Principal
QA/QC
Project
Manager II
Engineer
Associate II
Engineer
Associate I
Project
Services
Coordinator II
E
n
v
i
r
Traffic Data
Vendor
(Count Data)
ECORP
(Environmental)
$300 $260 $170 $150 $130

BASE DESIGN SERVICES
Kick-off meeting 4 2 $1,380
PDT Virtual conference calls (4) 16 4 $4,840
General project management 8 60 24 $21,120
Task A: Subtotal 8 80 6 24 $27,340
Field Review/Site Evaluation 16 16 160 $1,200 $32,080
Utility Research & coordination 4 16 40 $300 $10,060
Survey (Allowance) 8 $30,560 $32,640
Traffic Data (Speed, ADT's & TMC's), Tech Reports 40 8 $100 $5,000 $16,860 Task B1: Subtotal 68 40 200 $1,600 $5,000 $30,560 $91,640 Preliminary plan preparation 4 16 60 120 $33,560
Preliminary cost estimate 1 4 40 $8,140
Public Involvement Meetings (1 meeting) 8 8 $300 $3,740 Task B2: Subtotal 5 28 108 120 $300 $45,440
Initial Scoping 6 4 $2,240
Environmental Document $14,431 $14,431
Task B3: Subtotal 6 4 $14,431 $16,671
65% Submittal
Title sheet (1) 1 1 8 $1,630
General notes/legends (1) 4 8 8 $3,600
Detail Sheet/typical sections (1) 2 16 24 $6,840
Curb Ramps- Minimal design (9) 2 16 70 60 $25,660
Sidewalk Gaps (1) 1 4 12 24 $6,980
Curb Ramp- Detailed design (2) 2 12 70 40 $21,620
Curb Ramp with bulb-outs- Detailed design (6) 2 36 220 180 $74,360 Signing & Striping with Bike Lane improvements (14) 2 12 80 140 $38,320 Traffic signal (HAWK, RRFB's) 2 16 100 40 $27,760
Cost estimate 1 4 40 16 $10,540
90% Submittal
Curb Ramps and Sidewalk 2 16 80 160 $42,360
Signing & Striping with Bike Lane improvements 1 8 40 80 $21,180 Traffic signal (HAWK, RRFB's) 1 8 60 20 $15,580
Cost estimate 1 2 20 8 $5,420
Specifications 1 40 8 $12,060
100% Submittal
Curb Ramps and Sidewalk 2 8 40 80 $21,480
Signing & Striping with Bike Lane improvements 1 4 20 40 $10,740 Traffic signal (HAWK, RRFB's) 1 8 30 20 $10,480
Cost estimate 1 2 10 8 $3,720
Specifications 1 12 8 $4,780
Task B4 Subtotal 24 215 933 956 $365,110
Construction Support 40 40 $17,200
Task B5: Subtotal 40 40 $17,200
TOTAL BASE DESIGN SERVICES 37 437 1131 1276 1900 $5,000 $14,431 $30,560 $563,401 FEE PROPOSAL FOR ENGINEERING, DESIGN AND ENVIRONMENTAL SERVICES RFP:

City of Barstow
ATP Project Cycle 5
KOA
CL
(Surveyor) Total
Hourly Rates (Fully Burdened): NTE
Other
Direct
Costs
Task B2: Preliminary Engineering
Task B4: Plans, Specifications & Estimate
Task B1: Records Research & Data Collection
Task A: Administration/Project Management
Task B5: Construction Support
Task B3: Environmental