9070 Artesia Boulevard
1 History of Enforcement
January 25, 2025 – Resolution No. 25-04 Passes
February 3, 2025 – City obtains second abatement warrant February 4, 2025 – City executes second abatement warrant May 27, 2025 – City obtains third abatement warrant (2 phases) July 23, 2025 & October 2, 2025 – Abatement Warrant Extension November 12, 2025 – Abatement Completed
December 17, 2025 – Cost Demand Letter
2 Property Ownership
Los Angeles County Recorder’s records indicate the registered owner of the Property is JJR Holdings, LLC. (“Owner”) JJR Holdings, LLC. gained ownership of the Property in 2023
3 Resolution 25-04
Previous Abatement
October 2024 – City executes abatement warrant
Abatement included: trimming overgrown vegetation, painting front building; painting over graffiti; removing trash, junk, and debris; removing two beehives; and securing the Property January 22, 2025 – Demand Letter
January 27, 2025 – Resolution 25-04 passes
4 February 2025
Abatement Warrant
City ordered to:
Board up and secure structure
Fill trench on west side of structure
Re-key damaged locks
February 4, 2025 – City executes warrant at property with Public Works staff
5 February 2025 Abatement
Before Pictures
6 February 2025 Abatement
After
Before
7 February 2025 Abatement
After
Before
8 May 2025
Abatement Warrant
Phase 1
Secure structure
Test for toxic materials
Conduct required remediation for toxic materials
Phase 2
Demolish vacant structure
November 12, 2025 – All testing, remediation, and demolition completed
9 May 2025 Abatement
Before Pictures
10 The Property Today
Vacant structure demolished
Mulch
White-Picket Fencing
11 Cost Breakdown
May 2024 Locksmith (recoup): $482.81
February 2025 Public Works Crew Costs: $1,876.27
Code Enforcement Costs: $14,392.79
City Attorney’s Office: $20,187.00
May 2025 – Asbestos and Demolition Survey: $3,930.00
Titan Environmental Solutions, Inc.: $12,900.00
Integrated Demolition and Remediation: $144,800.00
Total 2024-2025 Abatement Costs: $198,568.87
12 Any questions?