TO:Honorable Mayor and Members of the City Council
ATTENTION: Ryan Smoot, City Manager
FROM:Len Gorecki, Assistant City Manager/Public Works Director SUBJECT: Consideration and possible action to authorize the City Manager to approve Agreement File No. 51.97 – Change Order No. 14-1137-

2.01 issued by the County of Los Angeles Public Works for design modifications to the Woodruff Avenue Traffic Signal
Synchronization Program (TSSP) project.

DATE:April 27, 2026

EXECUTIVE SUMMARY
Agreement File No. 51.97 is a cooperative funding agreement between the City and the County of Los Angeles for the design and implementation of the Traffic Signal Synchronization Program (TSSP) for Woodruff Avenue from Foster Road to Rose Street in Bellflower. The County has issued Change Order No. 14-1137-2.01 in response to the City’s request for design modifications that would incorporate protected left turn signals at the intersection of Woodruff Avenue and Somerset Boulevard as part of the TSSP project.

RECOMMENDATION TO CITY COUNCIL
1) Authorize the City Manager to approve AFN 51.97 – Change Order No. 14-1137-

2.01, in a form approved by the City Attorney; and
2) Approve a budget amendment to increase the budget in Account No. 115-51608- 9000 to $550,000; or
3) Alternatively, discuss and take other action related to this item.

FISCAL IMPACT
The total amount of the proposed Change Order is $123,142, which will be added to the City’s proportional cost-share for the Woodruff Avenue TSSP project. This increases the City’s total project cost contribution to $547,242. The project is Proposition C (Prop C) eligible, and a budget request will be submitted to Metro to increase the overall project funding and utilize Prop C funds to cover the additional cost from the change order.

Page 1 of 2 ends

15-I
-1-

Staff Report – Project Change Order No. 14-1137-2.01 to the Woodruff Avenue TSSP Project
April 27, 2026

Page 2 of 2 ends

DISCUSSION
In May 2024, the City entered into a cooperative agreement with the County of Los Angeles for the implementation of Traffic Signal Syncronization Program (TSSP) for Woodruff Avenue. The County project spans the entire length of Woodruff Avenue from Firestone Boulevard in Downey to Willow Street in Long Beach and the costs for the proposed improvements are jurisdictionally shared between the cities of Downey, Bellflower, Lakewood, Long Beach and Los Angeles County.

The City received the final project design in October 2025. The design did not include protected left turn signals at Woodruff Avenue and Somerset Boulevard. Based on the high volume of traffic collisions at this intersection in recent years, coupled with the close proximity to Bellflower High School, the City requested a design modification to include protected left turn signals at this location to improve overall traffic operations and pedestrian safety.

The County reviewed traffic collision data provided by the City and agreed to incorporate our request into the project design. Since the City’s request is outside the scope of the original design, the City is soley responsible for costs associated with the project modification. Subsequently, the County and the awarded contractor have submitted Change Order No. 14-1137-2.01 to the City for approval to incorporate the City’s requested design changes.

The County estimates that the project will start sometime this summer, however a project construction schedule has not been provided to date. When the final construction schedule is received, Public Works staff will notify the City Council.

ATTACHMENT
Change Order No. 14-1137-2.01 ...........................................................................................3 -2-

14320 Albers Way
Chino, CA 91710
We think about a better world (909) 993-5470 Office www.elecnorbelco.com (909) 993-5476 Fax CA License 738518

March 23, 2026

Los Angeles County Public Works Serial No. 14-1137-002 900 S. Fremont Ave
Alhambra, CA 91803

Attention: Mr. Yahya Altuntas, Construction Manager

Reference: Woodruff Avenue Traffic Signal Synchronization Program (TSSP) Project ID No. TSM0010258
Belco Job No. 14-1137

Subject: Price Proposal for Signal Modifications at Woodruff & Somerset (City of Bellflower) Belco PCO No. 14-1137-2.01 ***Revision 1***

Dear Mr. Altuntas:

This letter serves as Elecnor Belco Electric, Inc.’s price proposal for revisions to the traffic signal improvements at the intersection of Woodruff Avenue and Somerset Boulevard. The revised scope incorporates protected left-turn phasing at the intersection, which requires modifications to the traffic signal equipment and associated infrastructure.

The work associated with this change includes additional signal equipment, poles, mast arms, loop detection, temporary signal equipment, relocation of certain existing equipment, and associated removals necessary to accommodate the revised signal configuration.

Pricing for this change is based on the contract bid item unit prices. The change reflects adjustments to the bid item quantities as summarized below:

-3-
~ belco
elecnor

14320 Albers Way
Chino, CA 91710
We think about a better world (909) 993-5470 Office www.elecnorbelco.com (909) 993-5476 Fax CA License 738518

Bid
Item Description Unit Price Original
Qty
Revised
Qty
Qty
Change Amount
24 Inductive Loop Detector and Leads Saw
Cut $17.00 11,305 11,555 +250 $4,250.00
32 Remove Type 17 Standard (Complete)
(Excl. Found.) $1,700.00 4 6 +2 $3,400.00
38 Remove Vehicle Head (Complete) $200.00 50 54 +4 $800.00 39 Remove Pedestrian Head (Complete) $200.00 41 37 -4 ($800.00) 40 Remove Pedestrian Push Button $80.00 25 23 -2 ($160.00) 43 Remove Type 17 Foundation $2,000.00 4 6 +2 $4,000.00 53 Relocate Retro Reflective Street Name
Sign $600.00 7 9 +2 $1,200.00
54 Relocate Luminaire Assembly $600.00 2 4 +2 $1,200.00 59 Switch Pack $53.00 16 20 +4 $212.00
66 Temporary Signal Pole With Mast Arm $3,000.00 10 12 +2 $6,000.00 72 45' Signal Mast Arm $6,815.00 3 5 +2 $13,630.00
73 12' Luminaire Mast Arm $1,208.00 17 19 +2 $2,416.00
92 Type 26 Standard (LADOT) $21,526.00 3 5 +2 $43,052.00 106 Type 26 Standard Foundation (LADOT) $6,672.00 3 5 +2 $13,344.00 116 3-12" LED Vehicle Head (Complete) $2,050.00 110 122 +12 $24,600.00 123 Relocate Sign $109.00 20 22 +2 $218.00
126 No. 6 Pull Box $1,385.00 38 42 +4 $5,540.00
132 5-Conductor Signal Cable (Excluding
Conduit) $4.80 3,035 3,085 +50 $240.00

Net Contract Increase: $123,142.00.

Due to the additional removals, installation of new foundations and poles, additional signal heads, pull boxes, and associated wiring and testing required to implement the revised signal configuration at the Woodruff Avenue and Somerset Boulevard intersection, this change will impact the overall project schedule. Elecnor Belco Electric, Inc. respectfully requests an additional fifteen (15) working days to complete the added work associated with this change. -4-
~ belco
DI
DI
DI
D
D
elecnor __
II~□□□□
II~□□□□
ID □□□□
DD □□□
DD □□□

14320 Albers Way
Chino, CA 91710
We think about a better world (909) 993-5470 Office www.elecnorbelco.com (909) 993-5476 Fax CA License 738518

If this proposal is acceptable, please issue a change order at your earliest convenience. Should you have any questions or require additional information, feel free to contact me at (951) 532-4833 or via email at [email protected].

Sincerely,
Elecnor Belco Electric, Inc.

Donald Hopkins
Project Manager