City of Brisbane
City Council Special Meeting Agenda
Monday, November 30, 2026 at 5:30 PM ● Hybrid Meeting ● 50 Park Place, Brisbane, CA The public may observe/participate in City Council meetings using remote public comment options or by attending in person. The City Council may take action on any item listed in the agenda.

To Address the Council
In Person:

Location: Community Meeting Room 50 Park Place, Brisbane, CA 94005 To address the City Council on any item – whether on the posted agenda or not – please fill out a Request to Speak Form located in the Community Meeting Room Lobby and submit it to the City Clerk, preferably before the start of the meeting. Speakers are not required to submit their name or address.

Remote Participation:

Members of the public may observe/participate in the City Council meeting by logging into the Zoom Webinar listed below. City Council meetings may also be viewed live and/or on-demand via the City’s YouTube Channel, youtube.com/brisbaneca, or on Comcast Ch. 27. Archived videos may be replayed on the City’s website, brisbaneca.gov/meetings. Please be advised that if there are technological difficulties, the meeting will nevertheless continue if remote participation is available.

The agenda materials may be viewed online at brisbaneca.gov at least 72 hours prior to a Regular Meeting, and at least 24 hours prior to a Special Meeting.

Remote Public Comments:

Remote meeting participants may address the City Council via Zoom Webinar. Aside from commenting personally while in the Zoom Webinar, you can also use the call in number. The public comments received will be noted for the record during Oral Communications 1 and 2 or during an agenda item. We encourage you to email comments in advance of the meeting to [email protected]. That email address, however, will not be monitored during the meeting and emails received during the meeting will not be responded to or brought to the attention of the City Council during the meeting.

Join Zoom Webinar: zoom.us (please use the latest version: zoom.us/download) brisbaneca.gov/cc-zoom
Webinar ID: 991 9362 8666
Call In Number: 1 (669) 900-9128
Note: Callers dial *9 to “raise hand” and dial *6 to mute/unmute.

Special Assistance:

If you need special assistance to participate in this meeting, please contact the City Clerk at (415) 508- 2113.

Notification in advance of the meeting will enable the City to make reasonable arrangements to ensure accessibility to this meeting.

Page 1 of 15 ends

November 30, 2026 -2- 5:30 PM
Writings that Are Received After the Agenda Has Been Posted Any writings that are received after the agenda has been posted but before 4pm of the day of the meeting will be available for public inspection at the front lobby in City Hall and on the internet (brisbaneca.gov/meetings).

Any writings that are received after 4pm of the day of the meeting will be distributed to the Council and made available for public inspection at the front lobby and on the internet the day after the meeting (brisbaneca.gov/meetings).

Call to Order – Pledge of Allegiance
Roll Call
A. Remote Attendance Under the Just Cause Provisions of the Brown Act Adoption of Agenda
Continued Public Hearings
B. Consideration of proposed Baylands Specific Plan and related actions, including amendments to the Brisbane General Plan Land Use and Circulation Elements, amendments to TitleSection 17 of the Brisbane Municipal Code to establish zoning regulations, adoption of the Bayshore Mobility Plan, and certification of the Final Environmental Impact Report (FEIR)prepared for this project in accordance with the California Environmental Quality Act (CEQA).

Adjournment

Page 2 of 15 ends

Baylands Specific Plan and EIR – Meeting 10 Page 1 of 4

CITY COUNCIL MEMO
Meeting Date: November 30, 2026
From: Kevin Gardiner, Interim Community Development Director Subject: Baylands Subarea – Additional Topics
Introduction
Tonight’s meeting is the tenth in the ongoing public hearing on the Brisbane Baylands Specific Plan, Final Environmental Impact Report (FEIR), and related approvals that began on September 14, 2026. The meetings are structured around Measure JJ requirements and major project components, enabling a step-by-step review of the materials and of how the project addresses Measure JJ’s requirements.

At the November 9, 2026 meeting councilmembers requested further discussions of the FEIR alternatives and public safety. These topics were scheduled for the November 19, 2026 meeting but were not reached, and are presented again for discussion tonight.

Public Safety
The staff memo prepared for the November 19, 2026 meeting stated that the Specific Plan includes new police and fire facilities, and it described fire station locations, a police substation, and the timing for each. That description was not accurate. The Draft Specific Plan does not identify locations for future fire stations or police facilities, and it does not establish their size, staffing, or timing. Those details come from two technical appendices to the FEIR, the Police Facilities and Staffing Plan and the Fire Protection Services Plan (FEIR Appendices N.1 and N.2), which were prepared to estimate the level of police and fire services needed to serve buildout of the Specific Plan for the purposes of evaluating the project's environmental effects of constructing facilities that would provide police and fire services. The discussion below has been revised to reflect this.

Police services in the Baylands would be provided by the Brisbane Police Department, and fire and emergency medical services by the North County Fire Authority (NCFA). The FEIR estimates that buildout of the Specific Plan would add about 4,905 residents and 19,480 workers, roughly doubling calls for both police and fire service. To determine whether this growth would require new or expanded facilities, the FEIR relied on the two appendices, which describe one way that facilities and staffing could be provided to maintain service levels. Based on that analysis and the associated mitigation measures, the FEIR concludes that impacts on public services would be less than significant.

