AGENDA REPORT
Meeting Date: June 14, 2022
Item Number:

To: Honorable Mayor & City Council
From: Daren Grilley, Assistant Public Works Director/City Engineer Christine Chung, Associate Project Manager
Subject: AMENDMENT NO. 6 TO AN AGREEMENT BETWEEN THE CITY

OF BEVERLY HILLS, THE LOS ANGELES COUNTY

METROPOLITAN TRANSPORTATION AUTHORITY, AND

ENVIRONMENTAL INTELLIGENCE, LLC, FOR INDEPENDENT
COMPLIANCE MONITORING SERVICES FOR SEGMENTS 1 AND
2 OF THE PURPLE LINE EXTENSION PROJECT; AND
APPROVAL OF AN APPROPRIATION OF $3,021,700 FROM THE
GENERAL FUND; AND

APPROVAL OF A CHANGE PURCHASE ORDER TO

ENVIRONMENTAL INTELLIGENCE, LLC FOR INDEPENDENT

COMPLIANCE MONITORING SERVICES IN THE AMOUNT OF
$3,021,700 FOR A TOTAL AMOUNT NOT TO EXCEED
$12,884,800
Attachments: 1. Amendment No. 6

RECOMMENDATION
Staff recommends that City Council move to approve Amendment No. 6 to Agreement No. 481-17 with Los Angeles County Metropolitan Transportation Authority (Metro) and Environmental Intelligence, LLC (EI) to provide independent compliance monitoring services related to Segments 1 and 2 of the Purple Line Extension project; approve an appropriation of $3,021,700 from the General Fund to the ongoing contractual services account (No. 001-12401-731220); and approve a purchase order in the amount of $3,021,700 for Fiscal Year 2022/23 for a total not to exceed contract amount of $12,884,800. The cost of EI’s services associated with the Purple Line Extension Project will be reimbursed by Metro, with the exception of an estimated $177,100 for in-person monitoring at the Beverly Hills High School, which is paid for by the City.

BEVERLY
HILLS
-�
E-13
Meeting Date: June 14, 2022

Page 2 of 3 ends

INTRODUCTION
On September 5, 2017, City Council approved a one-year agreement between the City, Metro and EI for independent compliance monitoring (ICM) services in the amount of $1,472,540. Amendment No. 1, approved on August 7, 2018, provided an additional $1,279,860 for a total contract amount not to exceed $2,752,400 and an extension of the term of the agreement to September 30, 2019. Amendment No. 2, approved on August 6, 2019, provided funding of $1,247,600 for a total not to exceed of $4,000,000 and service term through September 30, 2020. Amendment No. 3, approved on March 31, 2020, provided funding of $3,100,000 for a total not to exceed of $7,100,000 and service term through June 30, 2021. Amendment No. 4, approved on June 1, 2021, provided funding of $2,763,100 for a total not to exceed of $9,863,100 and service term through June 30, 2022. Amendment No. 5, approved on January 18, 2022 approved an extension of the Agreement’s termination date to December 31, 2025, subject to annual extension for each year beyond June 30, 2022.

DISCUSSION
With concurrence from Metro, EI was selected through a Request for Qualification process to provide the ICM services for Segments 1 and 2 of the Metro Purple Line subway extension project. EI began working with the City and Metro in September 2017. The scope of their services is as follows:  Ensure Metro’s compliance with any and all conditions and mitigation measures included in the Segment 1 and Segment 2 Memorandum of Agreements, including all Exhibits attached thereto, Metro permit applications and submittals and any conditions of approval included in the City-issued permit.  Work collaboratively with Metro (including contractors and subcontractors) and the City (including City representatives) to support Metro’s compliance with all applicable conditions and mitigation measures.  Enforce the conditions and mitigation measures as provided under the MOA Articles, “Enforcement of Permit Conditions and Mitigation Measures,” as necessary to achieve compliance.  On February 19, 2019, the City and Metro executed the MOA for Design Build of the Wilshire/Rodeo Station, which included the requirement for the ICM to be onsite at the Beverly Hills High School for certain work activities during specific hours when school is in session. The City Agreed to absorb the cost of monitoring at the High School.

