IT Project Summary – February 12, 2026

1. Phone System Migration (Frontier → RingCentral)
 Port date scheduled for 2/26/26.
 Frontier billing audit in progress (17–20 statements).  Phase 1 device deployment underway; Parks & Rec sites pending.  Estimated 60–80% cost savings upon completion.

2. Microsoft Enterprise Platform
 EA Renewal: Awaiting Microsoft ROC response; may require reapplication.  M365 AD/Exchange Migration: Budget completed; pending EA activation.  OneDrive/SharePoint: Analysis pending until M365 migration is underway.

3. Police Department Technology Initiatives
 MDC/MDT Replacement: Try-and-Buy rugged laptops in testing; long-term lease program under development (20-unit minimum).
 Dispatch Call Recording: New CaptureTech server shipping; deployment expected March–April.  Drone Program: Vendor demos completed; cost analysis pending.  In-Car Cameras: Axon demos completed; cost analysis pending; current WatchGuard system is legacy/out-of-support.
 Cellular Modems/Routers: Vendor demos in progress (T-Mobile, Verizon, Peplink, Digi, Cradlepoint).  Homeland Security Grant ($17k): Eligibility review underway; quotes pending.

4. PD & FD Wireless Upgrade
 All access points staged and tested.
 Final testing and 30-day validation phase pending.

5. Tyler Technologies – EERP & ELP
 Supporting contractors with secure VPN access.
 On-site ELP implementation scheduled ongoing
 Ongoing system updates, backups, and staff access coordination.

6. ESRI GIS Implementation
 ITD access established; discovery phase ongoing.
 Coordination with FD, Planning, Engineering.

7. Granicus Platform Modernization
 Peak & Swagit: Final testing underway; hybrid go-live targeted for early March 2026.  GoDelivery: Implementation complete; awaiting City Manager approval for categories.  Website Upgrade: Current site outdated; requirements delivered to Granicus.

8. Frontier Fiber Expansion
 Site surveys completed for City Hall, PD, Harvey House.  Reviewing franchise agreement and potential Frontier-funded buildout.  All city sites submitted for fiber feasibility review.

9. Citywide Camera System Upgrade
 Phase 1 (Feb–June 2026): 12-site upgrade, mobile units, 5-year maintenance plan.  Phase 2 (FY27): Enterprise software + 19 servers.
 Phase 1 within $750k budget; Phase 2 requires new appropriation.  Meeting with Executive Admin pending for Council presentation.

10. Desktop/Laptop Replacement Program
 Ongoing Windows 10 → 11 upgrades; some devices require full replacement.  Reviewing updated Dell configurations and costs.
 Developing long-term leasing strategy for predictable refresh cycles.

11. Cora Harper Community Center – IT Rebuild
 Cooling system renovation must finish before IT can deploy new network, IDF, cameras, and infrastructure.

12. Infrastructure & Security
 Continuous wireless, firewall, and switch upgrades.
 Staff training and cross-training ongoing.
 Secureworks Red Team Test scheduled FY26 Q3–Q4 (first internal penetration test).

13. .GOV Domain Transition (AB 1637 Compliance)
 Registration completed; domain added to Cloudflare.
 Full transition planned during M365 phases (ETA FY26 Q4–FY27 Q2).  Compliance deadline: January 1, 2029.

14. Website Optimization (Ongoing)
 Fixing links, UI issues, and content across departments.