AGENDA REPORT
Meeting Date: May 16, 2023
Item Number:

To: Honorable Mayor & City Council
From: Mandana Motahari, City Architect
Eli Benitez, Associate Project Manager
Subject: ACCEPTANCE OF THE CONTRACT WORK FOR:

A. LIBRARY ROOFING REPAIR AND PARTIAL ROOF
REPLACEMENT PROJECT WITH BEST CONTRACTING, INC.,
IN THE FINAL AMOUNT OF $116,305.02; AND

AUTHORIZATION OF CITY CLERK TO RECORD NOTICE OF

COMPLETION
B. FIRE STATION HEADQUARTERS CHILLER REPLACEMENT
PROJECT WITH THERMAL CONCEPT INC., IN THE FINAL
AMOUNT OF $160,448; AND

AUTHORIZATION OF CITY CLERK TO RECORD NOTICE OF

COMPLETION
Attachments: 1. Notices of Completion

RECOMMENDATION
Library Roofing Repair and Partial Roof Replacement
Staff recommends City Council move to accept the described contract work with Best Contracting, Inc. and authorize the City Clerk to record the attached Notice of Completion.

Fire Station headquarters Chiller Replacement
Staff recommends City Council move to accept the described contract work with Thermal Concept Inc. and authorize the City Clerk to record the attached Notice of Completion.

BEVERLY
HILLS
-�
E-14
Meeting Date: May 16, 2023

Page 2 of 3 ends

INTRODUCTION
This report provides information and requests City Council acceptance of the contract work indicated below and authorization of the City Clerk to record the Notices of Completion with the Los Angeles County Recorder.

DISCUSSION
Library Roofing Repair and Partial Roof Replacement
The Capital Improvement Project No. 00833, New Roofing Installations on City Buildings, provides for City buildings roofing replacement or major repairs. The library roof was assessed and partial roof replacement and some major repairs were identified as a priority. The improvements replaced approximately 1,100 square feet of the single ply roofing system and repair was performed on an approximately 500 square foot area. The recent February and March rainstorms proved the new work to be watertight and successful.

Staff from the Public Works and Community Development Departments inspected the work and are satisfied that all work performed is consistent with construction documents.

Fire Station Headquarters Chiller Replacement
The Capital Improvement Project No. 00786, provides for long-term replacement of City building major infrastructure systems including, but not limited to, HVAC, Plumbing and Electrical systems. The existing chiller at Fire Station headquarters was original to the building constructed in 1990; the unit had reached the end of its serviceable life and was prioritized for replacement. Unit replacement has been completed and the new chiller will deliver a clean, reliable and energy-efficient network of chilled water to the air handler units.

Staff from the Public Works and Community Development Departments inspected the work and are satisfied that all work performed is consistent with construction documents.

FISCAL IMPACT
Library Roofing Repair and Partial Roof Replacement
Funding for this work is budgeted in Fund 405, Capital Improvements Program No. 00833, New Roofing Installations on City Buildings. The total contract amount is $119,675 which includes a contingency amount of $10,879. Due to added scope for additional repairs, one change order in the amount of $7,509.02 was issued. The total project cost amounts to $116,305.02, thus, a balance of $3,369.98 will be credited back to the original funding source.

The current amount paid on the contract is $110,489.75, with a retention balance of $5,816.02 to be paid 35 days after the recordation of the Notice of Completion.

Fire Station Headquarters Chiller Replacement
Funding for this work is budgeted in Fund 405, Capital Improvement Project No. 00811, Major Building Systems Maintenance and Replacement. The total contract amount is $174,827.52, which includes a contingency amount of $18,731.52. Due to added scope, one change order in the amount of $4,352 was issued. The project cost amounts to $160,448, thus a balance of $14,379.52 will be credited back to the original funding source.

Meeting Date: May 16, 2023

Page 3 of 3 ends

The current amount paid on the contract is $152,425.60, with a retention balance of$8,022.40 to be paid 35 days after the recordation of the Notice of Completion.

Shana Epstein,
Director of Public Works
Approved By
Attachment 1

THIS DOCUMENT IS OFFICIAL BUSINESS

OF THE CITY OF BEVERLY HILLS AND

ENTITLED TO FREE RECORDING UNDER
SECTION 6103 OF THE GOVERNMENT CODE
Requested by ___________________________
AFTER RECORDING MAIL TO:

CITY CLERK'S OFFICE
Room 290, City Hall
455 North Rexford Drive
Beverly Hills, CA 90210
Space above this line for recorder's use

NOTICE OF COMPLETION
Notice is hereby given that:

1. The undersigned is owner of the interest or estate stated below in the property hereinafter described.

2. The full name of the undersigned is: City of Beverly Hills

3. The full address of the undersigned is: 455 North Rexford Drive, Beverly Hills, CA 90210

4. The nature of the title of the undersigned is: In fee.

5. The full names and addresses of all persons who hold title with the undersigned are: None

6. A work of improvement on the property hereinafter described was completed on: May 16, 2023

7. The name of the contractor, if any, for such work of improvement was: Best Contracting, Inc.

8. The property on which said work of improvement was completed is in the City of Beverly Hills, County of Los Angeles, and State of California, as is described as: Library Roofing Repair and Partial Roof Replacement Project (Bid No. 23-350-1)

9. The street address of said property is: 444 N. Rexford Dr., BH, CA Dated:

STATE OF CALIFORNIA } Signature of }
COUNTY OF LOS ANGELES } Owner or Owners }
Huma Ahmed, being duly sworn, says: That she is the City Clerk of the City of Beverly Hills, the corporation that executed the foregoing notice as owner of the aforesaid interest or estate in the property therein described; that she makes this verification of behalf of said corporation; that she has read said notice and knows the contents thereof, and that the facts therein stated are true.

Signature of
Corporate Officer
Named Above X

THIS DOCUMENT IS OFFICIAL BUSINESS

OF THE CITY OF BEVERLY HILLS AND

ENTITLED TO FREE RECORDING UNDER
SECTION 6103 OF THE GOVERNMENT CODE
Requested by ___________________________
AFTER RECORDING MAIL TO:

CITY CLERK'S OFFICE
Room 290, City Hall
455 North Rexford Drive
Beverly Hills, CA 90210
Space above this line for recorder's use

NOTICE OF COMPLETION
Notice is hereby given that:

1. The undersigned is owner of the interest or estate stated below in the property hereinafter described.

2. The full name of the undersigned is: City of Beverly Hills

3. The full address of the undersigned is: 455 North Rexford Drive, Beverly Hills, CA 90210

4. The nature of the title of the undersigned is: In fee

5. The full names and addresses of all persons who hold title with the undersigned are: None

6. A work of improvement on the property hereinafter described was completed on: May 16, 2023

7. The name of the contractor, if any, for such work of improvement was: Thermal Concept, Inc.

8. The property on which said work of improvement was completed is in the City of Beverly Hills, County of Los Angeles, and State of California, as is described as: Fire Station headquarters Chiller Replacement Project (Bid No. 22-350-40)

9. The street address of said property is: 445 N Rexford Dr., BH, CA Dated:

STATE OF CALIFORNIA } Signature of }
COUNTY OF LOS ANGELES } Owner or Owners }
Huma Ahmed, being duly sworn, says: That she is the City Clerk of the City of Beverly Hills, the corporation that executed the foregoing notice as owner of the aforesaid interest or estate in the property therein described; that she makes this verification of behalf of said corporation; that she has read said notice and knows the contents thereof, and that the facts therein stated are true.

Signature of
Corporate Officer
Named Above X