ Project engineer for the City of Oceanside, CA, Integrated Master Plan. ƒ Project engineer for the Elsinore Valley Municipal Water District, CA, Wastewater Master Plan.

Joaquin Ramirez, PE

PROJECT ENGINEER
Joaquin has eight years of experience in hydraulic modeling, master planning, and GIS. His experience includes performing hydraulic analysis for similar master planning efforts, including hydraulic modeling and wastewater collection system analysis. He has developed and performed hydraulic modeling for clients across the nation with trusted, credible results. ƒ Project engineer for the City of Visalia, CA, Collection System Master Plan. ƒ Project engineer for the City of Lemoore, CA, Integrated Master Plan. ƒ Project engineer for the City of Banning, CA, Integrated Master Plan.

THE CITY OF BARSTOW // CITYWIDE WASTEWATER AND SEWAGE FACILITIES MASTER PLAN CAROLLO // PROPOSAL // APRIL 2022
\\Io-bd-1\bd-data\Marketing\Pursuits\Client20(OCO)\Barstow\CitywideWW,Water&SewerFacilitiesMP\Prop0422\Indd\4-Personnel 5 PERSONNEL
Grace Mitzel, PE

HYDRAULIC MODELING
Grace has seven years of experience as a hydraulic modeling engineer. She has worked successfully on critical aspects of model development, calibration, and hydraulic analysis including water quality evaluations. She has completed projects utilizing models provided by Bentley Systems, Inc. to solve water distribution system problems including improving fire flows, sizing pipelines, and evaluating pressure zones. ƒ Staff engineer for the City of Morro Bay, CA, OneWater Morro Bay Integrated Water Master Plan.
ƒ Modeling engineer for the City of Lemoore, CA, Water Master Plan. ƒ Staff professional for the City of Porterville, CA, Integrated Master Plans.

Rachel Duncan, PE, ENV SP

WATER REUSE ANALYSIS
Rachel is a civil engineer with seven years of experience specializing in climate change vulnerability assessments for water and wastewater infrastructure and water supply planning projects with an emphasis on climate change impact modeling and analysis, alternatives analysis, and decision modeling. She has additional experience in recycled water project planning and design, permitting, funding, and hydraulic modeling. ƒ Lead engineer for the City of South Pasadena, CA, One Water 2050 Plan—Integrated Water, Wastewater, Recycled Water, and Stormwater Master Plan. ƒ Assistant project manager for the Joint Water Commission, OR, Joint Water Commission Water System Master Plan.
ƒ Project manager for the City of Lathrop, CA, Recycled Water Program Development Recycled Water User Guide.

Jackie Silber, GISP
GIS
Jackie is a GIS lead with 20 years of experience in GIS and technical training, including geospatial GIS analysis for water resource planning and demographic forecasting projects.

Her GIS skills focus on geodatabase design and optimization, manipulation and conversion of projections, CAD and KML to GIS conversion, spatial analysis, automation of repetitive analysis using Model Builder and Python, and creation of cartographic figures. ƒ GIS for the Cucamonga Valley Water District, CA, Water System Master Plan. ƒ GIS for the East Orange County Water District, CA, Peter’s Canyon Water Treatment Plant Feasibility Study and Master Plan Update.
ƒ GIS specialist for the City of South Pasadena, CA, One Water 2050 Plan.

THE CITY OF BARSTOW // CITYWIDE WASTEWATER AND SEWAGE FACILITIES MASTER PLAN CAROLLO // PROPOSAL // APRIL 2022
\\Io-bd-1\bd-data\Marketing\Pursuits\Client20(OCO)\Barstow\CitywideWW,Water&SewerFacilitiesMP\Prop0422\Indd\4-Personnel 6 PERSONNEL
Seema Chavan, PE

FUNDING
Seema has over 20 years of experience in environmental engineering. Her projects have focused on funding assistance, permitting (including agency coordination and permit acquisition), and public involvement. Her experience includes identifying potential sources of loan and grant funding for CIP projects. She has developed Grant Visioning workshops to identify potential funding opportunities for clients.
ƒ Project SRF coordinator for the City of Santa Cruz, CA, Drinking Water SRF funding assistance projects.
ƒ Project manager responsible for the development of the 2017 WIFIA Letter of Intent submittal for the City of South San Francisco, CA, WQCP Wet Weather Improvements Project.
ƒ Funding specialist for the City of Antioch, CA, Brackish Water Desalination Project Grant Funding Support.

Mike Wetterau, PE

CCTV REVIEW
Mike has seven years of experience as a member of Carollo’s infrastructure planning team.

He assists with the development and analysis of existing water conveyance and sewage collection systems, as well as the development of reports for evaluation of existing system information, data, and model analysis. Mike is NASSCO PACP/MACP certified, and has prepared capital improvement recommendations for several clients based on existing CCTV inspection records.
ƒ CCTV review for the City of Chino Hills, CA, Wastewater Master Plan Update. ƒ CCTV review for the Tahoe-Truckee Sanitation Agency, CA, Master Sewer Plan. ƒ Staff engineer for the City of Torrance, CA, Sewer Master Plan.

ADS Environmental Services, LLC (ADS)

FLOW MONITORING
ADS Environmental Services (ADS) is a premier sewer collection system flow monitoring service provider, established in 1975,. As the largest sewer flow meter manufacturer and service provider in the wastewater flow metering industry, ADS offers an extensive but focused range of equipment, software and services that fulfills the requirements.

National Plant Services, Inc. (NPS)

CCTV INSPECTION
Established in 1981, NPS is a full-service sewer and storm drain cleaning, inspection, rehabilitation, and maintenance contractor. In addition to cleaning and inspection, NPS provides laser inspection, sonar inspection, LiDAR inspection, flow monitoring/sewer studies, industrial plant cleaning, specialty cleaning/mechanical cleaning, smoke testing, line grouting, spot repairs, lateral lining from the mainline, and top hats (lateral seals).

Zanjero, Inc. (Zanjero)

WATER RIGHTS
Zanjero specializes in planning and policy to support the sustainable and resilient stewardship of water and power resources. They are skilled in all phases of planning and management of multi-disciplinary projects including infrastructure, economic, natural resources, water rights, energy markets and contracts, regulatory, political, social, and administrative concerns.

THE CITY OF BARSTOW // CITYWIDE WASTEWATER AND SEWAGE FACILITIES MASTER PLAN CAROLLO // PROPOSAL // APRIL 2022
\\Io-bd-1\bd-data\Marketing\Pursuits\Client20(OCO)\Barstow\CitywideWW,Water&SewerFacilitiesMP\Prop0422\Indd\4-Personnel 7 PERSONNEL
Scope
The following scope of services was developed based on our current understanding of the project. Should Carollo be selected for this project, we would welcome the opportunity to sit down with you to discuss the scope assumptions to finalize an approach that works best for the City.

THE CITY OF BARSTOW // CITYWIDE WASTEWATER AND SEWAGE FACILITIES MASTER PLAN CAROLLO // PROPOSAL // APRIL 2022
\\Io-bd-1\bd-data\Marketing\Pursuits\Client20(OCO)\Barstow\CitywideWW,Water&SewerFacilitiesMP\Prop0422\Indd\5-Scope 8 SCOPE
Task 1 – Data Collection and Existing/Future
Service Area Characteristic Identification
Carollo will review available relevant reports and other data for use in this project, as well as other relevant information. We will develop a data collection table that will be presented at the project kickoff meeting and will update the data collection table as items are received.

We will also update the City on outstanding items
remaining for the project. Carollo will review all relevant planning documents related to land use (including
residential, commercial, and industrial/cannabis sector uses), growth projections, and planned developments.

Based on this review, the land use categories and
acreage will be updated and used to determine existing
and future wastewater flow projections. Carollo will
coordinate with City staff on major developments that
will be included in the WSMPU, including a project
meeting with the City’s planning department.
ƒ Assumptions: Future growth will be generally based
on the sphere of influence (SOI), however, the City
may identify specific growth areas outside the SOI
as appropriate.
ƒ Deliverables: Data collection list (PDF and Excel file format); maps and data related to existing and future
study area land use (native file format and PDF).

Task 2 – Identify Wastewater Flows and
Sewer System
As part of this task, Carollo will summarize historical average and peak wastewater flow rates, and will
develop wastewater flow projections in five year
increments through 2040. In addition, we will categorize the City’s collection system facilities as local, collector, trunk, or interceptor pipes, and will identify/describe major interceptor reaches.
ƒ Deliverables: Maps and data related to wastewater
flows and the sewer system (Excel format and PDF –
wastewater categories and reaches will be provided
in GIS format).

Task 3 – Flow Monitoring
As part of this task, the Carollo team will provide
temporary flow monitoring services for a period of
two weeks, including at least one holiday, at locations selected by Carollo and the City. Based on our initial
review of the City’s collection system mapping, we have assumed that 16 flow meters will be installed as part
of this task.
ƒ Assumptions: Assumes no fee permits and that
traffic control services (plans and field controls) are not necessary beyond basic Watch manual type
controls at low traffic sites that can be handled
directly by an ADS two person crew (no flagging,
lighted arrowboard, 18 cones, and six signs).
ƒ Deliverables: Flow monitoring maps (GIS and PDF);
electronic flow monitoring data (Excel); and a flow
monitoring report (PDF).

Task 4 – Hydraulic Model Development and
Interceptor Capacity Analysis
Carollo will update the City’s existing collection system hydraulic model, re-allocate wastewater flows into
the model, and re-calibrate the model based on the
temporary flow monitoring data collected as part of Task

3. The model update will be conducted by comparing
the City’s most recent sewer system database, record
drawings, and other data sources against the existing
hydraulic model. We will use water meter billing data
to allocate dry weather flows into the model at a parcel level to modeled manholes and will calibrate the model

THE CITY OF BARSTOW // CITYWIDE WASTEWATER AND SEWAGE FACILITIES MASTER PLAN CAROLLO // PROPOSAL // APRIL 2022
\\Io-bd-1\bd-data\Marketing\Pursuits\Client20(OCO)\Barstow\CitywideWW,Water&SewerFacilitiesMP\Prop0422\Indd\5-Scope 9 SCOPE
against the flow monitoring program data based on
calibration standards developed by the Wastewater
Planning Users Group. Carollo will conduct a model
calibration meeting to summarize the model calibration
effort, calibration results, areas of concern, or operational discussion items. We will use the calibrated hydraulic
model to analyze the capacity of the City interceptors
and will document the capacity of the City’s existing
interceptors. We will also identify the remaining capacity of the interceptors.
ƒ Assumptions: The City will provide an existing,
functioning hydraulic model of the collection system,
with minor updates necessary to reflect system
changes that have occurred since 2010.
ƒ Deliverables: Maps and data related to the hydraulic
model, remaining capacity of the interceptors (Excel/
GIS format and PDF). Electronic flow monitoring
data will be provided in Excel file format, and a flow
monitoring report will be provided in PDF format.

Task 5 – Analyze Existing and Future
Wastewater Facilities
Carollo will evaluate the capacity of the existing
wastewater treatment plant system, including
screening, the allowable headwork’s loading study, the
influent pump station, primary treatment, aeration,
secondary clarification, effluent percolation ponds,
and primary/secondary sludge treatment. We will also
evaluate and analyze the feasibility of regional or subregional wastewater treatment facilities to serve future flows as part of this task. Task 7 will include an analysis of the costs to upgrade or expand the existing treatment facilities/collection system against the costs to construct package plants in new growth areas.
ƒ Assumptions: Up to three wastewater treatment
expansion alternatives will be analyzed.
ƒ Deliverables: Wastewater treatment evaluation
technical memorandum (TM) (Word and PDF); Maps
of potential regional/sub-regional treatment facilities (GIS and PDF).

Task 6 – Evaluation and Analysis of the
Wastewater Collection System
The Carollo team will conduct limited CCTV inspection
of the City’s collection system. It is currently unknown what portion of the City’s existing system has been
CCTV’d in the past. For this reason, we have included
a budget allowance of $70,000 for CCTV inspection
services. The CCTV inspection work will be performed
by NPS. Carollo will document the findings of the CCTV
inspection as part of this task. We will also document
the findings of historical CCTV analysis results
performed by the City, if any.

Carollo will use the calibrated hydraulic model to
evaluate the capacity of the collection system.