The Police Facilities and Staffing Plan in Appendix N.1 describes a police substation within the Baylands, in a visible, publicly accessible ground-floor location, open before the first certificate of occupancy, along with a second patrol beat before grading begins and added 24-hour staffing as development proceeds. It does not identify a site for the substation. The Fire Protection Services Plan in Appendix N.2 describes relocating Fire Station No. 81 from 3445 Bayshore Boulevard to 140 Valley Drive, across from City Hall, and building a second station in the northeastern Baylands near the US 101 interchange, which would house an aerial ladder company and a squad once the Geneva Avenue bridge over the Caltrain tracks is complete. It assumes that the a temporary relocated station would be needed prior to the start of construction on any Baylands building 75 feet or taller, and a new Baylands station would be

Page 3 of 15 ends

Baylands Specific Plan and EIR – Meeting 10 Page 2 of 4 constructed prior to occupancy of 50 percent of the mid- and high-density residential or commercial areas. It also carries forward response standards from the 2018 Program EIR, including a four-minute travel time for the first engine company on 90 percent of incidents and a requirement that all Baylands development be within 1.5 miles of a fire station and 2.0 miles of a ladder truck. The FEIR concludes that the physical impacts of constructing police and fire facilities would be no different from the impacts associated with overall Baylands development. Therefore, the FEIR does not require further mitigation measures related to police and fire facilities.

Because these details appear only in the FEIR appendices, they are planning assumptions used for the environmental analysis rather than requirements of the Specific Plan. Unless they are carried into the Specific Plan, the Development Agreement, or the conditions and mitigation measures adopted with the project, the locations of public safety facilities, their timing, and who would build and fund them remain to be determined. The question of whether facilities would be near the new residential districts is therefore still open. The residential districts are concentrated in the northwest portion of the Baylands around the Bayshore Caltrain station, and neither fire station site described in Appendix N.2 is within those districts.

Staff recommends that the project approvals secure public safety facilities through one or more of the following: (1) Specific Plan policies requiring adequate police and fire facilities, with siting criteria and timing tied to development milestones, such as requiring that all Baylands development, including each residential district, meet the response time and distance standards in every phase; (2) Development Agreement provisions for land dedication, construction, and funding of facilities, equipment, and staffing, including interim services until permanent facilities are in place; and (3) adopted conditions that define appropriate timing triggers for increased public safety facilities.

If the Council prefers particular locations, such as a police substation near the Caltrain station or a fire station within or near the residential districts, it can seek to negotiate for those to be dedicated in connection with the Development Agreement. Any configuration that differs from the appendices would be reviewed with NCFA and the Police Department and checked against the FEIR. Staff requests Council direction on these public safety concerns at tonight's meeting.

FEIR Alternatives
The California Environmental Quality Act (CEQA) requires an Environmental Impact Report (EIR) to describe and evaluate a reasonable range of alternatives to a project that would feasibly attain most of the project's basic objectives while avoiding or substantially lessening one or more of its significant environmental effects (CEQA Guidelines Section 15126.6). The alternatives give the Council and the public a basis for comparing the proposed Specific Plan with other ways the site could be developed.

The EIR must also identify an “environmentally superior” alternative other than the “No Project Alternative.” If the Council approves the Specific Plan or an alternative that results in significant and unavoidable environmental effects, it must adopt findings that include a “statement of overriding considerations” explaining why the selected project is desirable notwithstanding the unavoidable impacts.

Chapter 8 of the FEIR (Volume 3, Revised Draft EIR) evaluates two No Project alternatives (No Project-No Build and No Project-General Plan Buildout) and seven land development alternatives in two groups:
one group that maintains the proposed density of 2,200 units and 6.5 million square feet of commercial

Page 4 of 15 ends

Baylands Specific Plan and EIR – Meeting 10 Page 3 of 4 space, and one group that reduces the allowable development program. The proposed density alternatives retain the Specific Plan's 2,200 units: Alternative 1 (Proposed Density Development Around an Operating 45-Acre Light Maintenance Facility); Alternative 2 (Proposed Density, Balanced Commercial), which shifts about 400,000 square feet of office space from west to east of the Caltrain tracks; and Alternative 3 (Proposed Density, Lower Maximum Building Heights), which limits commercial buildings to 12 stories and residential buildings to 8 stories. The reduced density alternatives lower the intensity of development: Alternative 4 (Reduced Commercial Development) retains 2,200 units but reduces commercial space to 4.5 million square feet, while Alternatives 5, 6, and 7 reduce the residential total to 1,800 units and commercial space to 4.5 million square feet, differing in the location of commercial development, the presence of an operating light maintenance facility, and building height. The FEIR also describes alternatives that were considered but rejected, including an alternative location and several water supply alternatives.

The FEIR identifies Alternative 7, Reduced Density, Lower Maximum Building Height, as the “environmentally superior” alternative. Alternative 7 would include 1,800 dwelling units, 4.5 million square feet of commercial and office space, and 500,000 square feet of hotel space, compared to 2,200 units and 6.5 million square feet of commercial and office space under the Specific Plan. It would limit commercial buildings to 12 stories and residential buildings to 8 stories, eliminating the towers of 20 or more stories allowed under the Specific Plan, and would expand the planned solar farm so that more of the Baylands' electricity is generated on site. Alternative 7 would reduce several significant impacts, including operational air emissions , but would not avoid all of them; traffic noise, the permanent increase in ambient noise, and construction emissions would remain significant and unavoidable. In addition, Alternative 7 would result in a higher per capita VMT as compared with the Specific Plan, which means it would result in a smaller reduction in regional VMT and mobile source GHG emissions than the Specific Plan. The FEIR finds that Alternative 7 would meet most of the project objectives, although to a lesser degree for housing production, office-based employment, and fiscal performance.

