1 2022
City of Bellflower
Project Update
October 10, 2022

2 3

4 5
17617-17639 Bellflower Blvd.
(west side between Ramona St. and Cedar St.)

6 *Estimated opening date -Summer 2023

7 Phase
4 Phase
3 Phase
2 Phase
1 8

DOWNTOWN/CIVIC CENTER EV FAST CHARGING STATION

9 10
2022

PUBLIC WORKS STREET

PROJECTS

11 BELLFLOWER BLVD. MEDIAN PROJECT
Artesia Blvd. to Rose St.
➢Project will include new landscaped center medians,
roadway rehabilitation, pedestrian bulb-outs, duratherm crosswalks, and Class II bike lanes.
➢Estimate Cost: $1,356,000 (Federally funded)
➢Estimated Start: January 2023; Estimated Completion: June 2023

12 BELLFLOWER BLVD. MEDIAN PROJECT
Artesia Blvd. to Rose St.

13 LAKEWOOD BLVD. TRAFFIC SIGNAL IMPROVEMENTS
(at Five Intersections)
➢Project will include two new traffic signals on Lakewood Blvd. at Cedar St. and Mayne St.; modifications to existing signals with new protected left turn arrows at Flower St. and Somerset Blvd.; and traffic signal and roadway improvements at Lakewood Blvd. and Alondra Blvd. to increase left turn pocket capacity and add exclusive right turn lanes.
➢Estimate Cost: $3,000,000 (Measure M)
➢Estimated Start: May 2023; Estimated Completion: November 2023

14 LAKEWOOD BLVD. TRAFFIC SIGNAL IMPROVEMENTS
(at Five Intersections)
Lakewood Blvd./Flower St.

NEW TRAFFIC SIGNALS

SIGNAL MODIFICATIONS/IMPROVEMENTS
Lakewood Blvd./Mayne St.Lakewood Blvd./Cedar St.

Lakewood Blvd./Alondra Blvd.Lakewood Blvd./Somerset Blvd.

15 BELLFLOWER BLVD. REHABILITATION
Flower St. to Beach St.
➢Project will include full asphalt rehabilitation, duratherm crosswalks, various concrete improvements, and a new decorative traffic signal to replace the existing signal at Park St. The asphalt component is at 100% design and traffic signal component is at 70% design.
➢Estimate Cost: $1,900,000 (SB1 Funds)
➢Estimated Completion: Late 2023 or Early 2024

16 BELLFLOWER BLVD. REHABILITATION
Flower St. to Beach St.

17 ALONDRA BLVD. REHABILITATION
Bellflower Blvd. to Hayter Ave.
➢Project will include full asphalt rehabilitation and various concrete improvements. Project currently at 60% design.
➢Estimate Cost: $2,300,000 (SB1 Funds)
➢Estimated Completion: Fall 2023

18 ALONDRA BLVD. REHABILITATION
Bellflower Blvd. to Hayter Ave.

19 FACILITIES PROJECTS

20 BUTTERFLY GARDEN PARK
➢Project includes the development of a new park with
permeable surfaces, a walking path, benches, plants that attract butterflies, and complimentary butterfly shaped paving. ➢Estimate Cost: $1,228,000 (Federal and local funds)
➢Groundbreaking 10/4/22; Estimated Completion: April 2023

21 BUTTERFLY GARDEN PARK

22 BELLFLOWER GATEWAY SIGN
➢Project includes the installation of a decorative electronic sign and landscape improvements at the southwest corner of
Alondra Blvd. and Bellflower Blvd.
➢Estimate Cost: $494,000 (Public Art Fund)
➢Estimated Start: January 2023; Estimated Completion: April 2023

23 BELLFLOWER GATEWAY SIGN

24 CONSTITUTION PARK AND THOMPSON PARK

IMPROVEMENTS
Constitution Park Thompson Park
➢Improvements include
installation of lighting and
security cameras, additional
fencing, a new playground, and a
walking path with outdoor
fitness stations.
➢Estimated Cost: $580,000 (Parks
Facilities Fund)
➢Estimated Start: March 2023;
Estimated Completion: June 2023
➢Improvements will include a new
playground and a new ADA
parking stall.
➢Estimated Cost: $300,000
(Park Facilities Fund)
➢Estimated Start: February 2023;
Estimated Completion: May 2023

25 CONSTITUTION PARK AND THOMPSON PARK

PROJECTS
Constitution Park Revitalization Thompson Park Playground

26 PUBLIC WORK YARD OFFICE RENOVATION
➢Project includes the construction of new administrative offices and restrooms at the Public Works Maintenance Yard.
➢Estimate Cost: $1,700,000 (local funds)
➢Estimated Start: January 2023; Estimated Completion: August 2023

27 PUBLIC WORK YARD OFFICE RENOVATION

28 SIMMS PARK

STORMWATER CAPTURE PROJECT
➢Project will include a stormwater filtration and infiltration facility, replacement of the existing ballfield with a new artificial turf ballfield, replacement of the existing parking lot with a new permeable pavement parking lot, and new
trees and landscaping.
➢Estimated Cost: $18,700,000 (Measure W, Measure A &
local funds)
➢Estimated Start: June 2023; Estimated Completion: February 2025

29 SIMMS PARK

STORMWATER CAPTURE PROJECT

30 SIMMS PARK

YOUTH AND SENIOR CENTER PROJECT
➢Project will include the construction of a new single-story 11,800 square foot building with functional areas for seniors, youth, and office staff; including a kitchen, patio, and restrooms; and the relocation of parking areas.
➢Budgeted Amount: $10,700,000 (Measure A & local funds) ➢Estimated Start: October 2023; Estimated Completion: March 2025

31 SIMMS PARK

YOUTH AND SENIOR CENTER PROJECT