Deficiencies in the existing system will be identified, and the future system scenarios will be developed in five
year increments through 2040. Future system analysis
will be conducted, and the existing system deficiencies will be sized to accommodate future system flows.

Improvements required to serve future customers will
also be identified. Areas outside of the current City
limits will be analyzed per City direction, including, but not limited to, High Desert Estates, North and South
Lenwood, Marine Base (Nebo, Yermo), Skyline North
and East, Soapmine Road, North Barstow, and South
Barstow. We will also develop project alternatives for the BNSF sewer capacity limitation.
ƒ Assumptions: A CCTV budget allowance of
$70,000 is assumed.
ƒ Deliverables: Collection System Analysis TM (Word
and PDF); maps of CCTV’d lines (GIS and PDF);
NASSCO PACP output results (native file format/
PDF) for CCTV’d lines; maps showing recommended
rehabilitation and repair recommendations (GIS and
PDF); wastewater capacity deficiencies and proposed
improvements (GIS and PDF); hydraulic modeling
files (native file format).

Task 7 – Economic/Feasibility Analysis
As part of this task, Carollo will perform a high level economic/feasibility analysis of constructing regional/ sub-regional wastewater treatment facilities, upgrading the wastewater treatment facilities/collection system,
constructing package treatment plants, and increasing
existing treatment plant capacity. This economic analysis will be summarized in the wastewater treatment
evaluation TM being prepared as part of Task 5.
ƒ Deliverables: Deliverables associated with this task
will be provided as part of the wastewater treatment
evaluation TM (Task 5).

Task 8 – Water Recycling Analysis
As part of this task, Carollo will analyze different options for the use of recycled water. We will document
potential reuse benefits, and will conduct a high level recycled water market analysis. The market analysis
will consider potential reuse customers including urban and farmland irrigation, commercial and industrial uses, environmental enhancement/groundwater recharge,
and other viable options. We will document/define
regulations for recycled water use for the various uses

THE CITY OF BARSTOW // CITYWIDE WASTEWATER AND SEWAGE FACILITIES MASTER PLAN CAROLLO // PROPOSAL // APRIL 2022
\\Io-bd-1\bd-data\Marketing\Pursuits\Client20(OCO)\Barstow\CitywideWW,Water&SewerFacilitiesMP\Prop0422\Indd\5-Scope 10 SCOPE
planned for the area, and will analyze the impacts of
recycled water use, including environmental impacts,
water rights impacts (water rights analysis will be
conducted by Zanjero). We will develop up to three
(3) reuse alternatives, and will develop a cost/benefit matrix to evaluate each alternative and identify the
preferred alternative.
ƒ Assumptions: Stakeholder outreach is not included
in this task.
ƒ Deliverables: Water recycling analysis TM (Word
and PDF); maps of potential regional/sub-regional
treatment facilities (GIS and PDF).

Task 9 – Pollution Control and Water Recycling
Funding Alternatives
Carollo will review City provided information related
to previous grant applications that the City has
pursued, and other relevant data/information. Based
on discussions with City staff and review of available
planning documents/CIP elements, Carollo will define
the City’s funding needs, the timing of funding needs,
and the projected expenditures for the City based on
available information. Carollo will summarize funding
options that can be used to pay for and/or offset a
portion of the capital costs of identified improvements.

We will then conduct one (1) virtual meeting with
City staff to review the stormwater funding options
assessment. Carollo will summarize findings from this
task as a chapter in the master plan report.
ƒ Deliverables: Funding alternatives chapter in master
plan Task 12 (Word and PDF).

Task 10 – Capital Improvements
Carollo will define the recommended CIPs to serve
existing and future users. Carollo will conduct a project meeting with the City to review the proposed CIP
projects, and to discuss project prioritization. Carollo will develop a capital improvement program that
includes capital improvement costs, proposed project
phasing, existing and future user cost allocations,
and annual capital costs expenditures. Carollo will
conduct a project meeting to review the draft capital
improvement program. Carollo will present detailed
project sheets for each recommended CIP, including the
project description, cost, and phasing. Carollo will also review summary tables of the recommended capital
improvement program as part of the meeting.
ƒ Assumptions: Capital improvement costs will be
Class 5 estimates as defined by the Association for
the Advancement of Cost Engineers.
ƒ Deliverables: Capital improvement TM (Word and
PDF); capital improvement program and CIP detail
sheets (Excel and PDF).

Task 11 – GIS Integration and Training
Hydraulic model results, combined with proposed
developments and land use changes, will be published
to ESRI’s ArcGIS Online and displayed in a dynamic and
intuitive interactive ArcGIS Dashboard which allows
users to make decisions based on summarized model
results and future sewer flows over time. If desired, an ArcGIS Online partnership can be established to create
a trusted collaboration between the City and Carollo
so the Dashboard can be transferred to the City at
project closeout.

This task also includes a two-day, in-person, hydraulic model and GIS tool training session, led by Carollo’s
project engineer.
ƒ Deliverables: ArcGIS Dashboard (cloud-based
solution); model training materials (Word, PDF, and
other native file formats as appropriate).

Task 12 – WSMPU Report
Carollo will develop a draft master plan report
that summarizes the methods, findings and
recommendations from Task 1 through Task 11. We will
submit the draft report to the City for review. Carollo will develop the final master plan report based on the
comments on the draft report and any discussion items.
ƒ Deliverables: Draft master plan (Word and PDF,
electronic only); final master plan (five (5) hard
copies, one (1) electronic copy on external hard drive, Word and PDF).

Task 13 – Project Management and Meetings
Project management will be conducted under this task.

This includes managing the project team, coordinating
with subconsultants, managing the scope of work, and
project meetings. Carollo will conduct a project kickoff meeting as well as six (6) additional project meetings.

This task also includes quality assurance and quality
control activities associated with the project.
ƒ Assumptions: Assumes three (3) in person meetings,
four virtual meetings.
ƒ Deliverables: Monthly invoices/progress reports
(PDF); meeting agenda and minutes (Word and PDF).

Results
The following is a list of the major deliverables that will be developed as part of the project.
ƒ Prioritized data collection list (PDF and Excel).
ƒ Study area maps and data (GIS, PDF, and other
appropriate native file formats).
ƒ Historical wastewater flow summaries
(Excel and PDF).
ƒ Collection system maps including pipe type
delineation (GIS and PDF).
ƒ Flow monitoring maps (GIS and PDF).
ƒ Electronic flow monitoring data (Excel) and flow
monitoring report (PDF).
ƒ Remaining capacity tool for interceptors
(GIS and Excel).
ƒ Wastewater treatment evaluation TM
(Word and PDF).
ƒ Collection system analysis TM (Word and PDF).
ƒ NASSCO PACP output for CCTV inspections
(NASSCO file format, Microsoft Access Database).
ƒ Collection system rehabilitation and repair
recommendation and capacity deficiency maps
(GIS and PDF).
ƒ Hydraulic modeling files (native file format).
ƒ Water recycling analysis TM (Word and PDF).
ƒ Capital improvement TM (Word and PDF) and CIP
planning tool (GIS/PDF and Excel).
ƒ ArcGIS dashboard (cloud-based solution).
ƒ Model training materials (Word, PDF, and other file
formats as appropriate).
ƒ Draft and final master plan (Word, PDF, hard copy/
hard drive for final).
ƒ Monthly invoices/progress reports (PDF).
ƒ Meeting agenda and minutes (Word and PDF).

THE CITY OF BARSTOW // CITYWIDE WASTEWATER AND SEWAGE FACILITIES MASTER PLAN CAROLLO // PROPOSAL // APRIL 2022
\\Io-bd-1\bd-data\Marketing\Pursuits\Client20(OCO)\Barstow\CitywideWW,Water&SewerFacilitiesMP\Prop0422\Indd\6-Results 11 RESULTS
Appendix
ƒ Additional Information
ƒ Resumes
Additional Information
Carollo confirms the receipt of Addenda 1, 2, and 3 and that the proposal is valid for a 90 day period starting April 5, 2022. We request the City consider the following exceptions and additions to the Professional Services Agreement for Consultant Services.

THE CITY OF BARSTOW // CITYWIDE WASTEWATER AND SEWAGE FACILITIES MASTER PLAN CAROLLO // PROPOSAL // APRIL 2022
\\Io-bd-1\bd-data\Marketing\Pursuits\Client20(OCO)\Barstow\CitywideWW,Water&SewerFacilitiesMP\Prop0422\Indd\Appendix-Exceptions

ADDITIONAL INFORMATION
ƒ Section 4: Please add the following to the end of
the paragraph: “Consultant is not responsible for
damage or delay in performance caused by events
beyond the reasonable control of Consultant. In the
event Consultant’s services are suspended, delayed
or interrupted for the convenience of City or delays
occur beyond the reasonable control of Consultant,
an equitable adjustment in Consultant’s time of
performance and cost of Consultant’s personnel and
subcontractors may be made.”
ƒ Section 5.12: Please add the following new
subsection to the end of the section:
» “5.12 Estimates and Projections. In providing
opinions of cost, financial analyses, economic
feasibility projections, schedules, and quantity
and/or quality estimates for potential projects,
Consultant has no control over cost or price of
labor and material; unknown or latent conditions
of existing equipment or structures that may affect
operation and maintenance costs; competitive
bidding procedures and market conditions; time
or quality of performance of third parties; quality,
type, management, or direction of operating
personnel; the incoming water quality and/or
quantity; the way City’s plant(s) and/or associated
processes are operated and/or maintained; and
other economic and operational factors that may
materially affect the ultimate project elements,
including, but not limited to, cost or schedule.

Therefore, Consultant makes no warranty that
City’s actual project costs, financial aspects,
economic feasibility, schedules, and/or quantities
or quality realized will not vary from Consultant’s
opinions, analyses, projections, or estimates.”
ƒ Section 7.6: Please add the following to the end of
the paragraph: “City shall pay Consultant’s approved
invoices within thirty (30) days of receipt.”
ƒ Section 11.7: Please add the following new subsection to the end of Section 11:
» “11.7 Warranties and Damages. Consultant shall
not be responsible for warranties, guarantees,
fitness for a particular purpose, breach of fiduciary
duty, loss of anticipated profits or for economic,
incidental, liquidated, or consequential damages to
City or any third party. Additionally, Consultant shall not be responsible for acts and decisions of third
parties, including governmental agencies, other than
Consultant’s subconsultants, that impact project
completion and/or success.”
ƒ Section 12.2: Please remove the last bullet item. We’re already required to provide original endorsements in the bullet item directly above this one. Additionally, providing a certified copy of the policy, including the endorsements, should only be required upon request if there is some
question as to coverage. The certificate of insurance and the noted endorsements should be sufficient and is what is normally required in other public agency contracts.
ƒ Section 13.1: Please add the following to the end of the sentence: “, which Consultant shall be entitled to use
and reasonably rely upon in completing the services
required hereunder.”
ƒ Section 18.1: Please add the following to the end of the paragraph: “Notwithstanding the foregoing, Consultant
shall be entitled to keep one (1) copy of all data that Consultant used, relied upon and/or incorporated into any deliverable required hereunder.”
ƒ Section 18.5: Please add the following to the end
of the paragraph: “The services to be performed by
Consultant are intended solely for the benefit of City.

No person or entity not a signatory to this Agreement
shall be entitled to rely on Consultant’s performance of its services hereunder, and no right to assert a claim
against Consultant by assignment of indemnity rights
or otherwise shall accrue to a third party as a result
of this Agreement or the performance of Consultant’s
services hereunder.”
Education
MS Environmental
Engineering, University of
Missouri, Rolla, 2006
BS Civil Engineering,
University of Missouri,
Rolla, 2004
Licenses
Civil Engineer, California
Professional
Affiliations
American Society of Civil
Engineers
Society of American
Military Engineers
Water Environment
Federation
Jeffrey A. Weishaar, P.E.

Jeffrey A. Weishaar, a civil and environmental engineer with Carollo Engineers, has worked on various wastewater projects, including elements of analysis, design, and construction.

