AGENDA REPORT
Meeting Date: June 9, 2026
Item Number:

To: Honorable Mayor & City Council
From: Daren Grilley, Assistant Public Works Director/City Engineer Christine Chung, Project Manager
Subject: AMENDMENT NO. 10 TO AN AGREEMENT BETWEEN THE

CITY OF BEVERLY HILLS, THE LOS ANGELES COUNTY

METROPOLITAN TRANSPORTATION AUTHORITY, AND

ENVIRONMENTAL INTELLIGENCE, LLC, FOR INDEPENDENT
COMPLIANCE MONITORING SERVICES FOR SEGMENTS 1
AND 2 OF THE PURPLE LINE EXTENSION PROJECT; AND

APPROVAL OF A PURCHASE ORDER IN THE AMOUNT OF
$1,359,700 FOR FISCAL YEAR 2026/27 FOR A TOTAL
CONTRACT AMOUNT NOT TO EXCEED $21,804,200
Attachments: 1. Draft Amendment No. 10

RECOMMENDATION
Staff recommends that City Council approve Amendment No. 10 to the Agreement with Los Angeles County Metropolitan Transportation Authority (Metro) and Environmental Intelligence, LLC (EI) to provide independent compliance monitoring services related to Sections 1 and 2 of the Purple Line Extension project; and approve a purchase order in the amount of $1,359,700 for Fiscal Year 2026/27 for a total contract amount not to exceed of $21,804,200. The cost of EI’s services associated with the Purple Line Extension Project will be reimbursed by Metro with the exception of an estimated $10,000.00 in Fiscal Year 2026-27 for in-person monitoring at Beverly Hills High School (or “BHHS”), which is paid for by the City.

INTRODUCTION
On September 5, 2017, City Council approved a one-year agreement between the City, Metro and EI for independent compliance monitoring services. Between 2018 and 2021, City Council approved Amendment Nos. 1 to 4 providing additional funding through each Fiscal Year up to June 30, 2022, for a total contract amount not to exceed $9,863,100. On Meeting Date: June 9, 2026

Page 2 of 3 ends

January 18, 2022, City Council approved Amendment No. 5, extending the Agreement’s termination to December 31, 2025, subject to annual extension for each year beyond June 30, 2022. Amendment Nos. 6, 7, 8, and 9 were approved in June 2022, May 2023, May 2024, and June 2025, providing additional funding for a total not-to-exceed amount of $20,444,500 and service term through June 30, 2026.

DISCUSSION
The current Memorandum of Agreements (MOAs) for Sections 1 and 2 of the Purple Line Subway Extension Project between the City and Metro requires an Independent Compliance Monitor (ICM) to provide oversight and enforcement to ensure Metro and its contractors comply with the conditions and mitigation measures outlined in the MOAs and the City Council authorized permits. In accordance with the terms of the MOAs, Metro will reimburse the City for the cost of ICM services associated with the Purple Line Extension Project.

Metro and the City jointly selected EI as a third-party monitor through a Request for Qualification process to provide the ICM services for Section 1 and Section 2 construction projects. EI began working with the City and Metro in September 2017.

Their primary scope of services includes:
 Verify Metro’s compliance with any and all conditions and mitigation measures included in the Section 1 and Section 2 MOAs, including all City-issued permit conditions.
 Enforce the conditions and mitigation measures as provided under the MOA Articles, “Enforcement of Permit Conditions and Mitigation Measures,” as necessary to achieve compliance.
 On February 19, 2019, the City and Metro executed the MOA for Design Build of Section 2 Station, which included the requirement for the ICM to be onsite at BHHS for certain work activities during specific hours when school is in session. The City agreed to absorb the cost of monitoring at BHHS. Metro’s construction impacts at BHHS are expected to be minimal in FY2026/27.
 Submit weekly summary reports, including documentation of any violations, which are made available to the public at www.beverlyhills.org/purpleline. From EI’s commencement date of September 11, 2017, through May 11, 2026, EI has issued 415 violations of MOA or permit conditions for Section 1 and 893 violations for Section 2. Based on these violations, Metro has released monetary contributions totaling $635,000 for Section 1 and $4,250,000 for Section 2 to date. An additional $615,000 for Section 1 and $1,300,000 for Section 2 remain pending for violationrelated payments. The City has utilized these monetary contributions toward construction mitigation measures, including the purchase of noise and dust mitigation devices, as well as the paving of Wilshire Boulevard and vicinity streets near the stations.

