Exhibit A
LIST OF PROJECTS FOR FISCAL YEAR 2026-27
FUNDED BY SB-1 - ROAD REPAIR AND ACCOUNTABILITY ACT OF 2017 New Proposed Projects
Title Description Location Component Priority Status
Estimated Project Useful Estimated Schedule
Min Max. Start Complete Phase
Main Street Route 66 Centennial Project Plans/specs are being drafted for partial reconstruction of Downtown Barstow between
1 st Ave and 7th Ave
Main Street Route 66 between 1st Ave and 7th Avenue. PreConstruction New 5 40 8/1/2026 September2026New
Previously Proposed Projects
Title Description Location
Estimated Project Useful Estimated Schedule
Min Max. Start Complete Phase
Pavement Preservation/Maintenance Project FY
2019/2020
Plans/specs are being drafted for street
preservation techniques on existing roadways.
The Project is defined South of I-15 in the City Limits. PreConstructionCarried Over 3 7 6/1/2027 Dec-27 Carryover
Traffic Signal Modifications on Main Street and
Barstow Road
Update traffic signal lights to larger led heads,
install pedestrian countdown heads, install video
cameras,
All city traffic signals on Main Street and Barstow Road Construction
In progress 15 25 Aug-2023 Dec-26 Carryover
N FIRST AVE BRIDGE and OVERFLOW BRIDGE- MOJAVE
RIVER PROJECT MANAGEMENT
First Avenue Bridge over Mojave River and Mojave
over crossing. Cost for project management.
First Avenue north of Irwin Road, Measure I funds are
being used for this
PreConstruction
In Progress 20 40 Sep-2023 Jul-2028 Carryover