BELMONT

COMMUNITY
CENTER
MASTER
PLAN

REFRESH
City Council Presentation
October 14, 2025

1. Project Overview + Update
 Recap/Context
 Schedule + Past Master Plan
 Revalidation of Need +
Benchmarking
 Best Practices + New Trends
 Foundational Framework

2. Design Overview

3. Program Refresh
AGENDA

CITY OF BELMONT

COMMUNITY CENTER CONCEPTUAL DESIGN UPDATE
TASK 1: MASTER PLAN REFRESH DRAFT WORK PLAN – 28 May 2025

SEPTEMBER OCTOBER

1.1 PROGRAM UPDATE

1. Project Management Team Meetings (PMTs)

2. New Trends in Recreation and Building Design

3. Program Validation & Refresh

4. Program Mapping

1.1.5. Revalidation of Need

1.1.6. Enhanced Role in Emergency Response

1.1.7. Sustainability Framework

1.1.8. Benchmarking and Lessons Learned

1.2 DESIGN & ARCHITECTURAL UPDATES

1.2.1. Project Management Team Meetings (PMTs)

1.2.2. Updated Master Plan Design Exhibits

3. Architectural Expression

4. Flythrough

1.3 UPDATED COST

ESTIMATE

1. Project Management Team Meetings (PMTs)

2. Updated Project Cost Estimate

1.4 FUNDING STRATEGY & SUMMARY REPORT

1. Project Management Team Meetings (PMTs)

2. Funding Opportunities

3. Funding Strategy

4. Summary Report

1.5 PROJECT PARTICIPATION

KICKOFF
Technical + Stakeholder +
Community Meetings

PLANNING,

BUILDING &

PUBLIC WORKS

PARKS & REC

COMMISSION

STUDY SESSION

PARKS & REC

COMMISSION

PRESENTATION

BELMONT COMMUNITY

FOUNDATION

PRESENTATION

CITY COUNCIL

PRESENTATION
Aug. 9

PARKS & COMMUNITY

REC STAFF CENTER

TENANTS
July 16 Sep. 3
Today
Oct 14 June 26
Project Management Team (PMT) June 20 July 18 Aug. 4 Aug. 13 Aug. 29 Oct. 3 PROJECT SCHEDULE (2025)

JUNE JULY AUGUST
Extended
Extended
Extended
July 2
MASTER
PLAN

CONCEPTUAL

PLANNING

WE ARE HERE

DESIGN CONSTRUCTION

DEPENDENT ON FUNDING BEING IDENTIFIED

SCHEMATIC CONSTRUCTION

DOCUMENTS

BID/AWARD CONSTRUCTION

PROJECT PHASES
Did you know? More than 1,700 local Belmont
youths attend programs at the community center
every week, and hundreds participate in outdoor
sports every day.

They need a safe, repaired community center
that has capacity for these activities, just like other communities have.

The City is looking into the most cost-effective
way to provide safe, updated spaces for these
activities, with a focus on qualifying this project for matching funds from the State or County.

SMART, EQUITABLE INVESTMENT IN BELMONT FAMILIES

NEED FOR A NEW BUILDING
The over-75-year-old Barrett Community
Center is bursting at the seams and cannot
meet current demand for programs. The
existing building faces leaks and structural
deterioration. To ensure it can safely serve
our community for generations to come, we
must bring it up to modern earthquake,
electrical, fire safety, and accessibility
standards.

BENCHMARKING
0 0.5 1 1.5 2 2.5
San Carlos
Belmont
Millbrae
San Bruno
South San Francisco
Redwood City
Burlingame
2040

INDOOR RECREATION SQUARE FEET (SF) PER RESIDENT
0 0.5 1 1.5 2 2.5
San Carlos
Belmont
Millbrae
San Bruno
South San Francisco
Redwood City
Burlingame
2024

EXISTING FACILITIES (NO NEW ADDITIONS) W/ NEW COMMUNITY CENTER W/ NEW COMMUNITY/AQUATIC CENTER W/ NEW COMMUNITY/RECREATION CENTER Community Center built in the last 5 years

SERVING OURYOUTH/ FAMILIES / ADULTS/ SENIORS

INDOOR SPACES
More than half of respondents
prioritized a Water Play / Aquatic
amenity, especially by Youth
participants.

Almost half of participants, especially
online survey respondents,
prioritized a Fitness + Wellness
Center and Gymnasium – one of
the most missed spaces in the
existing Community Center.

OUTDOOR SPACES
Water Play / Aquatics,
Playgrounds are the top priority of
residents.
2019 COMMUNITY OUTREACH RESULTS
COMMUNITY ENGAGEMENT SINCE 2020
THE COMMUNITY CENTER CONVERSATION SURVEYS 2024 PARKS RECREATION OPEN SPACE MASTER PLAN

THANK YOU FOR YOUR FEEDBACK,
BELMONT COMMUNITY!

COMMUNITY/REC CENTER BEST PRACTICES

HOLISTIC WELLNESS ACCESSIBLE TO ALL

ADAPTABLE SPACES EFFICIENT OPERATIONS

COMMUNITY-DRIVEN

SUSTAINABLE DESIGN
 community multipurpose
spaces
 splash play areas
 park restrooms
 trails
o outdoor fitness equipment
o park shelters
 playgrounds
 swimming/aquatics
• skateparks
 off-leash dog parks
CONTINUED + RISING DEMAND FOR…
 “eldertainment” + more seniorfriendly programming
 community events
 group activities
o newer sports such as pickleball +
padel + traditional sports
 multiuse courts
 arts programming
o therapeutic recreation
+ more!

