Artesia Extension Trunk Sewer Rehabilitation Phase 2
Bellflower City Council Meeting
May 28, 2024

LOS ANGELES COUNTY

SANITATION DISTRICTS
Converting Waste Into Resources

OUR MISSION
To protect public health and the environment through
innovative and cost-effective wastewater and solid waste management and, in doing so, convert waste into resources such as recycled water, energy, and recycled materials.

MATERIALS RECYCLING

Wastewater Facilities
. Water Reclamation Plant
. Wastewater Treatment Plant
Trunk Sewers
Sanitation Districts Service Area
Valencia
Av
Saugus
Lancaster
o11almdale
Los Angeles
County
La Canada
N
Whittier
Narrows
San/4o
Aeek
Pomona
- Los)
r C—oyotes
/ --
-Warren AV
Facility{�� ter
Long
Beach
Ocean Outfall

•30+ rehabilitation projects per year
•$100 million per year for at least the next 20 years
Investing in our Sewer Infrastructure

Project Team
Los Angeles County Sanitation Districts
Rene Canedo, Resident Engineer
Phil Kang, Supervising Engineer
Rosann Paracuelles, Supervising Engineer
Leon Findlay, Project Engineer
Owner
Sancon Technologies Inc
Ryan Helmuth, Vice President
Contractor

Project Summary
•5,798 feet of 10”- 39” Sewer Pipe
•44 Sewer Manholes to be rehabilitated with a protective coating system •Modification/repair of 10 Manholes
Existing sewer pipe to be rehabilitated with cured-in-place pipe liner (CIPP) Involves the Cities of Bellflower, Norwalk, and Cerritos Includes Ramona Street between Clark Avenue and Bellflower Boulevard, and Artesia/Woodruff
Rehabilitation was selected over replacement via open trench construction would be much more disruptive and costly
Construction Cost: $2,882,197

Public Benefit
Somerset Blvd Sewer Project rehabs the sewer that
serves tens of thousands of City of
Bellflower residents and businesses.

Ramona Street
Cl
a
r
k

A
v
e

Public Benefit
CIPP Lining extends lifespan
of sewer pipe by 50 years
Rehabilitation of sewer lines
helps minimize service
interruptions and keeps
construction costs down
Failure to rehab lines can
cause unscheduled service
interruptions, heavy traffic
impacts, and at worst sewer
spills and sinkhole

Cured -in-place-pipe (CIPP)

Typical Setups for CIPP lining

Typical Setups
Bypass

Typical SetupsBypass

Typical SetupsBypass

Typical Setups for MH Rehab

Ramona Street Impacts
We are working with the City of Bellflower and Bellflower Somerset Mutual Water Company to reduce service interruptions to trash, water, and traffic.

Water service shutoffs will be for only one single 12 -hour shutoff for each property and no critical facilities will be allowed to be shutoff.

No on-street parking will be in phases along Ramona Street.

We are working with the City of Bellflower and the trash hauler service provider on a modified trash pickup schedule during each phase.

We have coordinated with the City of Bellflower a full closure of Ramona St. & Bellflower Blvd. and Ramona St. & Clark Ave during weekends from Friday 5pm to Monday 6am to not impact commuter traffic.

Ramona Street Impacts
Typical service interruption
•7 am: Bypass and testing.
•8 am:Clean pipeline and perform pre-lining CCTV inspection. •9 am:Shutoff water services (where applicable) and install CIPP Liner. •11 am –1 pm:Cure CIPP Liner.
•1 pm –9 pm:Reinstate service and return water services (where applicable). •9 pm –10 pm:Perform post-lining CCTV Inspection.
•Once CIPP installation starts, it cannot stop until lining is completed and laterals are opened.

Bottled water will be delivered to residents.

Portable toilets and handwashing stations will be located along Ramona only during water shutoffs. Portable toilets will be primarily on private property with resident coordination.

Ramona Street Schedule
Duration: 1 weekMobilization and Prep work
•Business/Resident Notifications, Installation of temporary no parking signs •Installation of temporary cleanouts where required
Duration: 14 weeksBypass installation and CIPP Lining
•Installation of bypass systems (Phase-based)
•Temporary Service Interruptions (12 hours max) in 4 Phases •CIPP Lining (in 4 Phases)
•Trenching Restoration (Phase-Based)
•Parking will be impacted in individual phases
Duration: 2 weeksSite Restoration and De-Mobilization
•Final Restorations and Punch List Items
•Project Completion

en. IIBuu
-1 H I o. Be flower
'J ctory Auto Bo
Cedar St
S• n
IJ
r.r.
onda
Marlene' Flower
F. s:
tsar Sei
Indepe
a ape
-ease 3
Duration:
2 weeks
CedaraSt
1 La Puente''
Me»i[a�o$'S
el flower DMV
'amona
9elro
Peforme vir
170
Phase 2
Duration:
3 weeks
eetee{ Ma
idr_ ,!;7ii;'
"an.rr,CD�
Headquarter:
• ,

Outreach
Community Meeting
will be held 2 weeks
prior to construction
start.

Residents will be
issued notices via
doorknob hanger at
14-days, 7-days, and
24-hours in advance of
work.

District notices will be
issued with Resident
Engineer’s and
Contractor’s contact
information.

Questions?
Rene Canedo
[email protected]
(562) 781-9197
Ryan Helmuth
[email protected]
(714) 412-3448