AGENDA REPORT
Meeting Date: October 10, 2024
Item Number:

To: Honorable Mayor & City Council
From: Daren Grilley, Assistant Director of Public Works/City Engineer Samer Elayyan, Engineering Services Manager
Subject: ACCEPTANCE OF THE CONTRACT WORK FOR THE

CONSTRUCTION OF THE WATER MAIN REPLACEMENT
PROJECT IN COLDWATER CAÑON DRIVE WITHIN THE CITY

OF BEVERLY HILLS, CALIFORNIA BY WILLIAMS PIPELINE
CONTRACTORS, INC., IN THE FINAL AMOUNT OF
$7,991,971.29; AND

AUTHORIZATION OF CITY CLERK TO RECORD NOTICE OF

COMPLETION
Attachments: 1. Notice of Completion

RECOMMENDATION
Staff recommends that City Council accept the described work by Williams Pipeline Contractors, Inc. (Williams) in the final amount of $7,991,971.29 and authorize the City Clerk to record the attached Notice of Completion.

INTRODUCTION
This report provides information to City Council for the acceptance of the contract work in the final amount of $7,991,971.29 and authorization for the recordation of the Notice of Completion by the City Clerk with the Los Angeles County Recorder.

DISCUSSION
On November 1, 2022, a contract in the amount of $7,461,230 was awarded to Williams on the basis of competitive bids received after public advertising. Additionally, a contingency in the amount of $746,123 (10%) was approved, for a total purchase order amount of $8,207,353. This project scope included the replacement and installation of approximately 11,000 linear feet of 12-inch Ductile Iron Pipe (DIP), the installation of new valves, and the replacement and installation of fire hydrants as well as the installation of two (2) water meter boxes for each property, one for domestic service and the other for a Meeting Date: October 10, 2024

Page 2 of 2 ends

future irrigation meter. In addition to the original scope, the City initiated multiple change orders, including the replacement of a 50-year-old water main along Copley Drive during the reconstruction of the street, and the relocation of approximately 1,000 linear feet of an aged water main along Lago Vista Drive that was located behind the curb.

All construction components were inspected, and staff is satisfied that the work was completed according to the contract documents approved for this project.

The construction contract for the Coldwater Cañon Roadway Rehabilitation Project was awarded at the September 10, 2024 City Council meeting, and the construction is anticipated to start in the fall of 2024.

FISCAL IMPACT
The original construction contract purchase order was $8,207,353 (including a contingency in the amount of $746,123). The final contract amount is $7,991,971.29, leaving a purchase order balance of $215,381.71, which will be returned to the Water Enterprise Fund.

The current amount paid on the contract is $7,594,919.57 with a retention balance of $397,051.72 due to be paid 35 days after the recordation of the Notice of Completion.

Shana Epstein,
Director of Public Works
Approved By
Attachment 1

THIS DOCUMENT IS OFFICIAL BUSINESS

OF THE CITY OF BEVERLY HILLS AND

ENTITLED TO FREE RECORDING UNDER
SECTION 6103 OF THE GOVERNMENT CODE
Requested by Huma Ahmed
AFTER RECORDING MAIL TO:

CITY CLERK'S OFFICE
Room 290, City Hall
455 North Rexford Drive
Beverly Hills, CA 90210
Space above this line for recorder's use

NOTICE OF COMPLETION
Notice is hereby given that:

1. The undersigned is owner of the interest or estate stated below in the property hereinafter described.

2. The full name of the undersigned is City of Beverly Hills

3. The full address of the undersigned is 455 North Rexford Drive, Beverly Hills, CA 90210

4. The nature of the title of the undersigned is: In fee.

5. The full names and addresses of all persons who hold title with the undersigned are:

None

6. A work of improvement on the property hereinafter described was completed on October 10, 2024

7. The name of the contractor, if any, for such work of improvement was WILLIAMS PIPELINE CONTRACTORS, INC.

8. The property on which said work of improvement was completed is in the City of Beverly Hills, County of Los Angeles, and State of California, as is described as:

CONSTRUCTION OF THE WATER MAIN REPLACEMENT PROJECT IN COLDWATER CAÑON DRIVE WITHIN THE CITY OF BEVERLY HILLS (RFB 23-350-15)

9. The street address of said property is: None
Dated: City of Beverly Hills
STATE OF CALIFORNIA } Signature of }
COUNTY OF LOS ANGELES } Owner or Owners }
Huma Ahmed, being duly sworn, says: That she is the City Clerk of the City of Beverly Hills, the corporation that executed the foregoing notice as owner of the aforesaid interest or estate in the property therein described; that she makes this verification of behalf of said corporation; that she has read said notice and knows the contents thereof, and that the facts therein stated are true.

Signature of
Corporate Officer
Named Above X