Relevant Experience
 Project engineer for the City of Barstow,
California. Wastewater Treatment Plant Improvements Phase 1 Project. This project covered multiple subtasks including condition assessment of the wastewater treatment plant, project development and ranking, process modeling, preliminary design and final design. The Phase 1 construction
project includes rehabilitation of the aeration basins, secondary clarifiers, and gravity thickener, as well as SCADA upgrades, a
new dewatering facility and new standby
generator and additional miscellaneous site
piping, electrical and instrumentation upgrades. The Phase 2 construction project will include upgrades to the primary clarifiers
and aerobic digesters as well as a new influent pump station, a new electrical control building and additional SCADA, electrical,
and instrumentation upgrades.
 Project manager for the Encina
Wastewater Authority, California, Process
Master Plan for the Encina Water Pollution
Control Facility.
 Project engineer for the San Luis Rey
Water Reclamation Plant for the City of
Oceanside, California. The preliminary and
final design project will increase plant recycled water production capacity from less than 0.5 to 1.5 mgd and includes master
planning to an ultimate capacity of 7.5 mgd.

Specific responsibilities included process
evaluation and life-cycle cost analysis for
tertiary and disinfection processes during
preliminary design. Final design responsibilities included civil work, yard piping, mechanical and process design for drawing production, specification preparation, and
cost estimating.
 Condition assessment task leader for the
City of Colton, California, Wastewater Master Plan. Responsibilities included leading a team of discipline engineers to assess the
City’s wastewater treatment plant facility.
 Staff engineer for the Sewer Master Plan
for the City of El Centro, California. The project used H2OMAP Sewer® modeling software to identify potential improvement needs for the sewer collection system, including pipes, manholes, and pump stations. Models were based on existing demand and analyzed for existing and future supply and demand.
 Project engineer for the El Estero
Wastewater Treatment Plant Screening Evaluation for the City of Santa Barbara, California. The project evaluated screening technologies to replace the existing grinder and auger system at the influent pump station
facility. Over a dozen screens were evaluated to fit into a high-flow, low-head loss environment with limited installation requirements. Use of multi-rake climber screens, over 20 feet in height, was recommended to remove debris from the incoming flow. The recommendations came after extensive evaluations including interviews of
existing facilities that have the screens
in service.
 Project engineer for the Digester Gas Alternative Uses Evaluation for the South Orange County Wastewater Authority, California. Two treatment plants currently use engine generators to provide beneficial use of digester gas. This project evaluated existing
and new technologies that would allow the
plants to continue to utilize biogas under
new, more stringent air quality emissions
standards. The project recommended installation of new low emissions engine generators.
 Project engineer for the J.B. Latham
Wastewater Treatment Plant Digester Capacity Evaluation for the South Orange County Wastewater Authority, California.

The project included analysis of digester
performance and operations to determine
digester capacity for select goals. These included Class B biosolids, gas production for cogeneration, process stability, and
emergency storage.

Jeffrey A. Weishaar, P.E.
 Project manager for the Water Reclamation Plant Expansion for the City of San Clemente, California. The preliminary and final design project will increase plant recycled water production capacity from 2.2 to

4.4 mgd. Preliminary design responsibilities
included process evaluation of disinfection
processes and flow balancing to evaluate
on-site storage of secondary effluent prior
to tertiary treatment. Final design responsibilities included civil and yard piping, mechanical and process design for drawing production, specification preparation, and
cost estimating.
 Project engineer for the Regional Treatment Plant Headworks Upgrade for the South Orange County Wastewater Authority, California. The project involved production of drawings and contract documents for replacement of the headworks building
roof; rehabilitation of the existing mechanical bar screens; installation of new conveyors, screenings dewatering equipment, level measurement equipment in the existing
channels for bar screen controls, and gas
analyzers; channel concrete repair; odor
control; and electrical and instrumentation
modifications and upgrades. Roof replacement also incorporated a temporary odor control system with focus on the contractor’s responsibility in capturing odors. He provided construction management services, submittal review, and responses to contractor requests for information.
 Project engineer for the Coastal Treatment Plant Return Activated Sludge Flow Control Analysis for the South Orange
County Wastewater Authority, California.

The plant operates two sets of aeration basins, with different depths and no automatic control for adjusting the flow split and flow
rate of return activated sludge (RAS). The
analysis evaluated methods of improving
the existing RAS system. The project also included recommendations for six improvement projects with various degrees of cost and difficulty. The client approved three of
these for design.
 Project engineer for the Coastal Treatment Plant Return Activated Sludge (RAS) System and Headworks Upgrades for the
South Orange County Wastewater Authority, California. Preliminary design included identification of reliable rotary drum screen
manufacturers for raw wastewater screening
including customer surveys, site visits, cost
estimating, and detailed review of manufacturer specifications. Plans and specifications were prepared for replacement of the existing drum screens, replacement of the headworks influent force main knife gate valves, and other minor modifications to the headworks building. The plans and specifications also included design improvements to the
return activated sludge system as previously
identified in the RAS Flow Control Analysis.

He provided construction management services, submittal review, and responses to contractor requests for information.
 Project engineer for the Coastal Treatment Plant Aeration Blower Capacity Analysis for the South Orange County Wastewater Authority, California. The plant
operates two sets of aeration basins with
different depths, air demands, and blower
discharge pressures. The study involved
analysis of the existing blowers, plant flows,
aeration basin loading, and dissolved oxygen levels to determine the air demands for the various configurations of aeration basin
operation. Blower upgrade alternatives were
developed and analyzed for life-cycle costs
based on capital and annual costs for power
and cooling water consumption. Installation
of turbine blowers was recommended to allow better control of air delivery to the aeration basins.
 Project engineer for the Water Reclamation Plant Headworks Upgrades for the City of San Clemente, California. The design included drawings and contract documents for concrete repair and relining of the headworks influent channels and grit basins and replacement of mechanical bar screens. Relining of channels required design of a temporary bypass facility, including manual bar screens and odor control, with focus on the
contractor's responsibility to maintain and
operate the facility. He provided construction management services, submittal review, and responses to contractor requests
for information.

Education
MS Environmental
Engineering, University of
California, Berkeley, 2005
BS Civil Engineering,
California State
University, Fresno, 2003
Licenses
Civil Engineer, California,
Nevada
Professional
Affiliations
Nevada Water
Environment Association
American Water Works
Association
Timothy J. Loper, P.E.

Timothy Loper has 20 years of experience in wastewater collection system modeling, water distribution system modeling, water system feasibility studies, wastewater treatment facilities planning, and infrastructure master planning.

Relevant Experience
 Quality control engineer for the City of
Banning, California, Water and Wastewater
Master Plan. The project involved updating
the City’s water, sewer, and recycled water
master plans into an integrated master plan
to guide the City with budgeting and implementation of capital improvement projects.

Responsible for quality review and project
oversite and technical direction.
 Project engineer for the Elsinore Valley
Municipal Water District, California,
Wastewater Master Plan. Responsible for
coordination of GIS integration into the hydraulic model environment and construction of a SWMM model incorporating four separate collection system stations with
three wastewater treatment facilities. Capital
project recommendations were made to
serve future growth and system modifications were analyzed to eliminate lift stations and force mains with gravity sewers. The
project also involved preparation of a master plan report, including a capital improvement program. The project also developed a Sewer System Management Plan for all
four of the District’s separate
collection systems.
 Collection system lead for the City of
Riverside, California, Comprehensive
Wastewater Master Plan, which included
both treatment and wastewater collection
systems. Carollo built the City’s collection
system model using the Innovyze
InfoSWMM modeling software.
 Project manager for Vallejo Flood and
Wastewater District, California, Collection
System Master Plan. Responsible for day-today management and technical direction, including District and subconsultant coordination, progress meetings, and communication. Provided technical direction for development of the flow monitoring program, hydraulic model construction and calibration, and development of the inspection and rehabilitation program.
 Collection system lead for the West
County Wastewater District, California, District-Wide Master Plan. The project included the sanitary sewer collection system, Water
Pollution Control Plant, and non-process facilities, such as administration, laboratory, storage, and maintenance. Work efforts included condition and capacity assessments, alternatives evaluation, and 20-year capital
improvement program development. All the
District’s facilities were combined in one
master plan, allowing the needs of each to
be prioritized in an overall program. Other
work efforts included a risk-based analysis
of all 12,000 assets to identify failure likelihood, BioWin modeling to assess capacity, 3-D computational fluid dynamics modeling
of secondary basins to optimize performance, and a wet weather capacity improvements assessment of the 249-mile collection system.
 Project manager for the City of Shasta
Lake, California, 2016-2026 Water Master
Plan. The project involved development of a
new water system hydraulic model based
on the City’s most recent GIS database of
the water distribution system. The water distribution system hydraulic model was developed using the Innovyze InfoWater hydraulic modeling software package. The hydraulic model was calibrated using a three-step calibration approach, including a macro calibration, steady state (fire flow test) calibration, and extended period simulation calibration.
 Project manager for the City of Millbrae,
California, Water System Master Plan. Carollo was contracted to complete a water master plan that provided a capital improvement program to help mitigate storage deficiencies and hydraulic constraints caused by the separation of the City’s four
pressure zones. Responsible for update and
calibration of the hydraulic model, which
was developed in InfoWater. The City’s primary concern was lack of storage in the lower pressure zone and the potential for
Timothy J. Loper, P.E.
emergency outages in the event of a large
earthquake. Carollo conducted a seismic
evaluation of the water storage tanks, optimization of storage needs for the lower zone, and rehabilitation of existing tanks.
 Project engineer for the City of
Oceanside, California, Integrated Master
Plan, which included a new collection system hydraulic model prepared from GIS data using InfoSWMM. The existing system
was evaluated with respect to existing and
future capacity needs. The master plan also
considered a phased plan for replacement
of the City’s water and wastewater pipelines
as part of the rehabilitation and
replacement program.
 Collection system project manager for
the Central Contra Costa Sanitary District,
California, Comprehensive Wastewater Master Plan. The project involved conducting a pump station condition assessment and developing a force main inspection program and a large-diameter condition and rehabilitation plan. The project also included creation of a collection system asset management plan. The master plan focused on pump stations, force mains, and collection
system assets and summarized the District’s
assets in detail.
 Project manager for the City of Fresno,
California, Wastewater Collection System
Master Plan. The project identified capacity
constraints within the existing collection system and provided recommendations for infrastructure improvements necessary to accommodate densification and future growth, including future industrial growth.

The master plan included an update of the
City’s sewer rehabilitation project capital
improvement plan.
 Project manager for City of Tulare, California, Sewer, Water, and Storm Drain Master Plans and Sewer System Management Plan. The project developed master planning documents for infrastructure improvements to serve rapid growth within the City.

Responsible for coordination of the water,
sewer, and storm drain computer models
that integrate GIS databases into the modeling platform. The wastewater collection system included industrial and domestic
collection systems with separate treatment
facilities. The storm drain task required coordination with the Tulare Irrigation District for discharge of storm water from the City’s
drainage facilities.
 Project manager/project engineer for
the Madera County, California, Community
Services Area No. 3 (CSA-3) Infiltration and
Inflow (I/I) Evaluation and Sewer Capacity
Study. CSA-3 is a community services district outside of the City of Madera. The wastewater generated by CSA-3 is conveyed to the City’s collection system via a 10-inch-diameter sewer trunk and is metered in a 3-inch Parshall flume. Winter flows from CSA-3 are subject to high I/I
rates that submerge the flume. Carollo developed a temporary flow monitoring program that identified ten metering locations and collected flow for six weeks during the
winter of 2009/2010. Responsible for dayto-day project management and technical direction. Developed a hydraulic model of
the system and calibrated the model to dry
and wet weather conditions using flow
monitoring data. Was instrumental in discussions between the City of Madera and the County of Madera on allowable
wastewater flows per the agreement between the City and the County. Carollo developed capital projects to mitigate existing system deficiencies and sized a new lift station for buildout flows. Carollo also made recommendations on locations for CCTV inspection and smoke testing for detailed identification of I/I.
 Project manager for the Santa Cruz
County Sanitation District, California, 2017
Inflow and Infiltration (I/I) Study. Led the I/I
study, which included a flow monitoring
program, updates and calibration of the
County’s InfoSWMM sewer collection system hydraulic model based on flow monitoring data, and simulation of the effect of a 10-year design storm on the County’s sewer
collection system.

Education
BS Civil Engineering,
California State
University, Fresno, 2006
Licenses
Civil Engineer, Nevada,
California
Professional
Affiliations
American Water Works
Association
California Water
Environment Association
– Central San Joaquin
Section
Ryan F. Orgill, P.E.

