14-F
TO: Honorable Mayor and Members of the City Council
ATTENTION: Ryan Smoot, City Manager
FROM: Len Gorecki, Assistant City Manager/Director of Public Works
SUBJECT: Consideration and possible action to authorize the City Manager, or his designee, to directly negotiate a Public Works contract for the Designated Block Downtown Façade Improvement Program
(Specifications No. 22/23-08).
DATE: September 23, 2024
EXECUTIVE SUMMARY
This action would allow the Public Works Department to directly negotiate with contractors for bids for the Designated Block Downtown Façade Improvement Program (Specifications No. 22/23-08) as the project was recently advertised and bid and no bids were received.
RECOMMENDATION TO CITY COUNCIL
1) Authorize the City Manager, or designee, to directly negotiate for the construction of the Designated Block Downtown Façade Improvement Program (Specifications No. 22/23-08); or
2) Alternatively, discuss and take other action related to this item.
FISCAL IMPACT
This action creates no fiscal impact. Funds for the project are budgeted in Account No. 510-44410-4002 (Economic Development Project Funds).
DISCUSSION
On July 11, 2022, City Council amended the Economic Development Business Assistance Plan to include three additional programs to help attract and assist property owners and tenants in creating a new business, improve an existing business or modernizing an existing building within the City.
o“ 01: BELLFLO
“ s a
"o ROWING TOGETk‘YFS t f t
1 Staff Report – Authorization to direct negotiate for Designated Block Downtown Façade Improvement Program, Spec. No. 22/23-08
September 23, 2024
DISCUSSION – Continued
One such program is the Designated Block Downtown Façade Improvement Program whereupon the City Council can designate specific blocks in the Downtown to be eligible for exterior façade improvements in an effort to improve building aesthetics of the downtown area. During that meeting, staff recommended, and the City Council subsequently approved, the northwest corner of Bellflower Boulevard and Oak Street to be the first designated segment for the program in order to complement the Edgeway – Downtown Bellflower development currently being constructed at Bellflower Boulevard and Mayne Street.
Economic Development staff worked with an architectural firm to develop the design concept and construction documents for the façade improvements. Staff also worked with each property owner to establish the Grant of Façade Easement required for the proposed project.
On May 28, 2024, City Council approved Resolution No. 24-26 authorizing Public Works to advertise for bids for the project. A notice inviting sealed bids was completed and advertised the following week. A mandatory pre-bid jobsite walk was held at 10:30 a.m. on Thursday, June 20, 2024, and two contractors were in attendance. Bids were due by 11:00 a.m. on Tuesday, July 16, 2024; however, no bids were received.
Pursuant to California Public Contract Code § 22038(c) the City is allowed to carry out a project by force account or negotiated contract if no bids are received through formal or informal procedure. If approved, Public Works staff will reach out to potential contractors capable of preforming the necessary work and negotiate a contract to perform the work for the project. That contract will be brought to City Council for final review and award at a later date.