Since EI’s commencement date of September 11, 2017, through May 18, 2022, EI has issued 311 violations of MOA or permit conditions for Section 1 (Wilshire/La Cienega Station) and 569 violations for Section 2 (Wilshire/Rodeo Station). This agreement allows for necessary resources to enforce the MOAs in both Section 1 and Section 2 and is not limited to a specific number of people. EI is provided a weekly work plan describing the planned work activities. Based on this schedule, EI determines the required staffing levels to provide monitoring services. At the end of each week, EI regularly submitted a weekly summary to the City and Metro, which documented the work for the week and any violations issued; these reports are available to the public on the City’s webpage at www.beverlyhills.org/purpleline. Considering EI’s consistent enforcement of the MOA and permit conditions of the Metro Purple Line Extension project, staff recommends the City continue retaining the services of EI in order to maintain the current level of monitoring for the forecasted increase in Meeting Date: June 14, 2022

Page 3 of 3 ends

major construction activities over the next fiscal year. Section 1 construction is anticipated to be complete in 2024 and Section 2 by 2025.

FISCAL IMPACT
Costs associated with monitoring at the Wilshire/La Cienega and Wilshire/Rodeo Station will be reimbursed by Metro. The terms of the existing Design-Build Memorandum of Agreement (or MOA) for the Wilshire/La Cienega Station and MOA for the Wilshire/Rodeo Station both include provisions to provide reimbursement to the City for staff and consultants performing work associated with the construction of the Purple Line Extension project. The Wilshire/Rodeo Station MOA states that Metro is not responsible for the costs associated with monitoring at the Beverly Hills High School.

This agreement will require an appropriation of $3,021,700 from the General Fund to the ongoing contractual services account (No. 001-12401-731220) and a change purchase order to EI in the not to exceed amount of $12,884,800. Environmental Intelligence Contract Amendment Total Not To Exceed
Original Contract (481-17) Year 1 $1,472,540 $1,472,540 Amendment 1 (512-18) Year 2 $1,279,860 $2,752,400
Amendment 2 (459-19) Year 3 $1,247,600 $4,000,000
Amendment 3 (137-20) Year 4 $3,100,000 $7,100,000
Amendment 4 (182-21) Year 5 $2,763,100 $9,863,100
Amendment 6 (proposed) Year 6 $3,021,700 $12,884,800
EI bills on a time and materials basis using rates set forth in Exhibit B of the Agreement.

Jeff S. Muir, Director of FinanceShana Epstein, Director of Public Works Approved By Approved By
Attachment 1
1 B0785-0022\2667830v1.doc
AMENDMENT NO. 6 TO AN AGREEMENT BETWEEN THE

CITY OF BEVERLY HILLS, THE LOS ANGELES COUNTY

METROPOLITAN TRANSPORTATION AUTHORITY, AND

ENVIRONMENTAL INTELLIGENCE, LLC, FOR

INDEPENDENT COMPLIANCE MONITORING SERVICES
FOR SEGMENTS 1 AND 2 OF THE PURPLE LINE

EXTENSION PROJECT
NAME OF CONSULTANT: Environmental Intelligence, LLC
CONSULTANT’S RESPONSIBLE PRINCIPAL: David Levine
CONSULTANT’S ADDRESS: 811 West 7th Street
9th Floor
Los Angeles, CA 90017
CITY’S ADDRESS: City of Beverly Hills
345 N. Foothill Road
Beverly Hills, CA 90210
CITY’S RESPONSIBLE PRINCIPAL: Daren Grilley, City Engineer MTA’S ADDRESS Los Angeles County Metropolitan
Transportation Authority
One Gateway Plaza, 17th Floor
Los Angeles, CA 90012