BELMONT COMMUNITY CENTER CONCEPTUAL DESIGN
 Included o Opportunity to include • Not included
FOUNDATIONAL FRAMEWORK – 2025
MULTIGENERATIONAL +

MULTIFUNCTIONAL SPACES
HEALTH + WELLNESS

SERVICES

SUSTAINABLE DESIGN

RESILIENCY CENTER

RESILIENCY CENTER
KEEPING BELMONT SAFE + CONNECTED IN AN EMERGENCY
• Central location in the city
• Resiliency Center can serve as a place for:
• Family Reunification
• Supply distribution
• Power Charging
• Medical Assistance
• Cooling, heating, etc.
• Showers at the Pool Locker Rooms could provide
showers during emergency events.
• Generator/batteries could be included for backup
power during power outage.
• Building could include a server room to provide
redundancy for city server.

RESILIENCY CENTER
Role in an emergency

BELMONT

COMMUNITY
CENTER
1,000SF
2019 CONCEPTUAL DESIGN SITE PLAN

DEDICATED GYMNASIUM

CHILDCARE

PLAY YARD

PARK RR

OUTDOOR
POOL

COMMUNITY
LOUNGE
LOBBY
STAFF
PUBLIC
RR

MULTI-PURPOSE
ROOM
A

KITCHEN
& SUPPORT
B C
PATIO
PARTY
ROOM
POOL

SUPPORT
LOCKER
ROOMS
1ST
FLOOR
PLAN

ALTERNATIVE

POOL LAYOUT

CHILDCARE CHILDCARE
BCLC

CHILDCARE OFFICE

BELBURN DR

RALSTON AVE

ALTERNATIVE

PARK RESTROOM

LOCATION

PARK RR
500
SF
2019 CONCEPTUAL DESIGN – FLOOR PLAN LAYOUT

OUTDOOR
POOL
POOL

SUPPORT

LOCKER PARTY

ROOMS ROOM

FITNESS

ARTS & STUDIO
CRAFTS
BLDG

SUPPORT PUBLIC
RR
ROOM

GYMNASIUM

OPEN TO
BELOW

TERRACE

TERRACE
STAFF
CONF.

OPTIONAL WALKING TRACK
2ND
FLOOR
PLAN

PROGRAM PROGRAM
ROOM

PROGRAM
ROOM

BELBURN DR

RALSTON AVE
500
SF
2019 CONCEPTUAL DESIGN FLOOR PLAN LAYOUT

COMMUNITY
CENTER
1ST FL
2ND FL
POOL
GYM
1ST FL
2ND FL
1ST FL
2ND FL
IMPLEMENTATION PLAN – OPTIONS
2ND FL
1ST FL

GYMNASIUM AQUATIC COMMUNITY, GYM,
+ AQUATIC

PROGRAM REFRESH OPTIONS COMMUNITY CENTER

COMMUNITY CENTER
Entry
Lobby/Informal Gallery/Reception
Social Lounge
Community Room, Conference + Kitchen
Divisible Community Room (inc. Storage)
Conference Room
Kitchen
Program Rooms
7 Multigenerational Program Spaces (inc. Storage)
Arts + Crafts (inc. Storage)
Early Childhood Education
2 Preschool Classrooms + Support Spaces
Teen Space
Teen Lounge (inc. Storage)
Health + Wellness
Fitness + Wellness Studio (inc. Storage)

STAFF/SUPPORT SPACES
Staff
Support Spaces
Walls + Circulation

GYMNASIUM
Gymnasium (inc. Storage)

STAFF/SUPPORT SPACES
Staff
Support Spaces
Walls + Circulation

PARKING DRAFT
100-150 sp. req.

AQUATICS
Changing Room, Pool Party Room + Support

STAFF/SUPPORT SPACES
Staff
Support Spaces
Walls+ Circulation

AQUATIC CENTER

RECREATION CENTER
TOTAL ~31,000-45,000 SF
2025 UPDATED COST ESTIMATE

BELMONT COMMUNITY FOUNDATION
DRAFT

IN PROGRESS
MAINTAIN FACILITIES SO THEY DON’T FALL INTO DISREPAIR

AND DETERIORATE
DRAFT

IN PROGRESS

PROVIDE PARKS, SPORTS COURTS AND FIELDS, AND

A MUTIGENERATIONAL CENTER FOR ALL AGES
DRAFT

IN PROGRESS

PROVIDE A DISASTER RELIEF AND EMERGENCY EVACUATION

CENTER THAT MEETS EARTHQUAKE AND FIRE SAFETY STANDARDS
DRAFT

IN PROGRESS

SPORTS, ARTS, CRAFTS, FITNESS, HEALTH, AND WELLNESS

PROGRAMS FOR ALL AGES
DRAFT

IN PROGRESS

MAINTAIN CHILDCARE AND SUPERVISED AFTER-SCHOOL PROGRAMS DRAFT

IN PROGRESS
DRAFT

IN PROGRESS

MAINTAIN SENIOR SERVICES, INCLUDING HEALTH, FITNESS,

NUTRITION, WELLNESS, AND TRANSPORTATION PROGRAMS

UPDATE TO MEET CURRENT EARTHQUAKE

AND FIRE SAFETY STANDARDS