Ryan Orgill has 18 years of experience in master planning, hydraulic modeling, sewer system management planning, urban water management planning, and geographic information systems (GIS). He serves as Carollo’s companywide lead for sewer system modeling, calibration, and system analysis. In addition, Ryan developed Carollo’s means and methods for sewer system planning that have been adopted companywide and is an expert in delivering projects that incorporate all critical elements of collection system capital program needs.

Relevant Experience
 Project manager for the City of Scotts
Valley, California, Sewer Master Plan. As part
of the project, Carollo developed a collection system hydraulic model of the City’s sewer system and conducted a capacity
analysis of the system under existing and
future flow conditions.
 Project manager for City of Chino Hills,
California, Citywide Wastewater Master Plan
Update. This ongoing project will update
and evaluate the City’s wastewater collection system hydraulic model. The project scope also included coordinating with a
pipe inspection contractor to inspect up to
20 miles of pipeline.
 Project engineer for the City of Torrance,
California, 2020 Sewer Master Plan. This
project involved sewer system model development, calibration, analysis, and preparation of a phased capital improvement plan.

Flow monitoring data was used to calibrate
the model for both dry and wet
weather conditions.
 Project manager for the Padre Dam Municipal Water District, California, 2020 Comprehensive Facilities Master Plan Update.

This integrated master plan involves updating the District’s water, wastewater, and recycled water infrastructure. This project includes (recycled) water demand/sewer flows forecasting, water supply analysis, hydraulic
modeling updates for the water and recycled water systems, development and calibration of a new sewer model, and field condition assessment of key facilities with operations staff.
 Project manager for the South Tahoe
Public Utility District, California, Sewer System Hydraulic Model. No changes or updates had been made to the District’s wastewater collection system model that
was created 10 years ago using the Innovyze
InfoSewer hydraulic modeling software. In
the last decade, additional infrastructure
construction and collection system changes
have been made. This contract allowed for
on-call hydraulic modeling support to evaluate the existing model, identify potential improvements, and convert the model
to InfoSWMM.
 Engineer for the City of Oceanside, California, Sewer System Master Plan. Responsible for system evaluation, hydraulic modeling, development of the Sewer Master Plan report, and custom model training for
City staff.
 Project engineer for the Elsinore Valley
Municipal Water District, California, Sewer
System Management Plan, which involved
development and review of all applicable
SSMP requirements, including a system
evaluation and capacity assurance plan.
 Staff engineer for the Port of Oakland,
California, Phase I Sewer System Management Plan, which included development of a Port-specific overflow emergency response plan; fats, oils, and grease control plan; sanitary sewer use ordinances; operations and maintenance recommendations; and sanitary sewer design standards.
 Project engineer for the City of Hanford,
California, Sewer System Management Plan,
which involved development or review of all
applicable SSMP requirements, including an
overflow emergency response plan and a
review of the City’s most recent sewer system master plan, design standards, and sewer ordinances.
 Project engineer for the City of Pismo
Beach, California, Sewer System Management Plan, which included development of a fats, oils, and grease control plan.

Ryan F. Orgill, P.E.
 Project engineer for the City of Hughson, California, Sewer System Management Plan, which was developed as part of the
City’s Water, Sewer, and Storm Drainage
Master Plan project. The project involved
development of many of the SSMP elements, including a system evaluation and capacity assurance plan, overflow emergency response plan, and a fats, oils, and grease control plan.
 Project engineer for the City of Tulare,
California, Sewer, Water, and Storm Drainage Master Plans and Sewer System Management Plan. Tasks included creation and calibration of a dynamic hydraulic sewer
system model to evaluate flow monitoring
data, development of flow routing criteria,
and evaluation of the existing sanitary sewer
system to mitigate deficiencies and serve
future growth.
 Staff engineer for the City of Galt, California, Wastewater Collection, Water Distribution, and Storm Drainage Master Plans.

Responsible for calibration of the hydraulic
computer model to both dry weather and
wet weather conditions, assistance with
preparation of the Master Plan report, and
development of a staged capital
improvement plan for the City.
 Project manager for the Truckee Sanitary
District, California, 2017 Hydraulic Modeling
Assistance. Carollo assisted the District with
development and calibration of three of the
four existing wastewater collection system
models. The models were calibrated to peak
dry and peak wet weather flow conditions
using flow monitoring data from the 2016
and 2017 storm season.
 Hydraulic modeling lead for the City of
Modesto, California, Wastewater Collection
System Master Plan. The hydraulic model
was originally constructed in H2OMap
Sewer as part of the previous master plan. In
advance of the wastewater collection system master plan update, the City contracted with Carollo to convert the hydraulic model
from H2OMap Sewer to the more advanced
InfoSWMM platform. Responsible for updating and recalibrating the InfoSWWM hydraulic model, which involved more sophisticated simulation of storm drainage system cross connections within the InfoSWMM
model. Also responsible developing existing
and future wastewater flow projections, improvement alternatives to mitigate existing capacity deficiencies and serve future
growth, and a capital improvement plan.
 Project engineer for the City of Fresno,
California, Collection System Master Plan.

Responsible for hydraulic model update and
calibration of the City’s all-pipe sewer system hydraulic model under dry and wet weather conditions, development of improvement projects to mitigate capacity deficiencies, and development of a capital improvement plan for the City.
 Collection system engineer for the West
County Wastewater District, California, District-Wide Master Plan. Responsible for preparation and calibration of a dynamic
collection system model to evaluate wet
weather storm events to simulate existing
flow conditions.
 Project engineer for the City of Turlock,
California, Sanitary Sewer and Storm Water
Master Plans. Responsible for overseeing
the construction of the City’s sewer and
storm drainage system hydraulic models.

The City’s sewer collection system includes
numerous direct storm drainage connections to the sewer system in the City’s downtown area. As part of the analysis, several improvement alternatives were considered to alleviate capacity deficiencies in the sewer collection system. Preferred improvements to the sewer and storm drainage systems were incorporated into the Sanitary Sewer and Storm Water Master
Plan reports.
 Project engineer for the City of Chico,
California, Sanitary Sewer Master Plan Update. Responsible for conversion and update of the City’s previous HYDRA collection system model to the InfoSWMM hydraulic
modeling software application. Buildout average and peak flows were projected for future land use areas, as identified in the City’s General Plan Update. The project was calibrated to dry and wet weather flow conditions, and the collection system was analyzed under current and buildout peak flow conditions
Education
MS Civil Engineering,
California State
University, Fresno, 2013
BA Mathematics,
California State
University, Fresno, 2011
Licenses
Civil Engineer, California
Professional
Affiliations
American Society of Civil
Engineers
Joaquin D. Ramirez, P.E.

Joaquin Ramirez’s experience includes hydraulic modeling, master planning, and geographical information systems (GIS). He has developed and performed hydraulic modeling for clients across the nation, including Pacific States, Nevada, Texas, and Colorado.

Relevant Experience
 Staff engineer for the City of Modesto,
California, Wastewater Collection System
Master Plan. Responsible for recalibration of
the existing hydraulic computer model;
development of dry and wet weather flows.

Developed improvement projects to
mitigate capacity deficiencies, capital
improvement cost estimates, and
preparation of the technical report. The
project also included development of future
infrastructure to service projected growth.
 Staff engineer for the City of Modesto,
California, River Trunk Realignment, Beard
Brook Siphon, and Cannery Segregation
Line Improvements. Responsible for
assisting with design, sizing the new sewer
alignment, and modeling the future system.

Assisted in preparation of technical
documentation outlining design criteria and
planning. Numerous alternatives were
modeled in an effort to present the City with
viable options.
 Staff engineer for the Inland Empire
Utilities Agency, California, Wastewater
Facilities Master Plan Update, which includes
planning for infrastructure needs for the
Agency’s collection and treatment systems
through the year 2035, with flow projections
up to 2060. Responsible for incorporating
alternatives into a hydraulic model,
designing infrastructure to support future
development and multiple flow diversions,
and developing capital improvement
cost estimates.
 Staff engineer for Padre Dam Municipal
Water District, California, Comprehensive
Facilities Master Plan. This project was an
update to the 2001 Integrated Facilities Plan,
which addressed water, wastewater, and
recycled water services within the District’s
region through 2020. Responsible for
identifying pipe alignment with capacity
limitations and developing improvements
according to design criteria. Also developed
a capital improvement plan to assist the
District with project implementation.
 Staff engineer for City of Oceanside,
California, Integrated Master Plan.

Responsible for developing supporting
documentation for Master Plan and
performing a system analysis for the
sewer system.
 Project engineer for the City of Banning,
California Integrated Master Plan.

Responsible for calibration of the sewer
hydraulic model using InfoSWMM modeling
software. Performed a system evaluation
under existing and future conditions and
assisted in development of a capital
improvement plan.
 Project engineer for the City of Fresno,
California, Wastewater Collection System
Hydraulic Model Update. Responsible for
recalibration of the existing hydraulic
computer model and development of dry
and wet weather flows. Developed
improvement projects to mitigate capacity
deficiencies, and preparation of the
technical report.
 Project engineer for the City of Lemoore,
California, Integrated Master Plan.

Responsible for construction of the City’s
hydraulic model using InfoSWMM software
and calibration of the model. The hydraulic
model was used to perform capacity
analyses under multiple planning years and
aid in development of the City’s capital
improvement plan.
 Project engineer for the City of Lake
Havasu, Arizona Lift Station and Force Main
Analysis. Responsible for evaluation of lift
station and pump curves to determine
compatibility with proposed configuration
 Project engineer for Henderson Nevada,
Cadence Utility Master Plan Update. Task
included determining required backbone
infrastructure for water and sewer needs of
planned development.

Joaquin D. Ramirez, P.E.
 Project engineer for the City of Visalia,
California, Sanitary Sewer Master Plan.

Responsible for recalibration of the existing
hydraulic computer model. Development of
dry and wet weather flows, improvement
projects to mitigate capacity deficiencies,
and preparation of the master plan report.
 Staff engineer for the City of Turlock
California, Facility sizing and Preliminary
Design Report. Updated the City’s
distribution system hydraulic model to aid in
sizing a new storage tank, booster pump
station, and pipeline expansion.
 Staff engineer for City of Tulare
California, City of Tulare and Matheny Soultz
System Improvements. Updated the City’s
existing hydraulic water model. Performed
capacity analyses of the City’s supply,
storage and pipelines.
 Staff engineer for the City of Porterville
California, Integrated Water and Storm
Master Plan. Utilized the City’s hydraulic
models to perform capacity analyses of the
water distribution system and storm water
conveyance system under multiple planning
years. Aided in development of the City’s
capital improvement plan.
 Project engineer for Henderson Nevada,
Backbone Water Infrastructure Study. Task
included evaluation of the water distribution
system to determine the viability of a new
Backbone pipeline configuration.
 Staff engineer for City of Paso Robles
California, Recycled Water Distribution
System Design. Utilized hydraulic modeling
software to perform capacity analyses under
and assist with pipeline design.
 Staff engineer for the City of Fresno
California, Recycled Water Model
Development project. Responsible for
construction of the City’s recycled water
hydraulic model. The hydraulic model was
used to perform capacity analyses under
varied demand conditions and evaluate the
systems existing capacity and future needs.
 Project engineer for Santa Fe New
Mexico, Reuse Pipeline Conveyance
hydraulics and Alternatives. Performed
hydraulic analysis to evaluate the feasibility
of using existing pipeline to convey
reclaimed water from reclamation facility to
the Rio Grande.
 Staff engineer for the City of Clovis,
California, 2015 Urban Water Management
Plan. Responsible for updating the City’s
2010 Urban Water management plan. The
update included a description of the City’s
service area, water supply, reliability
planning, water use, supply and demand
comparison, water shortage contingency,
and water recycling.
 Staff engineer for the City of Merced,
California, 2015 Urban Water Management
Plan. Responsible for updating the City’s
2010 Urban Water management plan. The
update included a description of the City’s
service area, water supply, reliability
planning, water use, supply and demand
comparison, water shortage contingency,
and water recycling. This plan has been
approved by the City council.
 Investigated the influence of the San
Joaquin River flow on the migration of
Chinook salmon and evaluated ideal
conditions regarding migration.
 Collected data on greenhouse gas
emissions for the City of Chowchilla,
California, and compiled a report
categorizing department and
equipment emissions.
 Staff engineer for the City of Fresno,
California, Southeast Surface Water
Treatment Facility Design. Responsible for
collecting raw surface water samples for
analysis, assisting with jar testing, and
cataloging field data.

