AGENDA REPORT
Meeting Date: March 21, 2023
Item Number:

To: Honorable Mayor & City Council
From: Daren Grilley, Assistant Director of Public Works/City Engineer Robert Welch, Utilities General Manager
Manu Dhaliwal, Associate Project Manager
Subject: APPROVAL OF AN APPROPRIATION IN THE AMOUNT OF
$370,000 FROM THE WATER ENTERPRISE FUND; AND

APPROVAL OF A CHANGE PURCHASE ORDER IN THE AMOUNT
OF $700,000 TO PALP INC., DBA EXCEL PAVING COMPANY FOR
A TOTAL NOT-TO-EXCEED AMOUNT OF $2,215,360 FOR THE

ON-CALL PAVEMENT REPAIRS IN ORDER TO PERFORM THE

HILLCREST MAIN BREAK PAVEMENT REPAIRS
Attachments: 1. Change Order Proposal

RECOMMENDATION
Staff is requesting City Council approve an appropriation in the amount of $370,000 from the Water Enterprise Fund, to fund the On-Call Pavement Repairs Project work for the North Hillcrest Road main break emergency pavement repairs and approve a change purchase order in the amount of $700,000 to Palp Inc., dba Excel Paving Company (Excel) for a total not-to-exceed amount of $2,215,360.

INTRODUCTION
The On-Call Pavement Repairs project scope of work is to provide pavement repairs after water main breaks, water meter installations and other water related pavement cuts. The North Hillcrest Road water main break occurred on February 23, 2023, causing severe damage to the roadway and underlying subgrade, requiring a portion of the roadway to be reconstructed.

BEVERLY
HILLS
-�
E-9
Meeting Date: March 21, 2023

Page 2 of 2 ends

DISCUSSION
On April 12, 2022, City Council awarded the On-Call Pavement Repairs project to the lowest responsible bidder, Excel, and approved a purchase order in the amount of $1,515,360. The scope of work for this project is generally the repair of the right-of-way after being impacted by water main or water meter work. At the start of the project, the City had a backlog of over 200 repair locations, over half of which have been repaired at this time.

On February 23, 2023, the water main on North Hillcrest Road broke, severely damaging the roadway with sections of the roadway lifted six inches and other sections experiencing a few inches of sinking. After surveying the damage, staff determined that the west section of road, from 1059 to 1029 North Hillcrest Road, would need to be reconstructed. The reconstruction scope involves the removal of the existing asphalt and subgrade and the construction of new asphalt over base material.

The requested change order amount of $700,000 includes the price quoted by Excel for reconstructing this section of roadway, incidental repairs outside of the reconstruction area and contingency and results in a purchase order not-to-exceed value of $2,215,360.

FISCAL IMPACT
The Water Enterprise Fund (CIP Project No. 00195 – Street and Sidewalk Improvements, Water Enterprise Fund) currently has approximately $330,000 available for use.

Staff is requesting that City Council approve an appropriation in the amount of $370,000 from the Water Enterprise Fund to fund the On-Call Pavement Repairs project. The total change order cost is $700,000.

Jeff S. Muir,
Director of Finance
Shana Epstein,
Director of Public Works
Approved By Approved By

ACCOUNT NUMBER FUND DESCRIPTION AMOUNT
80006003-850000-00195 Water Enterprise $ 330,000
Water Enterprise Appropriation $ 370,000
TOTALS $ 700,000
Attachment 1
To: City Of Beverly Hills Manu Dhaliwal Contact:

Project Name: Beverly Hills Street And Alley Impvts Bid Number:

Beverly Hills, CA 90210 USA Fax:

Address: 455 N. Rexford Dr., Room 290 Phone:

Project Location: Various Locations, Beverly Hills, CA Bid Date: 5/9/2019 Item # Estimated Quantity Item Description Unit Unit Price Total Price 1 Hillcrest Main Break Pavement Repairs 15,200.00 SF $36.61 $556,472.00 Total Bid Price: $556,472.00
Notes:
• Excel Paving DIR No is 1000003331
Payment Terms:

Excel Paving to receive payment, no later than 30 days after date of invoice, regardless of general contractor receiving timely payment from the owner.

