Measure I Fiscal 2024/2025
Year-End Review and Adjustments
Attachment A
MEASURE I YEAR-END REVIEW AND ADJUSTMENTS FY 2024/2025
Five Year CIP Projects CIP 2024/2025
Amounts
Adjusted
Estimate
Measure I CarryOver/Adjustment
First Avenue Bridge over BNSF - Project Management $50,000 $125,000 $175,000 First Avenue Bridge over BNSF-Construction $1,000,000 $0 $1,000,000 First Avenue Over Mojave River-Project Management $100,000 $0 $100,000 West Section 7 Project Phase 2 - Design/Management/Inspection $75,000 $0 $75,000 Pavement Maintenance $16,300 $0 $16,300
Pedestrian and Bicycle Corridors-(ATP Match) $496,000 $0 $496,000 Barstow Rd and Rimrock Rd Traffic Signal $575,000 $0 $575,000 Rimrock Rd Reconstruction Barstow Rd to Ave H $500,000 $0 $500,000 Lenwood Rd between Agate and Tracks joint w/SBC $64,800 $0 $64,800 Pavement Management Program $52,000 $0 $52,000
Pavement Preservation (Design) $30,000 $0 $30,000
TOTAL: $ 2,959,100 $125,000 $3,084,100