Education
BS Civil Engineering,
University of Nevada,
Reno, 2017
Licenses
Professional Engineer,
Nevada
Grace N. Mitzel, PE
Grace Mitzel joined Carollo in 2015 as an engineering intern and began full time in 2017 as a staff professional for infrastructure planning. She assists with development and analysis of water, wastewater, and stormwater collection systems, as well as development of technical memoranda for evaluation of system information and data and model analysis.

Relevant Experience
 Staff professional for the City of Lemoore, California, Water, Sewer, and Wastewater Treatment Master Plan. Responsible for assistance with development, assembly, and calibration of the hydraulic
water model; assistance with a system analysis and recommendations for system enhancements; and assistance with development of the Water Master
Plan report.
 Staff professional for the Santa Cruz
County Sanitation District, California, Phase I
Inflow/Infiltration (I/I) Mitigation Program.

Responsible for developing a temporary
flow monitoring program, providing assistance with an I/I evaluation, recalibrating the hydraulic model, assisting with a system
analysis, and assisting with preparation of a
technical memorandum.
 Staff professional for the Marin Municipal Water District, California, Pine Mountain Tunnel Storage Transmission Analysis. Responsible for inputting facilities and pipelines into the existing hydraulic model, ensuring each model scenario includes the proper facilities, and assisting with preparation of a technical memorandum to present the findings of the analysis.
 Staff professional for the City of Morro
Bay, California, OneWater Morro Bay Engineering and Planning. Responsible for developing a stormwater hydrologic model, assisting with calibration of the hydraulic
water model, and assisting with
development of the project
technical memoranda.
 Staff professional for the City of Porterville, California, Integrated Master Plan. Provided engineering services for preparation of sanitary sewer, water system, and storm
drain master plans; recycled water feasibility
study; and storm water resources plan. Responsible for assembling and calibrating the hydraulic water model and assisting with
development of a water distribution system
master plan and capital improvement plan.
 Staff professional for the City of West
Sacramento, California, Water Master Plan
Update. The project goal was to identify
capital projects to serve existing customers
and develop a recommended plan for the
projected increase in demand associated
with the City’s General Plan Update. Responsible for updating the hydraulic model to include improvements made by the City,
running a fire flow analysis, identifying deficient fire flow nodes, and developing a memorandum presenting analysis findings.
 Engineering intern for the City of Riverside, California, Comprehensive Wastewater Master Plan. Responsible for assisting with
hydraulic model development by creating
wastewater loading polygons, as well as
assisting with model calibration.
 Engineering intern for the Mountain
House Community Services District, California, Wastewater Treatment Plant Expansion Wastewater Flow Projections. Responsible
for evaluating wastewater flows to summarize wastewater flow rates and developing land use based wastewater flow factors.
 Staff professional for the Washoe
County, Nevada, Pleasant Valley Interceptor
Reach 3 Preliminary Design. The project involved preliminary design and 30-percent cost estimates for two alternatives recommended in the alternatives study. Responsible for conducting an evaluation of the existing collection system, analyzing the impacts of the Bella Vista Ranch development on the system and facilities, and preparing a
letter report to present the findings. Additional responsibilities included updating the facility plan to include additional facilities
and developing a cost estimate for the
additional facilities.

Grace N. Mitzel
 Engineering intern and staff professional
for the Washoe County, Nevada, Pleasant
Valley Interceptor (PVI) Reach 3 and 4 Alternatives Study. The study documented the development and evaluation of alternatives
for PVI Reach 3 and Reach 4 in the South
Truckee Meadows wastewater collection
system, which is operated by the Washoe
County Department of Water Resources. Intern responsibilities included placing manholes on alternative alignments and developing pipeline alignments for septic user connection. Staff professional responsibilities included reviewing and editing the technical memorandum.
 Staff professional for the City of Scottsdale, Arizona, Integrated Water Resources Master Plan. This project consists of a comprehensive update of the City’s previous IWRMP, which was over a decade old, and
subsequent water and reclamation master
plans. The new IWRMP established the
framework to meet the City’s future water
resources, water quality, and water infrastructure needs through the planning horizon of 2055.
 Staff professional for the South Tahoe
Public Utility District, California, Hydraulic
Modeling Support. For the water distribution system model, Carollo developed a hydraulic model users guide, conducted model training, developed a pilot unidirectional flushing program, analyzed the development of District Metered Areas for the Stateline Pressure Zone, and conducted
other modeling-related tasks. For the
wastewater collection system model, Carollo
converted the District’s existing InfoSewer
model to InfoSWMM, helped the City implement a permanent flow monitoring program, calibrated the InfoSWMM model to dry and wet weather conditions, conducted
an analysis of the system’s response to a
design storm event, and conducted
hydraulic model training with the City.
 Staff professional for Vallejo Flood and
Wastewater District, California, Wastewater
Collection System Master Plan Update. This
project is ongoing and involves a condition
assessment of more than 375 miles of collection system pipeline. Pipelines were grouped into inspection and replacement
years based on condition scores and/or age
and estimated remaining useful life for a
comprehensive long-term rehabilitation and
replacement program. The project also includes a hydraulic analysis, using InfoWorks ICM, of pipes 10 inches and larger to identify
capacity deficiencies and develop
recommended improvements.
 Staff professional for the City of El Paso,
Texas, Boone Siphon Analysis. This project
consisted of conducting a hydraulic analysis
of the existing Boone Siphon to accommodate additional flows diverted as part of a sewer infrastructure project. Staff professional responsibilities included converting the hydraulic model from InfoSewer to InfoSWMM, validating the hydraulic modeling results, evaluating the hydraulic capacity of
the siphon, and assisting in developing
bypass recommendations.

Education
MS Civil and
Environmental
Engineering, Stanford
University, 2015
BS Civil and
Environmental
Engineering, University of
Illinois at UrbanaChampaign, 2014
Licenses
Civil Engineer, California
Certifications
Certified, Envision™
Sustainability
Professional, Institute for
Sustainable
Infrastructure, 2020
Professional
Affiliations
American Water Works
Association – Climate
Change Committee Vice
Chair
Rachel S. Duncan, P.E., ENV SP
Rachel Duncan is a civil engineer who specializes in climate change vulnerability assessments for water and wastewater infrastructure and water supply planning projects with an emphasis on climate change impact modeling and analysis, alternatives analysis, and decision modeling. She has additional experience in recycled water project planning and design, permitting, funding, and hydraulic modeling. Rachel is a graduate of Stanford University’s Sustainable Design and Construction program with a focus in water resources. Her studies at the University of Illinois at Urbana-Champaign centered on sustainable and resilient infrastructure systems as well as environmental economics and law.

Relevant Experience
 Lead engineer for the One Water 2050
Plan, City of South Pasadena, California.

Carollo developed this Plan for South Pasadena to assess water and wastewater facility needs through 2050. Rachel developed future water demand projections and supply analysis as well as projections for recycled
water demands and wastewater flows. Rachel documented existing and potential future potable and recycled water supplies that may be required to meet
future demand.
 Assistant project manager for the Joint
Water Commission Water System Master
Plan, Joint Water Commission, Oregon. Carollo is updating JWC’s Master Plan to evaluate the capacity and resilience of their water system and to develop a comprehensive
capital improvement program to meet their
level of service goals. As the assistant project manager, Rachel coordinated with the client and large project team to ensure
smooth delivery of the Master Plan. She also
conducted the 20-year demand analysis
and supply strategy development for the
Master Plan.
 Project engineer for the Northwest
County Recycled Water Strategic Plan, City
of Palo Alto, California. While with her previous firm, Rachel completed a demand analysis for recycled water users along the proposed pipeline alignment and created a hydraulic model of the system for pipeline and pump station sizing. She also contributed to
the business plan for the project by comparing non-potable, indirect potable, and direct potable recycled water alternatives for
the City.
 Project manager for the Recycled Water
Program Development Recycled Water User
Guide, City of Lathrop, California. While with
her previous firm, Rachel led the development of a Recycled Water User Guide, updates to City documents including the Recycled Water Ordinance, and supported for Site Supervisor Training.
 Project manager for the Recycled Water
Permitting, City of Lathrop, California. While
with her previous firm, Rachel completed
various Recycled Water Storage and Conveyance System Improvements Completion Reports and the Recycled Water User Reports for multiple expansions of the City’s recycled water system. Regional Water
Board compliance was required for the expansion of the recycled water system to appropriately manage recycled water use and disposal near the ecologically-sensitive
Sacramento-San Joaquin River Delta.
 Project engineer for the Valley Water Expedited Purified Water Program in San Jose, California. While with a previous firm, Rachel
contributed to the development of facilities
plans and preliminary cost estimates for indirect and direct potable reuse facilities, including advanced water purification facilities, conveyance facilities, injection wells, and percolation ponds. She also coordinated with the project team to develop a Program Plan that summarized the potable
reuse alternatives and selected a
recommended alternative.
 Project engineer for the Water Recycling
Study Report, City of Victorville, California.

While with her previous firm, Rachel supported the project by authoring the water supply characteristics and facilities chapter
of the Report, which included researching
the Mojave Groundwater Basin and related
Rachel S. Duncan, P.E., ENV SP
regulations as well as the quality and reliability of recycled water required to meet power plant cooling tower needs. The Study
presented information relevant to water recycling in the study area, identified quantitative and qualitative recycled water needs for major industrial users, and to evaluated and
recommended a project to meet
these needs.
 Project engineer for the North Valley Regional Recycled Water Program, City of Modesto and Del Puerto Water District, California. While with her previous firm, Rachel assisted with project permitting including
right of way crossings for roads and railroads, environmental permitting, and land use permitting with local agencies. The project will bring tertiary treated wastewater generated by the cities of Modesto, Turlock,
and Ceres to the agricultural customers
within the Del Puerto Water District via the
Delta Mendota Canal.
 Lead engineer for the Denver One Water Plan, City and County of Denver, Colorado. Carollo is developing a One Water Plan for Denver that creates a coordinated
framework to address the current and future water management challenges including rapid development and climate change.

Rachel reviewed existing water management planning and policy documents to identify what has already been done and
where potential gaps or inconsistencies exist
that could be resolved with the implementation of a One Water Plan. She will work with the core planning team of local and regional water managers to define a vision and set goals for the implementation of the
One Water Plan.
 Engineer for the Integrated Resources
Plan, City of Aspen, Colorado. Carollo is developing this plan for Aspen to assess potential future water demands and project alternatives to meet those supply needs. Rachel evaluated the vulnerability of current and potential future supplies to threats including, but not limited to, wildfire, drought, avalanche, aging infrastructure, and malevolent acts. She built a water supply model to evaluate potential water supply alternatives
and their ability to mitigate expected future
water shortages and increase resiliency
against identified threats.
 Lead engineer for the Climate Change
Water Resources Monitoring and Adaptation Plan, California Water Service. This Plan includes a review of existing vulnerability assessments and adaptation planning efforts, a vulnerability assessment of Cal Water’s infrastructure, operations, and services, and an assessment of climate change impacts to
water supply and demand. Rachel is leading
the water supply and demand assessment
and will analyze how climate change is expected to impact surface water, groundwater, and imported water supplies. The expected impact to each water supply source will be compared across all Districts to allow
for the prioritization of Districts to mitigate
near-term, medium-term, and long-term
impacts. The project team will develop adaptation strategies to reduce vulnerability to climate threats, prioritizing strategies based
on adaptation pathways and
investment considerations.
 Lead engineer for Risk and Resilience
Assessments for over 20 different cities and
water agencies in 11 different states. In response to requirements in America’s Water Infrastructure Act, Carollo is conducting risk
and resilience assessments to evaluate the
natural hazard and security risks to water
assets for cities and water agencies across
the country. Rachel has evaluated the risk to
assets from natural hazards including, but
not limited to, coastal and inland flooding,
wildfire, hurricanes, severe storms, tornados,
extreme heat, and drought. In addition to
evaluating existing risk, she documented
how these risks are likely to be impacted by
climate change and how hazards may become more or less frequent or severe in the future. She recommended adaptation strategies to mitigate high-priority risks.