In CEQA terms, “environmentally superior” is a comparative designation. It identifies the alternative that, on balance, would result in fewer or less severe significant environmental effects than the proposed project and the other alternatives evaluated in the EIR. It does not mean the alternative would have no environmental impacts; as noted above, Alternative 7 would still result in several significant and unavoidable impacts, and in some respects, such as per capita VMT, it would perform worse than the Specific Plan. The designation is also not a finding that the alternative would best meet the project objectives, be economically or financially viable, or be more sustainable over the long term. The EIR's comparison is limited to physical environmental effects and does not weigh factors such as housing production, fiscal performance, market feasibility, or broader sustainability goals.

CEQA does not require the Council to approve the environmentally superior alternative. However, if the Council approves a project other than the environmentally superior alternative, it must make findings, supported by substantial evidence, that the alternative is infeasible for specific economic, legal, social, technological, or other reasons, which may include its failure to meet project objectives (CEQA Guidelines Section 15091).

Because each alternative was analyzed in the FEIR, there is CEQA analysis to support approval of the Specific Plan as proposed, approval of an alternative, or approval of a hybrid option that incorporates elements of an alternative. However, the current version of the draft Specific Plan includes development

Page 5 of 15 ends

Baylands Specific Plan and EIR – Meeting 10 Page 4 of 4 standards and a land use plan that align with Modified Alternative 1 (2,200 units (to be further amended to 1,800 units per Council’s recent direction), 6.5 million commercial square feet, and a 45-acre HSR LMF east of the railroad tracks), so selecting a different alternative would require updates to the Specific Plan prior to its adoption, and the scope of those changes depends on the alternative chosen. Some changes, such as shifting office space between the east and west sides of the Caltrain tracks under Alternative 2, would be relatively limited. Others, such as Alternative 7, would require revisions to the land use plan, development standards and height limits, development program, phasing, and infrastructure planning.

Substantial modifications that the Planning Commission has not previously considered may also need to be referred back to the Commission for a recommendation, depending on the nature of the changes.

Selecting an alternative would also require staff to revise the CEQA Findings, the Statement of Overriding Considerations, and the Mitigation Monitoring and Reporting Program (MMRP) so that they reflect the version of the project Council ultimately approves, including which significant impacts remain, the reasons the Council finds the remaining impacts acceptable, and which mitigation measures apply. This work would take time and would extend the time period for Council action on the Specific Plan and FEIR beyond the intended December 17, 2026 decision date. Staff therefore requests that the Council indicate at tonight's meeting whether it wishes to pursue any alternative, or elements of an alternative, so that staff can advise on the scope and schedule of the needed revisions.

Follow-Up Items
At the November 9, 2026 meeting, councilmembers identified 28 follow-up items related to the Baylands Specific Plan. Staff has compiled these items into a matrix that was reviewed and accepted by the City Council on November 19th, and staff is preparing edits to the specific plan based on these responses.

Mayor Makin had not identified priorities at the November 9th meeting, as she noted she preferred to submit her priorities in writing. Those priorities have now been added to the matrix as Items 29 – 43.

The previous 28 items are retained in this document for reference but are unchanged from the prior version.

Attachments

1. Baylands Specific Plan: Council Follow-Up Items and Staff Responses, Items 1 – 43, dated November 30, 2026
___________________________________ ________________________________ Kevin Gardiner Jeremy Dennis, City Manager
Interim Community Development Director

Page 6 of 15 ends

Baylands Council Follow-Up Matrix | Page 1 of 9
Baylands Specific Plan: Council Follow-Up Items and Staff Responses November 30, 2026
Councilmembers identified priorities and follow-up items at the November 9, 2026 Baylands public hearing; this matrix groups them into 11 themes for staff response and direction back to Council. The matrix was reviewed and accepted by the City Council on November 19th, and staff is preparing edits to the specific plan based on these responses.

Mayor Makin had not identified priorities at the November 9th meeting, as she noted she preferred to submit her priorities in writing. Those priorities have now been added to the matrix as Items 29 – 43. The previous 28 items are retained in this document for reference but are unchanged from the prior version.

Follow-Up Items by Theme
# Council Statement Councilmember Staff Response
1 Consider designating 1,800
residential units as the baseline
within the specific plan.

Terry O'Connell Feasible, assuming Housing Element consistency is maintained.

The certified 2023-2031 Housing Element (HE) already counts the Baylands at 1,800 units (145 very low, 82 low, 287 moderate, 1,286 above moderate; HE Table 3-2), so a 1,800-unit baseline matches the sites inventory.

However, HE Program 2.A.2 commits the City to a Specific Plan that allows 1,800 to 2,200 units by right, without discretionary design review. Although the Program notes that the site inventory is conservatively based on an 1,800 unit total, the City may wish to continue planning for 2,200 units to maintain a larger buffer of available sites.
2 Start at 1,800 residential units as
the baseline planning assumption
because it preserves room for
negotiation in the development
agreement. The developer will want
the 2,200 units, so there needs to
be room for the City to have
something to negotiate, among
other things.

