EERP remaining effort forecast
From Richard Haller <[email protected]>
Date Tue 9/29/2026 4:03 PM
To Kimberlie A. Turner <[email protected]>; Anthony Thomas <[email protected]>; Sydnie Harris <[email protected]>
Cc Jennifer Cardinale <[email protected]>; Pamela Wilson <[email protected]> Hi Sydnie / Kim / Anthony,
Following up on my call with Anthony on Monday, I’ve pulled together a high-level overview of our current project trajectory and resource allocation through the remainder of the fiscal year.
Apologies for the slight delay, while straightforward at a high level, mapping this against active project phases requires careful alignment with our active Statement of Work.
Our current SOW remains structured to carry the engagement through August 1, 2027, encompassing a total allocation of 1,848 hours. We are currently on schedule and fully aligned with our budget parameters. As a reminder, our agreement utilizes a flexible pool of hours by workstream rather than rigid weekly caps, allowing us to surge support where and when project phases demand it.
Remaining Resource Allocation
To ensure we successfully cross the finish line for these remaining milestones, our estimated remaining effort is distributed across the project workstreams as follows:
Financials: Go-Live was complete on 7/1/2026
HCM, Payroll, & Time & Attendance: Tentatively scheduled for a January 1, 2027 go-live. We will need to validate this target date with your core team to ensure internal readiness.
EP&L Project: Scheduled for a July 1, 2027 go-live. This timeline will also require joint confirmation.
We see the following estimated work remaining per team member:
Resource Role Weeks remaining Estimated Hours
Remaining
Jason EP&L lead 9/28-08/01/2027 645
Pamela Proj Mgmt 9/28-08/01/2027 228
Steve HR & Payroll 9/28-08/01/2027 345
Richard M. System
Admin 9/28-08/01/2027 600*
Total remaining effort is 1,818 hours, leaving a tightly managed reserve buffer to accommodate unexpected scope adjustments as we approach the upcoming go-live dates.
Weekly burn rates will naturally fluctuate depending on testing and go-live preparation phases, but the totals above represent the minimum effort required to deliver successfully. * Administrative & Support Considerations
One item we should explicitly align on with the broader team is the volume of ongoing effort in the System Administrator support role. Because this was structured as general support rather than a discrete line item in the original SOW, we want to confirm the City's leadership intends to maintain ITP in this capacity through the remainder of the contract, or if internal resources are prepared to absorb any of this operational load.
Thanks
-RIchard
Richard Haller | Principal Partner