Barstow City Council
Original file
125 KB
Text extracted from the city's file for reading and search. Open the original on barstowcityca.iqm2.com. That file is the official record.

Joint Meeting Council/BFPD
08/18/26 05:15 PM
Engineering
Fidel Martinez
Contract
Doc ID: 6549

AGENDA ITEM
AGENDA MATTER:

AWARD OF CONTRACT FOR MAIN STREET REHABILITATION - 1 ST AVE. TO BARSTOW ROAD PROJECT (CITY OF BARSTOW PROJECT # ENCD-26-0042) AND APPROVAL OF ROAD CLOSURES ALONG MAIN ST., FROM FIRST AVENUE TO BARSTOW ROAD EXECUTIVE SUMMARY:

Staff solicited informal bids for the Main Street Rehabilitation Project-First Avenue to Barstow Road in accordance with the California Public Contract Code and the City of Barstow's Purchasing and Contract Policy. The project was publicly advertised to qualified contractors on June 26, 2026. The City received a total of three (3) bids by the bid deadline of July 15, 2026, at 2:00 p.m. All bids received exceeded the informal bid dollar threshold maximum of $220,000, as dictated per the California Public Contract Code and the City’s Purchasing and Contract Policy. As a result, City staff was required to reject all bids and obtain Council approval to re-advertise the project formally. All bids were rejected and a solicitation request was formally approved at the July 21, 2026, City Council meeting.

Upon approval of the City Council, City Staff re-advertised the project formally and invited sealed bids to be submitted for the Main Street Rehabilitation Project - First Avenue to Barstow Road in accordance with the City of Barstow's Purchasing and Contract Policy and the California Public Contract Code. The Project was publicly advertised to qualified contractors, as required, on July 22, 2026. The City received a total of seven (7) bids by the bid deadline of August 6, 2026, at 2:00 p.m.

The bids were reviewed for completeness and contractor qualifications. The apparent lowest responsive and responsible bidder is Sully-Miller Contracting. Sully-Miller Contracting has met the requirements necessary to perform the work in accordance with all applicable contract specifications and documents.

Out of the seven (7) bids received, three (3) bid submittals were incomplete and therefore nonresponsive.

DISCUSSION:

City Staff received direction from the City Council to explore upgrades to Main Street (Route 66) due to its dilapidated condition in preparation of the upcoming centennial celebrations of Route 66. Pavement rehabilitation options were explored and associated project documents and specifications were created.

The project generally consists of a 2" removal of existing asphalt section and a 2" replacement section of asphalt (grind & overlay), removal and replacement of dilapidated concrete curb and gutter, traffic control, replacement of pavement markings striping, replacement of sewer manhole cover assemblies, traffic loop detector replacement, and best management practices such as erosion control and storm water pollution prevention programs.

The City originally advertised the project as an Informal Bid per the City of Barstow’s Purchasing and Contract Policy on June 26, 2026, and received a total of three (3) proposals by the bid due date of July 15, 2026. Based on the proposals received exceeding the informal bid threshold of $220,000, City Staff requested approval by the City Council to reject all bids and obtained the City Council’s approval for formal bid solicitation and advertisement of the project on July 21, 2026.

The project was publicly advertised in accordance with the City of Barstow’s Purchasing and Contract Policy and formal bidding procedures on July 22, 2026. The City received a total of (7) seven bids by the bid due date of August 6, 2026, at 2:00pm. the bid results were publicly read aloud at the City of Joint Meeting Council/BFPD
08/18/26 05:15 PM
Engineering
Fidel Martinez
Contract
Doc ID: 6549

AGENDA ITEM
Barstow’s Council Chambers located at 220 E. Mountain View St., Barstow, CA.

The City received bids from the below listed contractors:

Contractor Proposal Price Bid Status
United Paving Co. $328,489.45 Incomplete
Sully-Miller Contracting $361,728.50 Complete
LCR Earthwork & Engineering $369,410.00 Incomplete
Onyx Paving Company $376,767.00 Complete
S. Christensen $387,230.65 Complete
CalMex Engineering $390,751.60 Complete
No Limit Construction $392,850.00 Incomplete
Based on the results of the formal bidding process and a review of the required bid documentation and qualifications, City Staff recommends that the formal bid be awarded to Sulley-Miller Contracting, with the lowest responsive and responsible bid price of $361,728.50 which includes a $25,000 contingency.

United Paving Co., LCR Earthwork & Eng., and No Limit Construction were disqualified based on incomplete bid submittals.

City Staff is also respectfully requesting the City Council’s consideration and approval of Resolution No.

XXXX-2026 (Attachment C) which will authorize periodic street closures during the asphalt milling and paving operations which have been tentatively scheduled, beginning Monday, August 31, 2026 to Wednesday, September 30, 2026. City Staff estimates there will be approximately a total of 5-7 working days needed to mill (remove) a 2" section of dilapidated asphalt and re-pave and compact a newly placed 2" roadway. During this time, traffic will be detoured toward Williams Street, Clark Street, 2nd Avenue, 1st Street, and 5th Street. Alternate routes will be provided to the community so residents and businesses can continue to be accessed. City staff will work closely with the awarded contractor on coordination and will provide advance notification to residents and business owners of the upcoming public improvement construction. The proposed closures are necessary to allow the contractor to safely and efficiently complete critical phases of work for the planned street rehabilitation. The proposed road closures will help minimize impacts to local businesses and residents, decrease construction duration times, and enhance the public’s safety.

FISCAL IMPACT:

The project will be funded by Senate Bill 1 (SB1) and have an overall project budget of $361,729.

RECOMMENDED ACTION:

City Staff recommends to Council the following:

Joint Meeting Council/BFPD
08/18/26 05:15 PM
Engineering
Fidel Martinez
Contract
Doc ID: 6549

AGENDA ITEM

1. Award the construction contract to Sully-Miller Contracting, the lowest responsive and responsible bidder.

2. Authorize the City Manager, or her designee, the authority to sign the construction contract, and any related documents associated with the project.

3. Approve and appropriate a construction budget in the amount of $361,729 to Account No. 4005005- 5831 (SB1 Funded).

4. Adopt Resolution No. XXXX-2026, approving the proposed street closures tentatively scheduled during the month of September at the following intersections:
· 1
st Avenue & East/West Main Street (Hard Road Closure with Detoured Routes) · 2