15-1001119-05 Page 1 of 1
ATTACHMENT A.1
NORTH FIRST AVENUE OVERHEAD BRIDGE OVER THE BNSF RAILROAD BRIDGE NO. 54C-0088 PROJECT
Revised Description of Project and Milestones
Project Title
North First Avenue Overhead Bridge Over The BNSF Railroad Bridge No. 54C-0088 Location, Project Limits, Description, Scope of Work, Legislative Description The North First Avenue Bridge over BNSF railway UPRR AMTRAK is located 0. 2 miles north of Main Street. The project limits are approximately from White Street to Riverside Drive. North First Avenue Bridge is the main north-south corridor connecting the northern and southern communities of the City of Barstow. Currently, the bridge has only two lanes, no shoulder, and only a 4' clear walkway on one side of the existing bridge and a Sufficiency Rating (SR) of 3.0. The replacement bridge is proposed to address the overall condition of the bridge and provide standard lanes, shoulders, and sidewalks.
Project Milestone Proposed
Preliminary Environmental Study (PES) Approved 04/09/2014 Begin Environmental (PA&ED) Phase 04/10/2014
Draft Environmental Document 10/03/2015
Begin Project Report 01/05/2015
End Environmental Phase (PA&ED Milestone) 12/04/2015
Begin Preliminary Engineering 30% Design (PS&E) Phase 09/05/2015 End Design Phase (Ready to List for Advertisement Milestone) 02/28/2022 Begin Right of Way Phase 10/12/2016
End Right of Way Phase (Right of Way Certification Milestone) 02/18/2022 Begin Construction Phase (Contract Award Milestone) 07/15/2022 End Construction Phase (Construction Contract Acceptance Milestone) 07/31/2024 Begin Closeout Phase 08/01/2024
End Closeout Phase (Closeout Report) 12/31/2025