While the Wilshire/La Cienega Station is scheduled to open May 8, 2026, work will continue through fall 2026 for street restoration and punch-list items. Final paving along Wilshire Boulevard between Stanley Drive and San Vicente Boulevard is anticipated in fall 2026. In Section 2, street restoration near Beverly Dr Station is expected by November 2026 with additional repairs and paving work west of Beverly Drive continuing into spring 2027.

Meeting Date: June 9, 2026

Page 3 of 3 ends

Because FY 2026/27 is expected to be the final year of construction within the City’s rightof-way, staff recommend retaining EI’s services until the City formally accepts the restored infrastructure.

FISCAL IMPACT
The total estimate for ICM services from July 2026 through June 2027 is $1,359,700. Per the existing MOAs, Metro will reimburse the City for the majority of these costs. The City will be responsible for approximately $10,000 for monitoring at BHHS. This agreement requires a FY 2026/27 appropriation of $1,359,700 from the General Fund (Account No. 001-12401-731220), as reflected in the FY 2026/27 Proposed Budget scheduled for City Council adoption on June 23, 2026, and a corresponding purchase order for Fiscal Year 2026/27 for a total contract amount not to exceed $21,804,200. Any unused funds at the end of the fiscal year will be returned to the General Fund as done in prior years.

Environmental Intelligence Contract Amendment
Amount
Total
Not To Exceed
Original Contract (481-17) Year 1 $1,472,540 $1,472,540 Amendment 1 (512-18) Year 2 $1,279,860 $2,752,400
Amendment 2 (459-19) Year 3 $1,247,600 $4,000,000
Amendment 3 (137-20) Year 4 $3,100,000 $7,100,000
Amendment 4 (182-21) Year 5 $2,763,100 $9,863,100
Amendment 5 (50-22) –
Extended termination date to 2025 N/A N/A
Amendment 6 (368-22) Year 6 $3,021,700 $12,884,800
Amendment 7 (241-23) Year 7 $2,766,000 $15,650,800
Amendment 8 (224-24) Year 8 $2,799,500 $18,450,300
Amendment 9 (242-25) Year 9 $1,994,200 $20,444,500
Amendment 10 (Proposed) Year 10 $1,359,700 $21,804,200
EI bills on a time-and-materials basis, using rates set forth in Exhibit B of the Agreement.

Shana Epstein,
Director of Public Works
Approved By
Attachment 1
1 B0785-0001\3240312v2.doc
AMENDMENT NO. 10 TO AN AGREEMENT BETWEEN THE

CITY OF BEVERLY HILLS, THE LOS ANGELES COUNTY

METROPOLITAN TRANSPORTATION AUTHORITY, AND

ENVIRONMENTAL INTELLIGENCE, LLC, FOR

INDEPENDENT COMPLIANCE MONITORING SERVICES
FOR SEGMENTS 1 AND 2 OF THE PURPLE LINE EXTENSION

PROJECT
NAME OF CONSULTANT: Environmental Intelligence, LLC
CONSULTANT’S RESPONSIBLE PRINCIPAL: Kristina Hysler
Regional Vice President, Consulting &
Engineering Segment
CONSULTANT’S ADDRESS: 811 West 7th Street
9 th Floor
Los Angeles, CA 90017
CITY’S ADDRESS: City of Beverly Hills
345 N. Foothill Road
Beverly Hills, CA 90210
CITY’S RESPONSIBLE PRINCIPAL: Daren Grilley, City Engineer MTA’S ADDRESS Los Angeles County Metropolitan
Transportation Authority
One Gateway Plaza, 17th Floor
Los Angeles, CA 90012