ACCEPTED:

The above prices, specifications and conditions are satisfactory and are hereby accepted.

Buyer:

Signature:

Date of Acceptance:

CONFIRMED:

Excel Paving Company
Authorized Signature:

Estimator: Darryl Rutledge
(562) 599-5841 [email protected]
3/3/2023 7:21:44 AM Page 1 of 1
&uet. Pewu19 e�=
PALP, Inc. dba Ell<:el P•vlng Co. o 0-.1 Engineering o Union Contractor CA UcenH # 688659 • Type1: A, C-12, C-31
2230 Lemon Ave. o Long Beech • CA • i0806
Ph: (562) 599-5841 • FAX: (562) 591·7485
Cost Detail
Project Name: Beverly Hills Street And Alley Impvts Customer: City Of Beverly Hills Job Number: 5685 Billing Address: 455 N. Rexford Dr., Room 290 Bid As: General Contractor Beverly Hills, CA 90210 USA
Estimator: Phone: Darryl Rutledge
Project Address: Various Locations, Beverly Hills, CA Contact: Manu Dhaliwal Completion Date:

Pay Items
Description Quantity UM Direct Cost Direct Cost
Unit Total
1 - Hillcrest Main Break Pavement Repairs 15,200.00 SF $31.02 $471,452.78 Demolition - Backhoe 282.00 CY $329.20 $92,835.00
Labor & Equipment 282.00 CY $329.20 $92,835.00
AC & PCC Demolition Sawcut Crew (838.00 LF/DY, 1.00 DY) 838.00 LF $1.95 $1,632.00 Concrete Saw 8.00 HR $64.00 $512.00
General Laborer [2] 8.00 HR $70.00 $1,120.00
AC & PCC Demolition Break Crew - Breaker-Stomper (0.00
CY/DY, 0.00 DY)
282.00 CY $0.00 $0.00
Backhoe Cat 416C With 750 LB Breaker 0.00 HR $159.13 $0.00 Operating Engineer 0.00 HR $0.00 $0.00
General Laborer 0.00 HR $0.00 $0.00
AC & PCC Demolition Load Crew - Backhoe (35.25 CY/DY,

8.00 DY)
282.00 CY $227.40 $64,128.00
Backhoe Cat 446 64.00 HR $74.00 $4,736.00
Truck Super 10 [4] 64.00 HR $150.00 $38,400.00
Foreman 64.00 HR $97.00 $6,208.00
Operating Engineer 64.00 HR $91.00 $5,824.00
General Laborer [2] 64.00 HR $70.00 $8,960.00
Dump Fee - Solids 57.00 LOAD $475.00 $27,075.00
Earthwork - Backhoe Load 282.00 CY $442.53 $124,793.60
Labor & Equipment 282.00 CY $442.53 $124,793.60
Load & Haul 282.00 CY $326.67 $92,120.00
Load Dirt Crew - Backhoe (35.25 CY/DY, 8.00 DY) 282.00 CY $205.39 $57,920.00 Backhoe Cat 446 64.00 HR $74.00 $4,736.00
Truck Super 10 [4] 64.00 HR $150.00 $38,400.00
Operating Engineer 64.00 HR $91.00 $5,824.00
General Laborer [2] 64.00 HR $70.00 $8,960.00
Dump Fee - Dirt 57.00 LOAD $600.00 $34,200.00
Rough & Fine Grade Dirt 15,200.00 SF $2.08 $31,673.60
Subgrade Preparation Crew - Skiploader (1,900.00 SF/DY,