Madison Davis See item 1. One potential strategy could be an incentive-based zoning approach, wherein 1,800 units are permitted for projects that meet the Specific Plan’s baseline standards but development between 1,800 and 2,200 units requires predefined community benefits, such as enhanced affordability, additional open space, community-serving retail, or other defined standards. Such approach can also be further refined in connection with the Development Agreement anticipated to be completed following Specific Plan adoption
3 Consider remediation being done
by district in its entirety before
moving on to building of that district.

Terry O'Connell Partially feasible. Remediation is governed by the approved Remedial Action Plans (DTSC, October 5, 2021; Regional Water Board OU-2, December 17, 2021; Final EIR Appendices K.4 and K.5; HE Section 3.1.2) and the Title 27 closure plan for the former landfill (Revised Draft EIR Section 4.13). These are organized by operable unit, not by Specific Plan district. Staff recommends a coordination in phasing between operable units and districts, plus deference to the Remedial Action Plan (RAP) and Remedial Design and Implementation Plan (RDIP) to say no occupancy until remediation sufficient to operate the use safely has been completed in accordance with regulatory agency standards.
4 Was under the impression that we
would be doing full westside
remediation prior to any
infrastructure or housing. Would like
to have the minimum viable product
requirement as well, and would like
to understand the feasibility of
doing it by district.

Frank Kern See item 3 above.
5 All remediation necessary to make
the residential areas safe for their
intended use must be completed
and approved before the first
residential unit is occupied. All
residential remediation must be
done before anyone moves in.

Madison Davis See item 3 above.
6 Find a way to be more specific on
phasing language, with
benchmarking that runs ahead of
the actual need for the proposed
amenity or infrastructure, so that we
Terry O'Connell Staff recommends replacing the phasing narrative with a phasing table of objective triggers. Each block of residential units or commercial square footage would be tied to infrastructure and amenities that must be complete (not just started) before building permits or occupancy, sized ahead of demand. Triggers should

Page 7 of 15 ends

Baylands Council Follow-Up Matrix | Page 2 of 9
# Council Statement Councilmember Staff Response
are never running behind what
infrastructure we need before the
need is there.
include the legally enforceable water supply agreement the General Plan requires (HE Section 4.1.3.2) and the on-site sewer and water recycling facility the HE identifies as required (HE Section 4.1.3.1), along with roads, storm drainage, parks, and public facilities. 7 Performance standard around the
Geneva Avenue extension,
especially the bridge. For example,
the bridge needs to be 50%
complete in terms of construction
before construction begins on
housing, or something like that.

Frank Kern Staff supports a Geneva Avenue performance standard but recommends milestones that are objective and verifiable, such coordination with the timing of public safety facilities, and/or the approval of higher traffic-generating uses such as offices. A percent-complete test is hard to verify. Related to items 6 and 21. 8 Feasibility of not accepting streets,
utility corridors, parks, and open
space until either the east or the
west side is completed. That way
we will know if those connect, if
they are working correctly, and if
there are any issues with their
construction.

Terry O'Connell Should streets and open spaces remain private (but publicly accessible), the City would not accept streets, utilities, parks, or open space at any point. Utilities would remain under the ownership of the respective providers. The question then becomes how to ensure quality and long-term private stewardship. Staff recommends the Specific Plan state that all streets, utilities, parks, and open space remain privately owned and maintained, with recorded public access easements; require construction to City standards with City inspection and testing before occupancy of the area served; and require a funded master association with long-term maintenance funding in place before the first sale (item 11).

Answer together with items 9 and 10.
9 Feasibility of not accepting streets,
utility corridors, parks, and open
space until either the east or the
west side is completed.

Frank Kern See item 8.
10 Performance standard stating that
the developer will own the
infrastructure on the east side until
it is fully built and delivered, before
the City takes it over.

Frank Kern If infrastructure remains private and/or under the ownership of the respective utility providers, east side infrastructure would stay private permanently, not just until build-out. Staff recommends the plan say so explicitly, with landfill cap, settlement, and Title 27 closure obligations remaining with the owner and master association, backed by long-term funding and financial assurance. 11 Secure permanent public access
throughout the Baylands without
transferring ownership or
environmental liability to the City.

Concerned about the City owning
much of anything out there; for
example, if there is a cap failure
and the City owns the road, the City
would be responsible in part for
addressing it. The City needs to
protect itself financially as much as
it possibly can.

Madison Davis Consistent with the intended approach. Staff recommends the Specific Plan require: (1) all streets, utilities, parks, and open space to remain privately owned and maintained; (2) recorded permanent public access easements, structured so public access is enforceable without the City taking on maintenance or liability; (3) maintenance funded by a master association assessment, with reserve requirements; (4) owner indemnity and insurance naming the City; and (5) City step-in rights to cure failures at the owner's cost, with no obligation to act.
12 Ensure that the City is not left
responsible for unfinished
infrastructure, deteriorating
property, environmental obligations,
or the cost of making the site safe
because a developer is unable or
unwilling to complete the project.

Madison Davis Should infrastructure stay private, the main risk shifts from City ownership to the owner or master association failing to build or maintain it. Tools include completion guarantees, performance bonds sized to the cost to complete or stabilize each phase, remediation financial assurance required by the oversight agencies, DA default remedies, and long-term maintenance security: recorded maintenance covenants, reserve study requirements. Staff recommends a stabilization standard for each phase (item 13). 13 Protect the City and the community
if the development is delayed,
suspended, abandoned, or
interrupted by developer
insolvency, bankruptcy, or change
in ownership. Every phase of the
development must be capable of
being safely maintained and
stabilized independently of
subsequent development.

Madison Davis Staff recommends requiring a stabilization plan for each phase showing that completed infrastructure, drainage, slopes, and remediation are stable and maintainable if no later phase proceeds, backed by security. Obligations should be recorded as covenants running with the land so they bind successor owners, and the DA should address assignment and change of ownership.

Page 8 of 15 ends

Baylands Council Follow-Up Matrix | Page 3 of 9
# Council Statement Councilmember Staff Response
14 Remove language from the specific
plan that implies public financing.

There will probably be public
financing, but it belongs in a
development agreement, not in the
specific plan.

Terry O'Connell Staff agrees financing terms belong in the DA and an Infrastructure Financing Plan. Staff will identify Specific Plan sections that reference public financing tools such as a CFD or Enhanced Infrastructure Financing District (EIFD) primarily in Chapter 8 of the Specific Plan and revise them to say financing will be set out in the DA and financing plan, subject to Council approval.
15 The City will not contribute to any
capital financing out of municipal
funds, whether general fund or
enterprise fund. Any money the City
has now would not be used for any
sort of financing; there would have
to be other options on that front.

Frank Kern Staff recommends defining "municipal funds" precisely. A policy that no existing or future General Fund or enterprise fund revenue pays for capital costs is workable. Council should clarify whether tools that do not use existing City revenue may be acceptable in connection with the DA. The policy should also carve out City affordable housing funds, since HE Program 2.A.2 commits the City to assist with funding for Baylands housing.
16 Hope the fiscal analysis does not
just address the City being fiscally
and revenue positive, but also
addresses how all the
infrastructure, remediation, and
related costs are funded and who is
required to pay for them.

Cliff Lentz Staff recommends requiring a companion Infrastructure Financing Plan listing each major infrastructure and remediation cost, the responsible party, the funding source, and timing, presented alongside the fiscal impact analysis. Because streets, utilities, and open space will stay private, the plan should also show long-term operation and maintenance costs and how future owners will pay them. Coordinate with items 14, 15, and 17.
17 The revenue-positive requirement
must be demonstrated through a
transparent, ongoing financial
framework, not projections, with a
consistent, clearly defined
methodology for calculating project-generated City revenues and expenses.

Madison Davis Staff recommends the DA require an adopted fiscal methodology, fiscal monitoring reports to Council at defined intervals, and a backstop if the project falls short. The methodology would be adopted before the first final map.
18 Coordinate with Caltrain and Union
Pacific Railroad about using the
railroad tracks in the evening to
transport dirt instead of a surface
street haul route.

Coleen Makin Staff can explore this with Caltrain and Union Pacific.

Considerations include track access agreements, loading facilities, scheduling around freight and passenger service, and cost. 19 Require a City Council-approved
truck haul route contained entirely
within the Baylands, including both
outbound and return travel, before
any soil relocation begins. The plan
should state that the Council-approved haul route stays entirely within the Baylands; the specifics
can be worked out in the future.

Madison Davis For on-site soil relocation, staff recommends a Specific Plan standard requiring a Council-approved haul route plan before any grading permit for soil relocation, with on-site movement (outbound and return) kept within the Baylands unless authorized by Council. 20 For the Geneva Avenue extension,
incorporate the Bi-County study into
the specific plan in a more robust
way.

Cliff Lentz Section 6.3.1 of the specific plan carries several General Plan programs into the plan. This includes consultation with Caltrans, MTC, the San Francisco County Transportation Authority, the San Mateo County Transportation Authority, C/CAG and others to develop and fund improvements that help US 101 carry regional through traffic, and for the City to develop design plans for the Geneva Avenue extension. The specific plan sets the right-of-way width, lane configuration, transit-only lanes for future bus rapid transit, bicycle and pedestrian facilities, and streetscape character for both the at-grade segments and the bridge over the Caltrain right-of-way. However, many details are left for a later design phase as the capital project is initiated. For example, the plan allows the median to support either center or side transit boarding “depending on future need,” and it requires the bridge to provide adequate vertical clearance under the Joint Powers Board’s electrification design criteria rather than fixing an exact height. Coordination with the partner agencies would happen mainly during that design and engineering phase. That is when connections, approvals, cost responsibilities, and construction sequencing get worked out. 21 Language that provides an
investment from the developer
toward Commute.org to mitigate the
Cliff Lentz The Specific Plan already mandates participation in Commute,org or a Transportation Management Association to provide a fare-free shuttle as part of the TDM plan. Language can be added to Table

Page 9 of 15 ends

Baylands Council Follow-Up Matrix | Page 4 of 9
# Council Statement Councilmember Staff Response
increased shuttle use the
development will create.

6.6.1 to specify that the contribution also cover increased demand for other shuttle services offered by Commute.org.
22 Strengthen the objective design
standards. The standards in the
specific plan do not go far enough;
would like to see something more
design-oriented rather than just
checking a box.

Cliff Lentz The standards may be strengthened, within limits. State law (Housing Accountability Act; SB 330) and HE Program 2.A.2, which commits to by-right approval without discretionary design review, allows only pre-defined, written, objective standards for Baylands housing. Design quality for residential and mixed-use residential development has to be written as measurable requirements.

Options include form-based frontage and massing standards, required articulation and materials menus, district-specific character standards, and an illustrated pattern book of objective requirements. Current state law does not impose the same requirements on commercial development, so there would be more flexibility for commercial design guidelines. Additional design standards and guidelines beyond those in the specific plan could be adopted as a companion objective design standards document. 23 Establish a strong, cohesive design
identity and meaningful City
oversight so the Baylands is
thoughtfully designed and built to a
consistently high standard over the
life of the project. The goal is to
avoid a collection of unrelated
projects built over many years and
instead create a cohesive, attractive
neighborhood with a consistent
standard of quality.

Madison Davis Tools include district-level design standards in the Specific Plan and companion standards as discussed in response to item 22, above. 24 Affordable housing should be
integrated throughout the districts.

Concentrating it in a small number
of large buildings or in isolated
areas is not right and is not
equitable; the goal is
neighborhoods where people of all
economic backgrounds live
together.

Madison Davis Feasible with tradeoffs. HE Programs 2.A.2 and 2.B.1 set a goal of 514 affordable units and require an affordable housing plan in the Specific Plan or DA, with sites for seniors, persons with disabilities, special needs, and lower-income households, and accessible units near transit. The HE also expects both 100% affordable and mixed-income buildings (HE Appendix C). Staff recommends the affordable housing plan spread affordable units across every district and phase in proportion to market-rate units, with comparable exterior design and equal amenity access. 100% affordable buildings would still be allowed, as long as no district concentrates them.
25 Include daycare facilities, using the
language that came from Build Up
San Mateo County.

Cliff Lentz Feasible. Staff will obtain the Build Up San Mateo County model language and recommend provisions for the DA (for example, a facility of set size per a number of units, or a phased in-lieu fee).

Childcare facilities can also qualify for a density bonus under Gov.

Code 65917.5.
26 Regarding energy neutrality, require
greater energy self-sufficiency than
the 53% currently proposed.

Cliff Lentz Staff will report on what raising the 53% target would take, including on-site solar and storage potential and cost. Options include a target that rises over build-out, or offsetting the gap through off-site renewable procurement (for example, through WestLight Energy). 27 Apply a site-specific greenhouse
gas evaluation rather than a
regional one, and incorporate the
Draft EIR recommendations for that
area.

Cliff Lentz Staff will clarify the EIR approach. The EIR evaluates GHG at the plan level, and later projects would be reviewed for consistency.

Staff recommends a Specific Plan standard requiring each development application to show compliance with the EIR GHG mitigation measures through a project-level GHG checklist, and further clarifying that the Mitigation Monitoring and Reporting Program measures must be implemented along with the plan's standards.
28 To promote workplace safety, the
specific plan should require the use
of appropriately skilled workers.

Cliff Lentz Staff recommends addressing this in the DA rather than the Specific Plan, through negotiated skilled and trained workforce or apprenticeship commitments.

Page 10 of 15 ends

Baylands Council Follow-Up Matrix | Page 5 of 9
Additional Items Received Since 11/19/26
# Council Statement Councilmember Staff Response
29 1. Remediation and Landfill
Closure (Before grading permits
and soil movement)
The developer shall submit and
comply with a City-approved,
enforceable, Remediation and
Landfill Closure Schedule
containing both completion
milestones and financial security.

No West-Side residential building
permits shall be issued for OU-SM
before the remediation of the
entirety of OU-SM is completed and
signed off by DTSC, the regulatory
agency.

No West-Side residential building
permits shall be issued for OU-2
before the remediation of the
entirety of OU-2 is completed and
signed off by RWQCB, the
regulatory agency.

Remediation of East-Side sites
designated for sustainability
facilities shall proceed concurrently
with West-Side remediation under
the approved schedule.

Coleen Makin Largely consistent with items 3 to 5. On 11/19/26, City Council provided direction to require remediation on the west side by OU.

The Specific Plan can be modified to include a requirement for an applicant to provide evidence of a remediation schedule with completion milestones and financial security to the satisfaction of DTSC and/or the Regional Water Quality Control Board, as applicable. Concurrent East-Side remediation for sustainability facilities is feasible as a schedule milestone.
30 2. Water Supply, Grading, and
Soil Transfer (Before grading
permits and soil movement)
No permits for grading or soil
transfer shall be authorized until the
City Council approves a secure and
reliable long-term water supply that
has been established consistent
with Measure JJ.

The developer shall be required to
submit with permit applications a
Construction Water Management
Plan addressing: water sources,
nonpotable water use where
feasible, drought restrictions, and
dust control.

The Plan must be approved by the
City before any applications for
permits will be considered.

Coleen Makin On 11/19/26, City Council provided direction to address the water supply requirement in stages. First, the Specific Plan shall require applicants to demonstrate evidence of adequate water supply for construction activities prior to issuance of any grading permit or approval of site disturbing activities. Second, the Specific Plan shall require applicants to demonstrate a reliable long-term water supply for development before to the City’s satisfaction prior to the issuance of the first building permit.

A requirement for a Construction Water Management Plan
addressing water sources, nonpotable use, drought restrictions, and dust control is feasible to add to the Specific Plan.
31 3. Construction Impacts and Soil
Hauling (Before grading permits
and soil movement)
Prior to grading or soil movement,
the developer shall obtain City
approval of a Construction Soil
Management Plan.