MTA’S RESPONSIBLE PRINCIPALS: Joseph DeMello (Segment 1) Carlos Martinez (Segment 2)
COMMENCEMENT DATE: September 11, 2017
TERMINATION DATE: September 30, 2019 (as amended by
Amendment No. 1)
September 20, 2020 (as amended by
Amendment No. 2)
June 30, 2021 (as amended by Amendment
No. 3)
June 30, 2022 (as amended by Amendment
No. 4)
June 30, 2023 (as amended by this
Amendment No .6), unless extended
pursuant to Section 1 of the Agreement until
December 31, 2025.
[Continued on next page]
DRAFT
2 B0785-0022\2667830v1.doc
CONSIDERATION: Original Agreement:

Not to exceed: $1,472,540
Amendment No. 1:

Not to exceed: $1,279,860

Amendment No. 2:

Not to exceed: $1,247,600
Amendment No. 3:

Not to exceed: $3,100,000 ($265,000 in FY
2020; $2,835,000 in FY 2021)
Amendment No. 4:

Not to exceed: $2,763,100 in FY 2022
Amendment No. 5:

No change in the Agreement amount
Amendment No. 6:

Not to exceed: $3,021,700 in FY 2023
Total Not to Exceed: $12,884,800, based on
the rates set forth in Exhibit B DRAFT
3 B0785-0022\2667830v1.doc
AMENDMENT NO. 6 TO AN AGREEMENT BETWEEN THE

CITY OF BEVERLY HILLS, THE LOS ANGELES COUNTY

METROPOLITAN TRANSPORTATION AUTHORITY, AND

ENVIRONMENTAL INTELLIGENCE, LLC, FOR

INDEPENDENT COMPLIANCE MONITORING SERVICES
FOR SEGMENTS 1 AND 2 OF THE PURPLE LINE

EXTENSION PROJECT
This Amendment No. 6 is to that certain agreement between the City of Beverly Hills (hereinafter called “CITY”), the Los Angeles County Metropolitan Transportation Authority (hereinafter called “MTA”) and Environmental Intelligence, LLC, (hereinafter called “CONSULTANT”) dated September 5, 2017, and identified as City of Beverly Hills Contract No. 481-17, as amended by Amendment No. 1, dated August 7, 2018, Amendment No. 2 dated August 6, 2019, and identified as Contract No. 512-18, Amendment No. 3 dated March 31, 2020, and identified as Contract No. 137-20, Amendment No. 4 dated June 1, 2021, and identified as Contract No. 182-21 (“Agreement”), and Amendment No. 5 dated January 18, 2022, and identified as Contract No. 50-22 (“Agreement”).

RECITALS
A. CITY and MTA entered into the Agreement with CONSULTANT in order to procure independent compliance monitoring services for the construction of Segments 1 and 2 of the Purple Line Extension Project, with such services more particularly described in Exhibit A of the Agreement (“services”).

B. The services are currently intended to implement and comply with:
(1) the Memorandum of Agreement for Contract C1045 of the Purple Line Extension Project – Segment 1 – Between the City of Beverly Hills and the Los Angeles County Metropolitan Transportation Authority, CITY Agreement No. 66-17, attached to the Agreement as Exhibit D and incorporated herein by this reference; (2) the Memorandum of Agreement for Contract C1120 of the Purple Line Extension Project – Between the City of Beverly Hills and the Los Angeles County Metropolitan Transportation Authority, CITY Agreement No. 71-19, attached to the Agreement as Exhibit H and incorporated herein by this reference; and
(3) any subsequent permits or conditions of approval issued by CITY or amendments to the memoranda of agreement between CITY and MTA related to construction for the Purple Line Extension Project (Exhibits D, H, and such future permits, conditions of approval, and/or amendments are collectively referred to as the “MOA”).

C. The purpose of the services is to ensure MTA and its contractor(s) comply with all mitigation measures and conditions included in the MOA, subsequent permits or conditions of approval issued by the CITY, and any amendments to the memoranda of agreement between the CITY and MTA during MTA’s construction for the Purple Line Extension Project.