8.00 DY)
15,200.00 SF $2.08 $31,673.60
3/3/2023 7:18:48 AM Page 1 of 5
PALP, Inc. dba Excel Paving Co. • General Engineering • Union eon tractor CA license t 688659 • Types: A, C-12, c.31
2230 Lemon Ave. • Long Beach• CA • 90806
Ph: (562) 599-5841 • FAX: (562) 591-7485
l!I
Iii
Iii
" ...
.L
" ...
.:.
.L
" ...
...
.L
.L
.L
• Iii
(i)
Q)
" ...
...
.L
.L
•
Q)
"
Description Quantity UM Direct Cost Direct Cost
Unit Total
Skiploader 64.00 HR $35.00 $2,240.00
Roller 10 - 12 Ton Vibratory 64.00 HR $44.00 $2,816.00
Water Truck 2,000 Gallon 64.00 HR $21.90 $1,401.60
Operating Engineer [2] 64.00 HR $91.00 $11,648.00
General Laborer [2] 64.00 HR $70.00 $8,960.00
Teamster 64.00 HR $72.00 $4,608.00
Equipment Moves 1.00 LS $1,000.00 $1,000.00
Equipment Moves - Shutttle Buggy 1.00 EACH $600.00 $600.00 Equipment Moves - Skiploader 1.00 EACH $400.00 $400.00
Aggregate Base CMB - Skiploader 513.00 TON $140.46 $72,056.46 Materials 513.00 TON $17.80 $9,131.66
Crushed Miscellaneous Base - Super 10 (Security Paving
Company (25th Street Recycling))
513.00 TON $17.80 $9,131.40
Environmental Fee Aggregates (Security Paving Company
(25th Street Recycling))

25.65 LOAD $0.01 $0.26
Labor & Equipment 513.00 TON $122.66 $62,924.80
Place Base 513.00 TON $61.33 $31,462.40
Place Base Crew - Skiploader (64.13 TON/DY, 8.00 DY) 513.00 TON $61.33 $31,462.40 Skiploader 64.00 HR $35.00 $2,240.00
Roller 10 - 12 Ton Rex 64.00 HR $40.70 $2,604.80
Water Truck 2,000 Gallon 64.00 HR $21.90 $1,401.60
Operating Engineer [2] 64.00 HR $91.00 $11,648.00
General Laborer [2] 64.00 HR $70.00 $8,960.00
Teamster 64.00 HR $72.00 $4,608.00
Fine Grade 12,500.00 SF $2.52 $31,462.40
Fine Grade Crew - Skiploader (1,562.50 SF/DY, 8.00 DY) 12,500.00 SF $2.52 $31,462.40 Skiploader 64.00 HR $35.00 $2,240.00
Roller 10 - 12 Ton Rex 64.00 HR $40.70 $2,604.80
Water Truck 2,000 Gallon 64.00 HR $21.90 $1,401.60
Operating Engineer [2] 64.00 HR $91.00 $11,648.00
General Laborer [2] 64.00 HR $70.00 $8,960.00
Teamster 64.00 HR $72.00 $4,608.00
AC - Asphalt Concrete Paving - Skiploader - AC 570.00 TON $170.67 $97,282.62 Material 570.00 TON $80.82 $46,069.82
Asphalt Concrete - AC - Conventional Mixes 570.00 TON $80.66 $45,976.20 Environmental Fee Asphalt Concrete (Blue Diamond
Materials)

28.50 LOAD $3.29 $93.62
Labor & Equipment 570.00 TON $89.85 $51,212.80
Asphalt Concrete Paving Crew - Skiploader (71.25 TON/DY,