The plan shall establish haul routes,
dust and noise controls, monitoring
and inspection, and surety
requirements.

Any construction-related soil-hauling trucks shall not use the Tunnel Avenue Bridge.

Unpaved haul routes shall be paved
or otherwise controlled to standards
approved by the City.

Coleen Makin Consistent with item 19. Adding a requirement for a City-approved Construction Soil Management Plan covering haul routes, dust and noise controls, monitoring and inspection, and surety to the Specific Plan is feasible and could be required before any grading or soil movement. Paving or otherwise controlling unpaved haul routes is consistent with the EIR air quality mitigation for construction dust. A prohibition on soil-hauling trucks using the Tunnel Avenue Bridge may not be feasible as a standard, as alternative routes are limited.

Page 11 of 15 ends

Baylands Council Follow-Up Matrix | Page 6 of 9
# Council Statement Councilmember Staff Response
32 4. Grading and Protection of
Existing Properties (Before
grading permits and soil
movement)
Prior to grading permit approval, the
developer shall submit a Grading
Plan that includes illustrative cross-sections.

The plan must include protective
measures in proposed grading that
protect existing properties from:
flooding, adverse elevation
changes, and loss of business,
utility, delivery, or emergency
access.

Planning Commission review and a
public hearing shall be required
pursuant to reinstated Municipal
Code Section 17.32.220.

Coleen Makin Adding a requirement for a Grading Plan with illustrative cross-sections and measures to protect existing properties from flooding, adverse elevation changes, and loss of access to the Specific Plan is feasible and is consistent with items 13 and 33. The requirement for Planning Commission review and a public hearing would require an amendment to reinstate Municipal Code Section 17.32.220.

Because grading permits are normally ministerial, adding a discretionary hearing for grading that serves housing could conflict with the by-right commitment in HE Program 2.A.2 and state limits on hearings for housing projects (SB 330). Staff recommends objective protection standards with staff review and public notice, or limiting a hearing to mass grading that is not part of a housing development approval.
33 5. Comprehensive Basin
Drainage System, Including
Visitacion Creek (Before soil
transfer or grading permits, or
submission of Tentative
Subdivision Map)
Prior to grading or soil transfer, the
developer shall obtain City approval
of a Comprehensive Basin-Wide
Drainage and Flood Protection
Analysis and Plan addressing the
entire Baylands, noting existing
developed properties, and
Visitacion Creek.

The plan shall identify permanent
improvements required at each
phase of grading, soil transfer, or
construction, to ensure long-term
safe and functional drainage if
development is delayed or
discontinued.

Coleen Makin A Comprehensive Basin-Wide Drainage and Flood Protection Analysis and Plan for the entire Baylands, including existing developed properties and Visitacion Creek, could be required before the first grading or soil transfer permit. The requirement that each phase include permanent improvements so drainage functions if development is delayed or discontinued is consistent with the phase stabilization approach in item 13. The plan should be coordinated with the EIR hydrology and sea level rise analysis. 34 6. One Coordinated Tentative
Subdivision Map and Grading
Plan (Before soil transfer or
grading permits, or submission
of Tentative Subdivision Map)
A Tentative Subdivision Map must
be submitted in conjunction with the
application for a grading permit.

The map must first illustrate existing
conditions: topography, elevations,
drainage, roads, structures, and
utilities. It must also indicate areas
of constraints: contamination, flood
hazards, wetlands, and other
limitations on development.

The Tentative map shall include the
proposed subdivision boundaries,
grading and elevations, streets and
access, utilities, drainage, and the
relationship of the proposed
improvements to the adjoining
properties.

Coleen Makin Feasible with refinement. The City may require a tentative map showing existing conditions, constraints, proposed lots, grading, streets, utilities, and drainage, and its relationship to adjoining properties in connection with maps that precede development.

Because remediation grading must proceed under DTSC and Regional Water Board oversight and individual parcels will be mapped over many years, staff recommends requiring a master (large-lot) tentative map and coordinated grading plan before the first mass grading permit for development, with remediation activities required by the regulatory agencies excepted. Later subdivision maps for individual phases would be consistent with the master map.
35 7. Circulation and Emergency
Access (Before soil transfer or
grading permits, or submission
of Tentative Subdivision Map)
Coleen Makin A Circulation and Emergency Access Phasing Plan could be required before the first grading permit, prepared in coordination with the North County Fire Authority and the Police Department.

The plan would maintain emergency access and minimize

Page 12 of 15 ends

Baylands Council Follow-Up Matrix | Page 7 of 9
# Council Statement Councilmember Staff Response
A Circulation and Emergency
Access Phasing Plan must be
submitted and approved prior to
issuance of a grading permit.

The plan shall minimize disruption
to existing businesses and maintain
appropriate emergency access at
every stage of development.
disruption to existing businesses at each stage, and would be coordinated with the fire station timing in FEIR Appendix N.2 and the Geneva Avenue milestones discussed in item 7.
36 8. Infrastructure Phasing and
Completion (Before building
permits for each phase or
increment)
The developer shall obtain City
approval of a Master Infrastructure
and Phasing Plan identifying
required improvements and
completion milestones for each
phase.

Each phase shall incorporate
infrastructure necessary to function
independently.

The plan shall include provisions to
protect the City and existing
properties if development is
suspended or terminated.