MTA’S RESPONSIBLE PRINCIPALS: Steve Kim (Segment 1)
Ayokunle Ogunrinde (Segment 2)
COMMENCEMENT DATE: September 11, 2017
TERMINATION DATE: September 30, 2019 (as amended by
Amendment No. 1)
September 20, 2020 (as amended by
Amendment No. 2)
June 30, 2021 (as amended by Amendment
No. 3)
June 30, 2022 (as amended by Amendment
No. 4)
June 30, 2023 (as amended by Amendment
No. 6)
[Continued on next page]
2 B0785-0001\3240312v2.doc
June 30, 2024 (as amended by Amendment
No. 7)
June 30, 2025 (as amended by Amendment
No. 8)
June 30, 2026 (as amended by Amendment
No. 9)
June 30, 2027 (as amended by this
Amendment No. 10), unless extended
pursuant to Section 2 of the original
Agreement
CONSIDERATION: Original Agreement:

Not to exceed: $1,472,540
Amendment No. 1:

Not to exceed an additional: $1,279,860

Amendment No. 2:

Not to exceed an additional: $1,247,600
Amendment No. 3:

Not to exceed an additional: $3,100,000
($265,000 in Fiscal Year (“FY”) 2019-2020;
$2,835,000 in FY 2020-2021)
Amendment No. 4:

Not to exceed an additional: $2,763,100 in
FY 2021-2022
Amendment No. 5:

No change in the Agreement amount
Amendment No. 6:

Not to exceed an additional: $3,021,700 in
FY 2022-2023
Amendment No. 7:

Not to exceed an additional: $2,766,000 in
FY 2023-2024
[Continued on next page]
3 B0785-0001\3240312v2.doc
Amendment No. 8:

Not to exceed an additional: $2,799,500 in
FY 2024-2025
Amendment No. 9:

Not to exceed an additional: $1,994,200 in
FY 2025-2026
Amendment No. 10:

Not to exceed an additional: $1,359,584 in
FY 2026-2027
Total Not to Exceed: $21,804,200 based on
the rates set forth in Exhibit B
4 B0785-0001\3240312v2.doc
AMENDMENT NO. 10 TO AN AGREEMENT BETWEEN THE

CITY OF BEVERLY HILLS, THE LOS ANGELES COUNTY

METROPOLITAN TRANSPORTATION AUTHORITY, AND

ENVIRONMENTAL INTELLIGENCE, LLC, FOR

INDEPENDENT COMPLIANCE MONITORING SERVICES
FOR SEGMENTS 1 AND 2 OF THE PURPLE LINE EXTENSION

PROJECT
This Amendment No. 10 is to that certain agreement between the City of Beverly Hills (hereinafter called “CITY”), the Los Angeles County Metropolitan Transportation Authority (hereinafter called “MTA”) and Environmental Intelligence, LLC, (hereinafter called “CONSULTANT”) dated September 5, 2017, and identified as City of Beverly Hills Contract No. 481-17, as amended by Amendment No. 1, dated August 7, 2018, Amendment No. 2 dated August 6, 2019, and identified as Contract No. 512-18, Amendment No. 3 dated March 31, 2020, and identified as Contract No. 137-20, Amendment No. 4 dated June 1, 2021, and identified as Contract No. 182-21, Amendment No. 5 dated January 18, 2022, and identified as Contract No. 50-22, Amendment No. 6 dated June 14, 2022, and identified as Contract No. 368-22, Amendment No. 7 dated May 2, 2023, and identified as Contract No. 241-23 (“Agreement”), Amendment No. 8 dated May 21, 2024, and identified as Contract No. 224-24 (“Agreement”), and Amendment No. 9 dated June 3, 2025, and identified as Contract No. 242-25 (“Agreement”).

RECITALS
A. CITY and MTA entered into the Agreement with CONSULTANT in order to procure independent compliance monitoring services for the construction of Segments 1 and 2 of the Purple Line Extension Project, with such services more particularly described in Exhibit A of the Agreement (“services”).