Education
MGIS, Penn State
University, 2017
BA Geography, California
State University,
Northridge, 2001
AA Geology, Pasadena
City College, 1997
Certifications
Certified Geographic
Information Systems
Professional (GISP),
Geographic Information
Systems Certification
Institute, 2012
Jackie M. Silber, GISP
Jackie Silber is a geographic information systems (GIS) lead with 20 years of professional experience in GIS and technical training. Her experience includes geospatial GIS analysis for water resource planning, environmental remediation sampling, and demographic forecasting projects. Her GIS skills focus on geodatabase design and optimization, manipulation and conversion of projections, CAD and KML to GIS conversion, spatial analysis, automation of repetitive analysis using Model Builder and Python, and creation of cartographic figures.

Relevant Experience
 GIS specialist for the 2020 Integrated
Water Master Plan and Urban Water Management Plan for Padre Dam Municipal Water District, California.
 GIS specialist for the San Gabriel Valley
Water Company Water System Master Plan
Update, California. In addition to developing
figures illustrating system deficiencies, Ms.

Silber also developed a Python script to
loop through an 11 million record table and
sum the total water demands for
every customer.
 GIS specialist for the 2020 Integrated
Water Master Plan and Urban Water Management Plan for Padre Dam Municipal Water District, California.
 GIS specialist for One Water LA 2040
Plan, California. Ms. Silber created
cartographic figures of wastewater and
stormwater pumping plant prioritization
based on current and/or future climate
hazard risks.
 GIS specialist for the 2019 Financial Master Plan Outdoor Budget Allocation for Monte Vista Water District in Montclair, California. Ms. Silber led the GIS image analysis to determine the area of permeable surface
area by parcel based on economic community type. This analysis helped the District to determine the amount of potable water
used for irrigation.
 GIS lead for the Cal Water Strategic Asset Management Plan, California Ms. Silber assisted with likelihood of failure and consequence of failure water pipeline analysis to establish asset management procedures for
Cal Water’s Willows District.
 GIS specialist for the Hydraulic Model
Implementation for Suburban Water Systems in Whittier, California. Ms. Silber created pressure system surface figures to compare water pressure modeling results
throughout the system.
 GIS specialist for the Antelope Valley
East Kern Water Agency in Palmdale, California. Ms. Silber consolidated land use patterns and developed water system and capital improvement plan figures.
 GIS specialist for OneWater 2050 Plan
for the City of South Pasadena, California.

Ms. Silber developed figures based on hydraulic modeling results of recommended fire flow improvements to address deficiencies as well as minimum and maximum pressures throughout the District.
 GIS specialist for the Water Distribution
System Infrastructure Plan for the City of
Santa Barbara, California. Ms. Silber developed an ArcGIS Online Collector web app and figures for field crew to capture results
of fire hydrant testing.
 GIS acting project manager for the GIS
and Hydraulic Model Hosting and Maintenance Services project for Mesa Water District, California. Ms. Silber created five web applications to assist department leads and
field crew access and search the District’s
GIS data. In addition, she worked with the
District to develop a customer outage text
notification system which allow Operation
staff to identify valves that will be out of service. The web app performs a network trace of the customers that will be affected and
sends the information to the Public Affairs
Department who contact the customers.

Provide on-going GIS support to the District
for other projects including the annual
water loss audit.

Jackie M. Silber, GISP
 GIS lead for the Mesa Water District,
Free Chlorine Conversion Study, California.

Ms. Silber developed figures to illustrate the
supply sources at different
demand conditions.
 GIS specialist for the 2020 Urban Water
Management Plan for the City of Big Bear
Lake, California.
 GIS specialist for City of San Diego,
Stormwater Recovery Feasibility Study,
California. Ms. Silber provided geospatial
analysis and created figures of 19
preliminary sites selected for stormwater
best management practices (BMP). BMP
parcel analysis was based on parcel slopes,
location in relation to bedrock and
groundwater basins, potential for high
runoff and proximity to storm water
conveyances. Drainage runoff was
calculated based on assumed annual
precipitation from the Western Regional
Climate Center data for San Diego.
 GIS specialist for the Central Contra
Costa, Sanitary District Comprehensive
Resiliency Adaptation Plan, California. Ms.

Silber created figures for a technical
memorandum related to assessing the
resiliency of the District collection system
facilities to withstand the effects of climate
changes and flooding from high tides and
precipitation events.
 GIS specialist for City of Omaha, OPW
53820 Cole Creek CSO Phase 4 Sewer Separation, Nebraska. Ms. Silber organized the geodatabase files and created figures of
sewer separation alternatives, historical
flooding, and smoke testing. as well as estimated the population served by the construction of new storm and sanitary sewers using 2020 Census population data.
 GIS lead for the City of West Linn Stafford, Area Sewer Evaluation, Oregon. Ms.

Silber developed watershed drainage basins
based on DEMs to determine the urban reserve areas that could be served by the City’s existing sanitary sewer system
by gravity.
 GIS specialist for a Long-Range
Wastewater Management Plan for the City
of Renton, Washington. As part of the pipe
risk approach, Ms. Silber developed an
ArcGIS-based criticality and vulnerability
model. The model identified and prioritized
critical assets near key infrastructure or that
are susceptible to failure.
 GIS specialist for the Charleston Water
System, Water Distribution Master Plan
Update, South Carolina. The project involves
the update of the master plan and the
development of the next 20-year Capital
Improvement Plan for the water distribution
system. The project includes review and
calibration of the existing all-pipes,
development of water demand projections,
and use of the calibrated model to support
the existing and future system evaluation,
criticality analysis, and development of
CIP projects.
 GIS specialist for the City of Medford,
Sanitary Sewer Master Plan, Oregon. To
help the City anticipate future needs, Ms.

Silber, developed figures illustrating the locations of high I/I due to sewer trunk line deficiencies. Also investigated existing and
future land use changes per parcel as part
of a wastewater capital charge per
equivalent residential unit analysis.
 ArcGIS online administrator/technical
advisor for the City of Houston, Northeast
Water Purification Plant, Texas. Ms. Silber
managed user access and advised Carollo
staff on data management in ArcGIS
Online/Collector.
 GIS specialist for King County Clean
Water Program, Seattle, Washington. Ms.

Silber created figures for the Action
Decision Sheet deliverable which includes
figures of combined sanitary overflow (CSO)
action plan and legacy pollution action
locations. The King County sanitary
wastewater and stormwater systems are
combined and climate changes in rainfall
amounts require planning for conveyance
system level of service.
1 PROJECT MANAGER Shay Koerber
Assignment
Project Manager
Education
Seattle Central Community
College, WA Sociology
Graduated 2000
O&M of wastewater collection
systems
California State University
Sacramento, CA 2013
Certifications
MACP, NACP Certified
O&M Certified
T-Lock Welder (Ameron Water
Transmission Group)
Experience
17 Years
Joined Firm
2005
Relevant Experience
▪ Successfully Managed over 300
Temporary and Permanent Sewer
Flow Monitoring Projects
▪ Expertise in Flow Monitoring,
Water Loss Control and SSES
▪ Software, Hardware, Data
Analysis and Field Experience
▪ Safety Training Coordinator
▪ 100% of Shay’s projects have
meet a 95% uptime rate or better
▪ Site Reports/ Site Safety Plan
development
▪ Traffic Management
Development
▪ Field Crew Scheduling and
Safety Preparation

TEMPORARY SEWER FLOW MONITORING & RAINFALL

DEPENDENT INFLOW & INFILTRATION STUDIES
Relevant Experience
As Manager Shay has successfully managed the project operations from beginning to end on over 200 temporary flow monitoring projects, totaling more than 1000 monitoring sites. These projects included studies required to obtain data for modeling, inflow and infiltration (I/I), billing, event notification services, flow proportional sampling, sewer smoke testing (SSES), and pump station calibrations. Shay has managed over 20 long term projects totaling more 300 monitoring locations.

Shay has also had the experience working with several different agencies in multiple major metropolitan cities throughout the United States. Shay has helped assist and manage several major projects, including Seattle, San Diego, Los Angeles, Las Vegas, Fresno, Reno, Oakland, OC San, MNWD, and San Jose.

Los Angeles Area, Long Term and Temporary Sewer Flow
Monitoring and Event Notification Services, Sampling, Los Angeles, California
Project Manager. ADS has monitored many long term and temporary locations throughout the Los Angeles area for the purpose of billing, capacity studies, master planning, multi-variable flow weighted sampling, and event notifications. Responsible for monthly QA/QC data posting to Prism web platform, monthly and quarterly reporting of flow quantity and water quality parameters/ loadings and adhering to strict uptime requirements. The cities/agencies include Las Virgenes, San Fernando, CVWD, La Canada, Universal, Beverly Hills, LA County (LACSD), Torrance, Glendale, Whittier, Alhambra, Compton, Carson, Gardena, Long Beach, Santa Monica.

City of Port Hueneme, CA. Long Term and Temporary Flow
Monitoring Services
Project Manager. ADS has operated a network of custody transfer flow monitoring stations since 2009 using multiple technologies including Nivus cross-correlation and ADS gated velocity technologies; in addition to operating a large-scale temporary network of monitoring stations for purposes of quantifying and prioritizing rain dependent inflow and infiltration (I/I) throughout the collection system. Responsibilities include monthly QA/QC data posting to Prism and quarterly certifications of accuracy.

SUMMARY OF EXPERIENCE
Shay is the Project Manager for ADS Environmental Services in the Huntington Beach, California office. He is responsible for the direct supervision of project personnel and the development of their professional and technical expertise in field activities. His responsibilities include safety training coordination, field record organization, and overall performance of company projects. 2 Shay Koerber
Orange County, California Long Term and Temporary Sewer Flow Monitoring and Event Notification Services
Project Manager. In responsible charge of projects from several contracted cities/agencies to conduct flow monitoring for capacity, I/I studies, SSES, and many wet weather studies. The Cities and agencies include SOCWA, IRWD, OC San, MNWD, SCWD, Brea, Fullerton, Anaheim, Seal Beach, Costa Mesa, Fountain Valley, Santa Ana, Tustin, Buena Park, Stanton, Garden Grove, Irvine, and Huntington Beach.

City of Las Vegas, Permanent Sewer Flow Monitoring, Las Vegas, Nevada Field Manager. Thirty sanitary sewer flow monitoring sites on a continuous basis since 1997. Flow data is used for billing, modeling and flow verification during diversion activities. Scope of services includes comprehensive service, data analysis and event notification services.

Deliverables also include as-needed temporary flow monitoring and removing and reinstalling monitoring stations.

City of San Diego, Sewer Flow Monitoring and Event Notification Services, San Diego, California Field Manager. Five-year contract with Metropolitan Wastewater worth $5,700,000. Monitor 161 sanitary flow monitoring sites in pipes ranging from 8” to 114” on a continuous basis since 2005. Responsible for providing daily updates of flow, hydraulic performance and event notification via wireless and landline telemetry to a web-based data delivery platform, Prism.

Daily service summaries and 95% or better uptime performance are provided along with monthly data analysis and finalization / certification of data used for billing, modeling and overflow alarming to meet EPA requirements.
requirements.

City of El Cajon, Sewer System Evaluation Services, El Cajon, California, Field Manager. ADS was contracted by the City of El Cajon to conduct 164,000 linear feet of sanitary sewer smoke testing as a follow-up to a system- wide flow monitoring effort to identify RDII. The project involved locating cracks, breaks and illegal connections, and after extensive investigation, over 250 defects were found which assisted the City in developing a rehabilitation plan and identifying necessary sewer repairs and replacement.

City of Westminster, Dry and Wet Weather Sewer Flow Monitoring Study, Westminster, Colorado Field Manager. ADS was sub-contracted by HDR Engineering to conduct temporary sewer flow monitoring at 41 gravity locations for a period of 7 months. Responsible for the deployment of wireless flow monitors in lines ranging in size from 8” to 60”, flow and map verification and validation of return to sewer ratio. The purpose of the study was to evaluate capacity and Rainfall Dependent Infiltration & Inflow (I/I).

SENIOR REGION ENGINEER PAUL MITCHELL, P.E.
1 EXPERIENCE SUMMARY
Paul has over 31 years of technical and engineering experience with an emphasis in wastewater collection systems, municipal waste, and environmental assessment/site remediation. He currently serves as Senior Region Engineer and Project Manager. His background includes work with long-term flow monitoring services for model verification, capacity studies for siphons, pump stations, and critical sewer segments, infiltration and inflow (I/I) analysis and prioritization studies, sewer system evaluation surveys such as physical inspections, smoke testing, as well as technical reporting and presentation.

Assignment
Sr. Project Engineer/Manager
Education
B.S., Chemical Engineering -
Cal State Polytechnic
University Pomona, 1986
M.S. Program Core Courses,
Civil/Environmental
Engineering – Cal State
University Long Beach, 1991
Registration
Professional Engineer,
California, No 049435
Professional Engineer,
Nevada, No 016878
Professional Engineer,
Utah, No 8972209-2202
Experience
32 Years
Joined Firm
2000
Relevant Experience
✓ Managed over 300 Temporary
Sewer Flow Monitoring Projects
✓ Expertise in Rain Dependent
Inflow and Infiltration
✓ Critical Site Flow verification
and Capacity Evaluation
Expertise

TEMPORARY SEWER FLOW MONITORING & RAINFALL

DEPENDENT INFLOW & INFILTRATION STUDIES
East Bay Municipal Utility District, Wet Weather Sewer Flow Monitoring Study, Oakland, California
Sr. Project Engineer/Manager. Had primary responsibility for running this 109 meter, 9 rain gauge, 3 year project to identify basins with substantial I/I issues. Responsibilities for the project included cost control, ensuring deliverables were met, and oversight of all field and data analysis activities. Also prepared the final data report that was included as a deliverable to Cal EPA.

City of San Jose, Numerous Sewer Flow Monitoring Studies, San Jose, California
Sr. Project Engineer/Manager. Fifty-two sanitary flow monitoring sites and 16 rain gauges on a continuous basis and provide daily updates of flow and hydraulic performance via wireless telemetry to a web based data delivery platform called Flowview™. Weekly service summaries and monthly uptime performance metrics are provided along with monthly data analysis and finalization / certification of data. Deliverables also include seasonal flow metering (up to 100 meters at a time) and Rainfall Dependent Infiltration and Inflow (RDII) performance reports that provide trend analysis of dry and wet weather performance.

Additions of up to 85 storm system flow monitoring locations and 9 more temporary rain gauging stations will enable the City to get a better handle on their storm system model.

City of Los Angeles, Wet Weather Sewer Flow Monitoring Study, Los Angeles, California
Sr. Project Engineer/Manager. ADS was awarded a 2-year
comprehensive sewer system performance evaluation for the City of Los Angeles, CA. This included deployment of 93 wireless flow monitors in lines ranging in size from 12-inch to 99-inch, flow and map verification, capacity evaluation, preparing a Web-based master database of flow data and capacity performance data. Rainfall Dependent Infiltration & Inflow (RDII) performance evaluations were conducted in metered tributary zones using Sliicer software to assist in the preparation and calibration of their wet weather performance model.

SENIOR REGION ENGINEER PAUL MITCHELL, P.E.
2 Orange County Sanitation District, Rain Dependent Inflow and Infiltration Study, Fountain Valley, California
Sr. Project Engineer/Manager. ADS was awarded a 4-year - $6,200,000 project. The project involved delineation of 120 master basins and deployment of 150 wireless flow monitors to support the Cooperative Projects Program wherein RDII was targeted for reduction within the 24 Member Agencies comprising the District service area. This was the foundation project for all future RDII reduction efforts District wide.

San Francisco Public Utilities Commission, Wet Weather Sewer Flow Monitoring Study, San Francisco, California
Technical Advisor. Scope includes temporary sewer flow monitoring at 109 sites for 112 days for year 1, and 32 sites for 120 days for year 2.

City of San Bernardino, Temporary Sewer Flow Monitoring Study, San Bernardino, California Sr. Project Engineer/Manager. ADS was sub-contracted by AKM Consulting Engineers to conduct temporary sewer flow monitoring at 25 gravity locations for a period of 14 days for dry weather model calibration.

Santa Cruz Count, Temporary Sewer Flow Monitoring Study, Santa Cruz, California Sr. Project Engineer/Manager. ADS was sub-contracted by ARCADIS to perform turn-key sewer and rainfall monitoring for a period of 60 days at 10 flow metering stations and 3 rain gauge stations for a Wet Season Study and 30 day monitoring period at 10 sites for the Dry Season Study City of Santa Barbara, Rain Dependent Inflow and Infiltration Study, Santa Barbara, California Sr. Project Engineer/Manager. The project involved delineation of 40 master basins and deployment of 45 wireless flow monitors and 8 rain gauges, RDII analysis, reporting, and future SSES recommendations. The technical report became a foundational reference for the City for future sewer system evaluations.

City of Burbank, Burbank, Rain Dependent Inflow and Infiltration Study, California Sr. Project Engineer/Manager. ADS was sub-contracted by Kennedy Jenks Consultants, the project involved delineation of 15 master basins and deployment of 20 wireless flow monitors and 3 rain gauges, RDII analysis, reporting, and future SSES recommendations.

City of Fullerton, Rain Dependent Inflow and Infiltration Study, Fullerton, California Sr. Project Engineer/Manager. The project involved delineation of 18 master basins and deployment of 27 wireless flow monitors and 3 rain gauges, RDII analysis, reporting, and SSES recommendations resulting in ADS performing smoke testing of 125,000 linear feet.

Midway Sanitary District, Rain Dependent Inflow and Infiltration Study, Westminster, California Sr. Project Engineer/Manager. The project involved delineation of 16 master basins and deployment of 28 wireless flow monitors and 3 rain gauges, RDII analysis, reporting, and SSES recommendations.

PUBLICATION AND PRESENTATIONS
Mitchell, P.S., Enfinger, K.L., “Scattergraph Principles and Practice – Evaluating Self-Cleansing in Existing Sewers Using the Tractive Force Method” Proceedings of the World Environmental & Water Resources Congress 2010; Providence, RI; American Society of Civil Engineers: Reston, VA Mitchell, P.S., Stevens, P.L., “Gated Cross Correlation Velocity – A Breakthrough Technology for Wastewater Flow Management” WEF Specialty Conference, Louisville, KY, 2009.

Mitchell, P.S., Stevens, P.L., Nazaroff, A., “Demystifying Base Infiltration in Sewers.” WEF Specialty Conference, Detroit, MI, 2006.

Mitchell, P.S., Stevens, P.L., “How to Maximize the Value of Sewer Flow Information.” ASCE Pipelines Technical Conference, Houston, TX. 2005.

JEFF GARCIA
Industry Tenure
2002 - Present
Certification
NASSCO
Pipeline Assessment
30 hour OSHA
10 hour OSHA
Medical
Services First Aid
CPR
Confined Space
Awareness
Education
Bachelor of Arts
Boston College
Jeff is responsible for supervising all phases of condition assessment projects including oversight and training of office and field staff. Jeff has extensive experience working on Sanitary Sewer Evaluation Study projects throughout the Western United States.

Jeff has over 19 years of sewer inspection experience and has experience in all phases of field evaluations. These include manhole inspections, sewer and storm inspections, flow monitoring, dye-test confirmation, smoke testing, building inspections, cleaning large diameter pipe, GPS surveys and data collection, public relations, field management, quality control and assurance, and safety training. He has his OSHA 10 and 30 Construction Safety Awareness, Medical Services First Aid, CPR and Excavation Safety Training.

Relevant Recent Experience
• Cleaning, Inspecting, and UV Spot Repairs of Truss pipe for San Bernardino County Special Districts.
• Closed-Circuit Televising Services of Sewer Mains and Manholes – Santa Cruz County Sanitation District (Large diameter pipe cleaning and inspection, IBAK SI Manhole MACP Level 2 Inspections)
• City Wide Sewer Line Cleaning, CCTV Inspection andManhole Inspection – City of San Gabriel, CA (Sewer cleaning and IBAK mainline scanning)
• Large Diameter Storm Drain Rehabilitation – CalTrans, (Large pipe cleaning and inspection)
• Trenchless Sewer Repairs – Coachella Valley Water District (Used Cosmic UV system to install 4’ spot repairs)
• Pipe Rehab with Sewer Laterals – LA County Sanitation Districts (dye testing, flow monitoring, cleaning, inspection, lateral bypass) • 75 Mile Condition Assessment – LA County Department Public Works (Clean and CCTV 75 miles of sewer pipe across multiple cities) • Sewer System Maintenance - City of Lynwood, CA
• CCTV Inspection, Citywide - City of Arcadia, CA
• Trunk Sewer Condition Assessment, LA County Sanitation District (Floating large trunk lines for cleaning/rehab)
• Sanitary Sewer Overflow Control Program Group 2 –
Sewer Rehabilitation – City of Los Angeles, CA
Education
BS Environmental
Engineering, University of
Colorado, Boulder, 2013
Licenses
Civil Engineer, Nevada
Certifications
Certificate, Pipeline
Assessment Certification
Program, NASSCO, 2022
Certificate, Lateral
Assessment Certification
Program, NASSCO, 2022
Certificate, Manhole
Assessment Certification
Program, NASSCO, 2022
Professional
Affiliations
American Society of Civil
Engineers
Truckee Meadows
Branch:

YMF President 2020
YMF Vice President
2019
YMF Director at Large
2017-2018
Water Environment
Federation
Michael W. Wetterau, P.E.

Michael Wetterau has six years of experience as a member of Carollo’s infrastructure planning group. He assists with the development of water and wastewater master plans through model construction/updates, model calibration, demand/flow projections, capacity analysis, and capital improvement plan development. Michael has completed hydraulic model studies used to confirm preliminary design size, complete alternatives analyses, and evaluate the impacts proposed developments have on existing system. Michael has experience developing strategies for consolidating facilities while ensuring system has sufficient capacity to accommodate changes. In addition, he is certified in NASSCO PACP/LACP/MACP.

Relevant Experience
 Engineer for the City of Chino Hills,
California, Wastewater Master Plan Update.

This is an ongoing project. Constructed a
new InfoSWMM hydraulic model of the
City’s sewer system was developed from
scratch utilizing the City’s latest GIS data and
calibrated using flow monitoring data. Used
condition assessment data to develop a
sewer rehabilitation and
replacement program.
 Engineer for the City of Santa Barbara,
California, Wastewater Pipe Freeway
Crossing Rehabilitation Project. The goal of
the project is to rehabilitate and consolidate
the number of highway crossings. Assisted
with the City’s InfoSewer model based on
survey data. Analyzed proposed sewer
rehabilitation and new sewer alignments
used to consolidate highway crossings to
ensure the proposed changes and existing
system have sufficient capacity.
 Staff engineer for the City of Scotts
Valley, California, Sewer System
Management Plan, which was updated to
meet regulatory requirements, and changes
to the system since the previous adoption.

This is an ongoing project. Responsibilities
included the development of an overflow
emergency response plan, water quality
monitoring program, a fats, oils, and grease
control plan, operation and maintenance
recommendations, a prioritized inspection
program, and System Evaluation and
Capacity Assurance Plan (SECAP). The
SECAP included development and
calibration of a fully dynamic hydraulic
model of the sewer collection system
calibrated to both dry weather and wet
weather conditions, evaluation of the
collection system for existing and future
design flow conditions, recommendations
for capital improvements to mitigate
deficiencies, condition assessment of
sanitary sewer facilities in the Port, and
development of costs associated with the
proposed capital improvements.
 Staff engineer for the City of Torrance,
California, Sewer System Management Plan,
which was updated to meet regulatory
requirements, and changes to the system
since the previous adoption. As part of the
project, responsibilities included
development of several supporting
documents specific to the City. These
include a SECAP, and water quality
monitoring program. The SECAP included
development and calibration of an
InfoSWMM model of the City’s collection
system calibrated to both dry and wet
weather conditions, evaluation of the
collection system for existing design flow
conditions, recommendations for capital
improvements to mitigate deficiencies, and
development of costs associated with the
proposed capital improvements.
 Staff engineer for Tahoe Truckee
Sanitation Agency, California, Wastewater
Master Plan. Reviewed historical CCTV and
condition assessment records to develop a
sewer rehabilitation and replacement
program. Assisted with the development of
a capital improvement plan.
 Staff engineer for the City of Morro Bay,
California, OneWater Morro Bay.