8.00 DY)
570.00 TON $89.85 $51,212.80
Skiploader 64.00 HR $35.00 $2,240.00
Roller 10 - 12 Ton Rex 64.00 HR $40.70 $2,604.80
Truck Tack 64.00 HR $15.50 $992.00
Street Sweeper 64.00 HR $150.00 $9,600.00
Foreman 64.00 HR $97.00 $6,208.00
Operating Engineer 64.00 HR $91.00 $5,824.00
Roller Operator 64.00 HR $91.00 $5,824.00
Raker [2] 64.00 HR $70.00 $8,960.00
3/3/2023 7:18:48 AM Beverly Hills Street And Alley Impvts Page 2 of 5 (Item 1 - Hillcrest Main Break Pavement Repairs continued) ...a
...a
...a
• - • - • - @
*
@ *
@
•
•
• - • -
• - • - @
@
• •
@
,,
• - • - • -
Description Quantity UM Direct Cost Direct Cost
Unit Total
Shoveler [2] 64.00 HR $70.00 $8,960.00
Demolition - Grinder 94.00 CY $60.94 $5,727.92
Labor & Equipment 94.00 CY $60.94 $5,727.92
AC Demolition Grinding Crew (188.00 CY/DY, 0.50 DY) 94.00 CY $60.94 $5,727.92 Grinder - A. Skid-Mini (18" Width) 4.00 HR $271.88 $1,087.52 Grinder - D. Track Attack (5' Width) 4.00 HR $537.50 $2,150.00 Skiploader 4.00 HR $35.00 $140.00
Water Truck 2,000 Gallon 4.00 HR $21.90 $87.60
Street Sweeper 4.00 HR $150.00 $600.00
Compressor With Attachments 4.00 HR $15.70 $62.80
Foreman 4.00 HR $97.00 $388.00
Operating Engineer 4.00 HR $91.00 $364.00
General Laborer [2] 4.00 HR $70.00 $560.00
Teamster 4.00 HR $72.00 $288.00
Trucking (1.00 DY, 0.00 Trucks, 0.00 LOAD/HR) 0.00 LOAD $0.00 $0.00 Dump Fee - Solids 0.00 LOAD $300.00 $0.00
AC - Asphalt Concrete Paving - Machine - AC 190.00 TON $161.45 $30,675.86 Material 190.00 TON $80.82 $15,356.61
Asphalt Concrete - AC - Conventional Mixes 190.00 TON $80.66 $15,325.40 Environmental Fee Asphalt Concrete (Blue Diamond
Materials)

9.50 LOAD $3.29 $31.21
Labor & Equipment 190.00 TON $80.63 $15,319.25
Asphalt Concrete Paving Crew - Machine End Dump (190.00 TON/DY, 1.00 DY)
190.00 TON $80.63 $15,319.20
Paving Machine Cedar Rapids 8.00 HR $135.00 $1,080.00
Roller 10 - 12 Ton Rex [2] 8.00 HR $40.70 $651.20
Truck Tack 8.00 HR $15.50 $124.00
Skiploader [2] 8.00 HR $35.00 $560.00
Shuttle Buggy; GAP 8.00 HR $400.00 $3,200.00
Street Sweeper 8.00 HR $150.00 $1,200.00
Foreman 8.00 HR $97.00 $776.00
Paving Machine Operator 8.00 HR $91.00 $728.00
Operating Engineer 8.00 HR $91.00 $728.00
Roller Operator [2] 8.00 HR $91.00 $1,456.00
Screedman [2] 8.00 HR $91.00 $1,456.00
Raker [2] 8.00 HR $70.00 $1,120.00
Shoveler [2] 8.00 HR $70.00 $1,120.00
General Laborer [2] 8.00 HR $70.00 $1,120.00
Tack Per SF 1.00 SF $0.05 $0.05
Traffic Control - Streets 1.00 LS $26,532.37 $26,532.37 Materials 1.00 LS $959.20 $959.20
Delineators 20.00 EACH $19.62 $392.40
Signs 5.00 EACH $43.60 $218.00
Special Signs 2.00 EACH $109.00 $218.00
Type II Barricades 2.00 EACH $38.15 $76.30
Type III Barricades 1.00 EACH $54.50 $54.50
Labor & Equipment 1.00 LS $25,573.17 $25,573.17
3/3/2023 7:18:48 AM Beverly Hills Street And Alley Impvts Page 3 of 5 (Item 1 - Hillcrest Main Break Pavement Repairs continued) • -
• - • - • -
@
@
• •
@
Jr
�
�
�
�
�
�
• - • - • - • - • - • - • - • - 0
@
@
• • • ,,
@ •
Description Quantity UM Direct Cost Direct Cost
Unit Total
Traffic Control Set Up/Take Down (1.00 WDAY/DY, 1.00 DY) 1.00 WDAY $1,844.80 $1,844.80 Truck Flatbed With Cones 8.00 HR $18.60 $148.80
General Laborer [2] 8.00 HR $70.00 $1,120.00
Teamster 8.00 HR $72.00 $576.00
Traffic Control Equipment (1.00 WDAY/DY, 17.00 DY) 17.00 WDAY $158.14 $2,688.37 Arrow Board [2] 0.79 MO $500.00 $790.70
Changeable Message Board [2] 0.79 MO $1,200.00 $1,897.67 Traffic Control Flagging (1.00 WDAY/DY, 17.00 DY) 17.00 WDAY $1,120.00 $19,040.00 General Laborer [2] 136.00 HR $70.00 $19,040.00
Maintain Traffic Control - Weekends 1.00 LS $2,000.00 $2,000.00 Manhole And Valve Adjusting 2.00 EACH $3,791.10 $7,582.20 Material 2.00 EACH $0.00 $0.00
Miscellaneous Materials - Each 2.00 EACH $0.00 $0.00
Labor & Equipment 2.00 EACH $3,791.10 $7,582.20
Break Manhole Down Crew (2.00 EACH/DY, 1.00 DY) 2.00 EACH $1,459.80 $2,919.60 Compressor With Attachments 8.00 HR $15.70 $125.60
Jackhammer 8.00 HR $4.00 $32.00
Truck Bobtail 8.00 HR $31.25 $250.00
Concrete Mixer 8.00 HR $5.00 $40.00
Foreman 8.00 HR $97.00 $776.00
General Laborer [2] 8.00 HR $70.00 $1,120.00
Teamster 8.00 HR $72.00 $576.00
Adjust Manhole To Grade Crew (2.00 EACH/DY, 1.00 DY) 2.00 EACH $1,739.80 $3,479.60 Compressor With Attachments 8.00 HR $15.70 $125.60
Jackhammer 8.00 HR $4.00 $32.00
Truck Bobtail 8.00 HR $31.25 $250.00
Concrete Mixer 8.00 HR $5.00 $40.00
Foreman 8.00 HR $97.00 $776.00
General Laborer [3] 8.00 HR $70.00 $1,680.00
Teamster 8.00 HR $72.00 $576.00
Asphalt Concrete Paving Crew - Hand (4.00 EACH/DY, 0.50 DY)