B. The services are currently intended to implement and comply with:
(1) the Memorandum of Agreement for Contract C1045 of the Purple Line Extension Project – Segment 1 – Between the City of Beverly Hills and the Los Angeles County Metropolitan Transportation Authority, CITY Agreement No. 66-17, attached to the Agreement as Exhibit D and incorporated herein by this reference; (2) the Memorandum of Agreement for Contract C1120 of the Purple Line Extension Project – Between the City of Beverly Hills and the Los Angeles County Metropolitan Transportation Authority, CITY Agreement No. 71-19, attached to the Agreement as Exhibit H and incorporated herein by this reference; and
(3) any subsequent permits or conditions of approval issued by CITY or amendments to the memoranda of agreement between CITY and MTA related to construction for 5 B0785-0001\3240312v2.doc
the Purple Line Extension Project (Exhibits D, H, and such future permits, conditions of approval, and/or amendments are collectively referred to as the “MOA”).

C. The purpose of the services is to ensure MTA and its contractor(s) comply with all mitigation measures and conditions included in the MOA, subsequent permits or conditions of approval issued by the CITY, and any amendments to the MOA between the CITY and MTA during MTA’s construction for the Purple Line Extension Project.

D. CITY, MTA, and CONSULTANT desire to extend the Agreement’s Termination Date and increase the Consideration.

E. CONSULTANT further represents that it continues to have no pre-existing relationship with either CITY or MTA, aside from this Agreement, that would prevent CONSULTANT from faithfully and capably performing the services.

NOW, THEREFORE, the parties agree as follows:

Section 1. The Termination Date shall be amended as set forth on the cover page of this Amendment 10.

Section 2. The Consideration shall be amended as set forth on the cover page of this Amendment No. 10.

Section 3. Exhibit B “Compensation” shall be amended as attached hereto and incorporated herein by this reference.

Section 4. Except as specifically amended by previous amendments and this Amendment No. 10, the remaining provisions of the Agreement shall remain in full force and effect.

EXECUTED the day of 2026, at Beverly Hills,
California.

CITY OF BEVERLY HILLS
A Municipal Corporation
_________________________________
CRAIG A. CORMAN
Mayor of the City of Beverly Hills, California
ATTEST:

_____________________________(SEAL)

HUMA AHMED
City Clerk
6 B0785-0001\3240312v2.doc
[Signatures continue]
APPROVED AS TO FORM: APPROVED AS TO CONTENT:
___________________________ ___________________________ LAURENCE S. WIENER NANCY HUNT-COFFEY
City Attorney City Manager
___________________________
SHANA E. EPSTEIN
Director of Public Works
___________________________

DAREN GRILLEY
Assistant Director of Public Works /
City Engineer
___________________________
SHARON L’HEUREUX DRESSEL
Risk Manager
___________________________

ANTHONY RODSTEIN
Purchasing Service Manager
[Signatures continue]

7 B0785-0001\3240312v2.doc

LOS ANGELES COUNTY METROPOLITAN
TRANSPORTATION AUTHORITY:
________________________________

STEPHANIE WIGGINS
Chief Executive Officer
________________________________

TIMOTHY LINDHOLM
Chief Program Management Officer
______________________________

SAMEH GHALY
Deputy Chief Program Management Officer
APPROVED AS TO FORM:
________________________________
RONALD W. STAMM
Principal Deputy County Counsel
[Signatures continue]
8 B0785-0001\3240312v2.doc
ENVIRONMENTAL INTELLIGENCE LLC:
________________________________

KRISTINA HYSLER
Vice President, Consulting & Engineering
Segment

9 B0785-0001\3240312v2.doc

EXHIBIT B

COMPENSATION
CONSULTANT shall be compensated for professional services provided on a time and materials basis in an amount not to exceed a total of Twenty-One Million Eight Hundred Four Thousand Two Hundred Dollars ($21,804,200). Of this total, Amendment No. 10 to this Agreement allocates One Million Three Hundred Fifty-Nine Thousand Seven Hundred Dollars ($1,359,700) in Fiscal Year 2026-2027 commencing July 1, 2026 and ending June 30, 2027, in accordance with the following billing rates: