TO: Honorable Mayor and Members of the City Council

ATTENTION: Jeffrey L. Stewart, City Manager

FROM: Len Gorecki, Assistant City Manager/Director of Public Works

SUBJECT: Consideration and possible action to authorize the City Manager to execute Amendment No. 3 to the Public Works Contract for Specifications No. 20/21-03, in a form approved by the City Attorney, with LCR Earthwork & Engineering Corp., for additional work for the Reconstruct City-Owned Parking Lot Located at 9818 Artesia Boulevard Project.

DATE: September 25, 2023

EXECUTIVE SUMMARY

This action would authorize the City Manager to execute Amendment No. 3 with LCR Earthwork & Engineering Corp. (LCR Earthwork) for additional work that was completed as part of the Reconstruct City-Owned Parking Lot Located at 9818 Artesia Boulevard Project (the “Project”).

RECOMMENDATION TO CITY COUNCIL

1) Authorize the City Manager, or designee, to execute Amendment No. 3 to the Public Works Contract with LCR Earthwork for Specifications No. 20/21-03, in a form approved by the City Attorney; or

2) Alternatively, discuss and take other action related to this item.

FISCAL IMPACT

The additional amount in Amendment No. 3 is $3,500, which represents an increase of

0.74% from the current contract amount of $474,850. The current contract amount includes the original bid of $226,870 plus an additional amount of $247,980 from Amendment Nos. 1 and 2. The revised contract amount would be $478,350; however, the contractor is giving the City a credit of $9,065 for Bid Item No. 14 for a final contract amount of $469,285. Funds are available in Account No. 011-47028-9000 (General Fund Parking Lot Improvements).

-1-

Staff Report – Amendment to Public Works Contract for Specifications No. 20/21-03 September 25, 2023

Page 2 of 2 ends

DISCUSSION

On September 26, 2022, the City awarded a contract to LCR Earthwork to reconstruct the City-owned parking lot located at 9818 Artesia Boulevard as part of the City’s efforts to improve City-owned public parking lots. On February 13, 2023, the City approved Amendment No. 1 to include additional work for the recently acquired property adjacent to the City-owned parking lot. On March 27, 2023, the City approved Amendment No. 2 to include additional excavation and replacement of the poor-quality soil with porous base material. The additional concrete work under Amendment No. 3 was requested by City staff to fill in a void between the concrete curb and the parking lot that otherwise would have resulted in a section of dirt.

The total additional cost of $3,500 represents an increase of 0.74% from the current contract amount. Following the $9,065 credit for Bid Item No. 14, the proposed final amendment would result in a total contract amount of $469,285, which exceeds the City Manager’s signature authority. Consequently, Public Works recommends that the City Council authorize the City Manager to execute Amendment No. 3 with LCR Earthwork for the Project.