DRAFT
4 B0785-0022\2667830v1.doc
D. CITY, MTA, and CONSULTANT desire to extend the Agreement’s Termination Date and increase the Consideration.

E. CONSULTANT further represents that it continues to have no preexisting relationship with either CITY or MTA, aside from this Agreement, that would prevent CONSULTANT from faithfully and capably performing the services.

NOW, THEREFORE, the parties agree as follows:

Section 1. The Termination Date shall be amended as set forth on the cover page of this Amendment 6.

Section 2. The Consideration shall be amended as set forth on the cover page of this Amendment No. 6.

Section 3. Exhibit B “Compensation” shall be amended as attached hereto.

Section 4. Except as specifically amended by Amendment No. 1, Amendment No. 2, Amendment No. 3, Amendment No. 4, Amendment No. 5, and this Amendment No. 6, the remaining provisions of the Agreement shall remain in full force and effect.

EXECUTED the day of 2022, at Beverly Hills,
California.

CITY OF BEVERLY HILLS
A Municipal Corporation
_________________________________

LILI BOSSE
Mayor of the City of Beverly Hills, California
ATTEST:
[Signatures continue]
_____________________________(SEAL)

HUMA AHMED
City Clerk
DRAFT
5 B0785-0022\2667830v1.doc
APPROVED AS TO FORM: APPROVED AS TO CONTENT:
___________________________ ___________________________ LAURENCE S. WIENER GEORGE CHAVEZ
City Attorney City Manager
___________________________
SHANA E. EPSTEIN
Director of Public Works
___________________________

DAREN GRILLEY
Assistant Director of Public Works /
City Engineer
___________________________
SHARON L’HEUREUX DRESSEL
Risk Manager
[Signatures continue]
DRAFT
6 B0785-0022\2667830v1.doc

LOS ANGELES COUNTY METROPOLITAN
TRANSPORTATION AUTHORITY:
________________________________

STEPHANIE WIGGINS
Chief Executive Officer
APPROVED AS TO FORM:
________________________________
RONALD W. STAMM
Principal Deputy County Counsel
[Signatures continue] DRAFT
7 B0785-0022\2667830v1.doc
ENVIRONMENTAL INTELLIGENCE LLC:
________________________________

DAVID LEVINE
Principal

DRAFT
8 B0785-0022\2667830v1.doc

EXHIBIT B

COMPENSATION
CONSULTANT shall be compensated for professional services provided on a time and materials basis in an amount not to exceed a total of Twelve Million Eight Hundred Eighty-Four Thousand Eight Hundred Dollars ($12,884,800). Of this total, Amendment No. 6 to this Agreement allocates Three Million Twenty-One Thousand Seven Hundred Dollars ($3,021,700) in Fiscal Year 2022-2023 ending June 30, 2023, in accordance with the following billing rates:

DRAFT
2022 - 2023 Bill Rates- Environmental Intelligence
City of Beverly Hills I LA Metro Purple Line Extension
Independent Compliance Monitor Program
Labor Category (El) 2022/23 Rate
Principal $286.00
Senior Project Manager $265.00
Project Manager $196.00
Assistant Project Manager $156.00
GIS Manager/Programmer $220.00
GISTech $135.00
Lead ICM $134.00
ICM II (Day Shift) $109.00
ICM II (Swing Shift) $109.00
ICM II (Night Shift) $120.00
ICM II (Weekend Shift) $120.00
Administrative Support $90.00
Rion Noise Meters- Field EquiP.ment (P.er week - El) $166.00 Labor Category (Noise Monitoring Services) 2022/23 Rate Installation of Monitoring Stations (#1) $455.00
Remote Sensing Station (#2) $1,025.00
Additional Sound or Vibration Sensor (#3) $400.00
Dust Monitoring Sensor (#4) $1,030.00
Calibration of Remote Stations (Monthly #5) $185.00
Metro Owned Sigicom Sensors Hosting (#6) $255.00
N02 Sensor $420.00
Remote Station T&M ( #7) $185.00