Responsible for the development and
calibration collection system hydraulic
model build and calibration under dry and
wet weather conditions, evaluation of
existing infrastructure, development of a
capital improvement plan to mitigate
existing deficiencies and to serve future
Michael W. Wetterau
growth and assisted with the development
of the report.
 Staff engineer for the City of Riverside,
California, Comprehensive Wastewater
Master Plan Update. Responsibilities
included development of future flow
projections, hydraulic model development
and calibration of the collection system
under dry and wet weather conditions using
InfoSWMM, evaluation of existing
infrastructure, and development of a capital
improvement plan to mitigate existing
deficiencies and to serve future growth.

Developed a sewer replacement and
rehabilitation program based on condition
assessments, and an odor control program.
 Staff engineer for the Central Contra
Cosa Sanitary District, California, Collection
System Master Plan. The Master Plan
addressed needs over the 20-year horizon
for the existing 40-mgd plant liquids
treatment (including biological nutrient
removal needs), sludge treatment and
reuse/disposal options (including
incinerations plus digestion), water reuse,
and all other plant facilities. Major plant
upgrades and designs are anticipated to
follow the master plan. Responsible for
evaluation of existing information and
hydraulic modeling.
 Staff engineer for the City of Santa
Barbara, California, Water Distribution
Infrastructure Plan. Responsible for update
and calibration of the City's InfoWater
model, analysis of the water systems,
development of capital improvements to
mitigate existing deficiencies, development
of a system operations strategy before
abandoning tanks, and development of
the report.
 Hydraulic modeler for Yorba Linda
Water District, California, Water System
Capacity Analysis. Responsible for the
model conversion from InfoWater to
InfoWater Pro, system evaluation of
proposed system changes under existing
demand conditions, and development of
projects to mitigate deficiencies.
 Staff engineer for Tahoe City Public
Utilities District, California, Tahoe Cedars
and Madden Creek Water Systems Master
Plans. Assisted in the development of a
capital improvement plan.
 Modeler for Pasadena Water and Power
(PWP) Hydraulic Model Calibration.

Responsible for update and calibration of
PWP's water system hydraulic model using
the InfoWater modeling software, and
development of a system specific diurnal
pattern for PWP.
 Hydraulic modeler for the City of Lacey,
Washington, 337 Facilities and Pressure
Zone (PZ) Study and 400 PZ Storage Study.

The Study focuses on improving the level of
service in the College Street Corridor and
addresses PZ-wide needs. The Study
evaluates the impact of existing and new
facilities on water quality, storage, and
transmission capacity. Responsible for
updating the City’s InfoWater model to
complete the analyses, and assisted with
preparing the technical memorandums to
present the findings of the analysis.
 Engineer for the City of Salem, Oregon,
Wastewater Flow Data Analysis Phase 2. This
is an ongoing project. Currently working on
the wastewater flow data analysis for the
City and will use his knowledge to
summarize flows for the system and
develop capacity evaluation using the
hydraulic model
Previous Experience
 Technical intern at the United States
Environmental Protection Agency in the
Office of Civil Enforcement, Water
Enforcement Division. Provided technical
assistance and advice to Clean Water Act
enforcement case teams and balanced
technical and policy considerations to
recommend solutions to complex issues.

Education
MS Environmental
Engineering,
Northwestern University,
1997
BS Civil Engineering,
University of California,
Berkeley, 1993
Licenses
Civil Engineer, Nevada
Professional
Affiliations
American Academy of
Environmental Engineers
Water Environment
Federation
California Water
Environment Association
Seema Bhimani Chavan, P.E.

Seema Chavan, Carollo’s National Strategic Funding Leader, is an associate vice president and principal with Carollo with over 20 years of experience in environmental engineering. Her projects have focused on identifying and securing local, state, and federal loan/grant funding for infrastructure projects, developing strategic funding plans, assisting with compliance requirements as well as reporting.

Over the past six years, she has helped secure over $800 million in low interest loans and grants nationwide.

Relevant Experience
 Project manager for the City of Kansas
City, Missouri, 2018 WIFIA Letter of Interest
Package Development, Blue River WWTP
Biosolids Facility. Prepared WIFIA Letter of
Interest package, coordinated with EPA/City
staff, developed required documentation,
and submitted WIFIA package. EPA invited
the City to the application phase for
approximately $50M in funding.
 Funding manager responsible for the
development of 2021 WIFIA LOI packages
for the City of Bellingham, Washington, Post
Point Recovery Project and City of Santa
Cruz, California, Water Supply Project.

Responsible for the preparation of LOI
package; coordination with EPA/City staff;
development of required documentation;
and submittal of WIFIA package. Both
agencies have been invited to apply for
WIFIA financing of $132M and
$136M respectively.
 Funding manager responsible for the
development of two 2020 WIFIA LOI
packages for the Sarasota County, Florida,
Bee Ridge WRF and Advanced WWTP
Conversion and the West Valley Water
District, California, Roemer Water Filtration
Facility Expansion. Responsible for the
preparation of LOI package; coordination
with EPA/City staff; development of required
documentation; and submittal of WIFIA
package. Both agencies were invited to
apply for WIFIA financing of $132M and
$20M respectively. Supporting Sarasota
County through Application development.

Secured $132M in WIFIA funding.
 Project manager for the City of Salinas,
California, 2020 SWRCB Prop. 1 Stormwater
Grant Round 2 Grant Application. Identified
projects and enhancements for inclusion in
package, developed stormwater grant
application package, coordinated with
subconsultant on the development of
required information, submitted grant
package, and coordinated with SWRCB staff.

Secured $8.8M in grant funding.
 Project funding coordinator for the City
of Santa Cruz, California, DW SRF Funding
Assistance. Preparation of DWSRF loan
applications; Funding strategy, coordination
with SWRCB/EPA staff, coordination of
environmental and engineering
documentation during application process,
and coordination of loan application
package development and submittal.

Initiated third $100M+ loan application.

Responsible for the development of an
overall grant visioning workshop and
tracking potential funding opportunities for
the City’s $350 million CIP. Secured $149M
in SRF funding to date.
 Funding project manager for the City
of Antioch, California, Brackish Water
Desalination Project. Funding sources
include California Department of Water
Resources (DWR) Desalination Grant, DW
SRF loan financing, and WIFIA loan.

Responsibilities included the management
of the three funding agencies and various
grant/loan applications and requirements.

Responsible for supporting development,
submittal and management of the DWR
grant package. Responsible for the
development/submittal of the DWSRF loan
Seema Chavan, P.E.
application package and coordination with
funding agencies. Also responsible for the
development of the WIFIA application
package. Secured $55M in SRF and $10M in
DWR grant funding.
 Project manager for Pure Water
Monterey, California, U.S. Bureau of
Reclamation WaterSMART Title XVI Water
Recycling Project Under WIIN Act Grant
Application. Identified grant document
requirements; developed required grant
project benefits; prepared overall grant
application package; coordinated and
integrated multiple agency comments;
supported client for grant document
submittal; and followed-up with client.

Secured $20M in grant funding.
 Project manager for the Magna Water
Company, Utah, Water Reclamation and
Reuse project grant submittal to the U.S.

Bureau of Reclamation WaterSMART Title
XVI WIIN (FY 2019) Identified grant
document requirements, developed
required grant project benefits, prepared
overall grant application package
preparation, coordinated/ integrated
multiple agency comments, and provided
client support for grant submittal and
followed-up with client staff. Secured $4M
in funding.
 Project manager for the City of Santa Fe,
New Mexico, Reuse Pipeline Project, U.S.

Bureau of Reclamation and WaterSMART
Title XVI WIIN Grant Application. Identified
grant document requirements, developed
required grant project benefits, prepared
overall grant application package,
coordinated/integrated multiple agency
comments, and provided client support for
grant submittal and followed-up with client
staff. Secured $7M in grant funding.
 Strategic funding lead responsible for
the identification of potential funding
opportunities for the City of Alexandria,
Virginia, $144M Waterfront Improvement
Project. Identified potential funding
opportunities and project packing
strategies to optimize funding
opportunities, coordinated with federal and
state funding agencies to discuss
opportunities, and developed a funding
matrix. Developed a FEMA BRIC Grant
application and a the DCR Virginia
Community Flood Preparedness Fund
Grant. Secured $3.2M in DCR VCFPF
funding. FEMA Pending.
 Project manager for the Bay County,
Florida, Water Treatment Plant and AWT
SRF Loan Program Fiscal Sustainability Plans.

Responsible for developing the FSP. Tasks
included data/information collection,
development of draft FSP, coordination of
client review, and delivery of final FSPs.
 Strategic funding lead responsible for
the identification of funding opportunities
for the City of Willmar, Minnesota, Water
Treatment Plant. Identified potential funding
opportunities and project packaging
strategies, coordinated with federal/state
funding agencies to discuss opportunities,
and summarized finding in a funding matrix.

Developed DWSRF/CWSRF application
packages, Congressional Earmark requests
and request for Governor’s bonding bill
monies. Worked with federal lobbyist to
seek federal funding.

Gwyn-Mohr Tully, J.D.

Professional Summary
Mr. Tully is a licensed attorney in California with over 25 years of experience in surface and subsurface hydrology, law, and policy. Mr. Tully consults with public agencies and private clients on developing and implementing water resource management plans and individual water projects. In this context, Mr. Tully has conducted water rights investigations; assessed contractual water obligations; negotiated water transfers; prepared water settlements; evaluated surface and subsurface water supplies; prepared regulatory, legal, and political assessments; researched historical water rights and supplies; and conducted and coordinated highlevel stakeholder interactions. Mr. Tully wrote an Amicus Brief to the California Supreme Court in the case Barstow v. Mojave on the fundamental underpinnings of California Water Rights law.

Relevant Project Experience
Principal, Author, Water Supply Section for DWR’s 2020 UWMP Guidebook, California Department of Water Resources. Researched and analyzed all statutory criteria for preparing a water supply analysis for the 2020 UWMP cycle. Prepared guidance for urban water suppliers on how to meet the statutory criteria and prepare detailed assessments of all water supplies in a water supply portfolio. Drafted detailed Guidebook appendix that provided approaches to understanding the details of all types of surface and groundwater rights and contracts in California.

Principal, Comprehensive Water Management Strategy and 2020 UWMP, City of Benicia. Assessed intricacies of all water supplies available to the City and addressed attributes and vulnerabilities. Created comprehensive water management strategy that identified monthly water availability and integrated supplies to meet long-term water planning objectives. Identified new water supplies for City with neighboring purveyors and acquired pre-14 appropriative water right. Prepared City’s 2015 UWMP.

Principal, Water Asset Management Strategy, 2020 UWMP, CVP Contract Negotiation, and Transfers, City of West Sacramento. Analyzed the City’s water assets and assessed potential to maximize utility and monetize unused portions.

Developed annual revenue stream for the City through the CVPIA Accelerated Water Transfer program. Negotiated WIIN Act conversion of CVP Contract and prepared detailed water management analysis for negotiation team. Prepared comprehensive supply and demand assessment for City’s anticipated build-out conditions. Prepared City’s 2015 UWMP.

Principal, Water Asset Evaluation and Regional Water Transfer Actions, Sacramento Suburban Water District. Analyzed SSWD’s water contracts with neighboring agencies and assessed strengths and vulnerabilities. Advised on water contract consolidation and water transfer opportunities. Prepared and executed water transfer actions with neighboring water agencies. Implemented two “first-of-itskind” urban water transfers. Coordinated water management work with neighboring agencies to maximize conjunctive use.

Active Registration
California State Bar No. 199525
Skills
 Comprehensive water
resources planning
 Water rights assessments and
analysis
 Policy assessment and
development
 Water transactions,
negotiations, and agreements
 Deep understanding of
statewide water issues and
regulatory framework
 Analysis of CVP and SWP
system operations
 Expert on interstate water
agreements and adjudications
 Complex document drafting
and analysis
 Synthesis of technical, legal,
and political issues associated
with water supply reliability
Education
J.D., University of the Pacific,
McGeorge School of Law
M.A., Geography (hydrology),
University of Montana
B.A., Geography, University of
California, Berkeley