2.00 EACH $591.50 $1,183.00
Truck Tack 4.00 HR $15.50 $62.00
Truck Bobtail 4.00 HR $31.25 $125.00
Wacker 4.00 HR $12.00 $48.00
Foreman 4.00 HR $97.00 $388.00
Raker 4.00 HR $70.00 $280.00
Shoveler 4.00 HR $70.00 $280.00
Striping (Chrisp Company) 1.00 LS $5,000.00 $5,000.00
Mobilization 1.00 LS $8,966.75 $8,966.75
Superintendent 6.00 DY $800.00 $4,800.00
Project Manager 0.25 MO $16,667.00 $4,166.75
3/3/2023 7:18:48 AM Beverly Hills Street And Alley Impvts Page 4 of 5 (Item 1 - Hillcrest Main Break Pavement Repairs continued) ,,
�
• - •
,, -
�
�
,,
• -
@ *
@
@ •
,,
�
�
�
�
• - • - • -
• - •
,, -
�
�
�
• - • - • - 0
@
* *
Direct Cost Totals
Amount
Equipment Rented:

Direct Cost
Percent of
Equipment Owned:

Materials Owned:

Materials Purchased:

Labor:

Subcontracted:

Trucking Owned:

Trucking Hired:

Miscellaneous:

Plug:

Direct Cost:
$185,612.00
$42,698.50
$93,383.19
$71,517.29
$5,000.05
$0.00
$0.00
$73,241.75
$0.00
$0.00
$471,452.78

39.37%

19.81%

0.00%

1.06%

0.00%

0.00%

15.54%

0.00%

9.06%

15.17%
$556,472.00
Bid Price
$85,019.22
Pay Item Summary
Amount
Total Bond:

Total Indirect Cost:

Total Overhead:

Total Profit:

Total Direct Cost:

Total Bid Price:
$471,452.78
$0.00
$0.00
$0.00
Total DC Adds/Cuts: $0.00

84.72%

0.00%

0.00%

0.00%

0.00%

15.28%
Total Overall Cost: $471,452.78
Total Margin: $85,019.22

84.72%

15.28%
Percent of
3/3/2023 7:18:48 AM Beverly Hills Street And Alley Impvts Page 5 of 5