Coleen Makin Consistent with items 6, 12, and 13. Staff recommends that a Master Infrastructure and Phasing Plan be required in connection with the first Tentative Subdivision Map as the vehicle for the phasing table of objective triggers in item 6, with each phase required to include the infrastructure needed to function independently and a stabilization plan protecting the City and existing properties if development is suspended or terminated. 37 9. Police, Fire, and Other Public
Facilities (Before building
permits for each phase or
increment)
The developer shall fund the
necessary interim public services
and/or facilities to ensure public
safety until sufficient Baylands
public financing is available.

Coleen Makin Feasible through the DA. The FEIR police and fire plans conceive of a police substation that would open before the first certificate of occupancy and the relocated fire station to be operational before construction of any building 75 feet or taller (FEIR Appendices N.1 and N.2), but they do not identify a funding source. Developer funding of interim services and facilities could be required in connection with the DA until permanent funding is in place. Given item 41 and the direction that infrastructure remain private, staff recommends that the DA identify the permanent funding source for public safety facilities and staffing, and that the interim funding obligation be tied to those timing requirements.
38 10. Wastewater Treatment
Facility Location and Odors
(Before building permits for each
phase or increment)
Before approval of the Wastewater
Treatment Facility, the City shall
review and approve its location,
design, odor-control systems, and
operating standards.

The facility shall incorporate
stringent odor prevention and
control measures, monitoring,
complaint-response procedures,
and City inspection rights.

Coleen Makin There is no wastewater treatment facility proposed. Mitigation Measure AQ-3a requires the applicant to prepare Recycled Water Plant Odor Management Plan for review and comment by the Air District prior to review and approval by the City prior to issuance of permits for the facility. The Specific Plan and specify that the Plan include odor prevention and control, monitoring, complaint-response procedures, and City inspection rights. 39 11. Selected Alternative (Before
building permits for each phase
or increment)
The final alternative selected by the
Council shall be the development
alternative authorized under this
Specific Plan.

All land-use tables, development
standards, building heights,
drawings, and subsequent plans
shall be revised by amendment as
necessary.

Coleen Makin Consistent with the discussion of FEIR alternatives in the staff memo. The Council may select an alternative, or elements of one, analyzed in the FEIR, however depending on which alternative is chosen, it may impact the schedule for taking action on the plan.

Staff recommends that the Council make that selection before adoption so the adopted Specific Plan reflects it, rather than adopting the plan and revising it later by amendment. Depending on the alternative selected, revisions to land use tables, development standards, height limits, the development program, and the financial analysis could affect the schedule, may need Planning Commission review, and would need to be checked against HE Program 2.A.2. 40 12. Independent Engineering,
Geotechnical, Structural,
Coleen Makin Feasible and consistent with common practice. The City can retain independent consultants to review developer-submitted plans and

Page 13 of 15 ends

Baylands Council Follow-Up Matrix | Page 8 of 9
# Council Statement Councilmember Staff Response
Environmental, and Legal Review
(Independent engineering and
enforcement)
The City retains the right to hire
consultants to evaluate developer
submitted plans and technical
studies. In hiring said consultants,
the City shall establish the scope of
work or methodology to be
employed and consultant fees for
said work shall be at developer's
expense.

The developer shall provide access
to supporting data, testing, and
inspections, and shall correct
identified deficiencies before
applicable permit approvals.
technical studies, with the City setting the scope and the developer paying the cost under a cost recovery agreement. Fees must reflect the reasonable cost of the review. Review of housing projects must still be based on objective standards and occur within state permit processing timelines. Requiring access to supporting data, testing, and inspections, and correction of deficiencies before permit approval, is feasible.
41 13. Public Financing and Fiscal
Protection (Financial protection
and developer accountability)
Approval of this Specific Plan shall
not authorize any CFD (Community
Facilities Districts), EIFD
(Enhanced Infrastructure Financing
District), HOA (Homeowners
Association), POA (Property
Owners Association), public
reimbursement, or any other public
financing arrangement unless in the
City Council's sole discretion,
approval is granted.

Coleen Makin Consistent with items 14 and 15, which recommend that financing terms be set in the DA and an Infrastructure Financing Plan subject to Council approval. Staff recommends the Specific Plan state that no CFD, EIFD, public reimbursement, or other public financing is authorized without Council approval. However, homeowners and property owners associations are private entities rather than public financing, and a funded master association is the recommended mechanism for maintaining private streets, utilities, and open space under items 8 and 11. Staff recommends treating associations separately: requiring them, and requiring City review of their governing documents to confirm maintenance obligations and funding, rather than making their formation subject to Council discretion.
42 14. Developer and Successor-Builder Responsibility (Financial protection and developer
accountability)
The Master Developer shall retain
responsibility for required
remediation, backbone
infrastructure, sustainability
facilities, and other project
obligations following any parcel
transfer unless the City expressly
approves an assignment and
equivalent replacement security.

Such obligations shall be
established in recorded agreements
enforceable by the City.

Coleen Makin Consistent with item 13. Staff recommends the DA and recorded agreements require that the Master Developer remain responsible for remediation, backbone infrastructure, sustainability facilities, and other obligations after parcel transfers unless the City approves an assignment to a qualified successor with equivalent replacement security. Recording these obligations as covenants running with the land makes them enforceable against successor owners.
43 15. Developer Financial Capacity
and Security (Financial
protection and developer
accountability)
Prior to submittal of the Grading
permit application and Tentative
Subdivision Map, and each
subsequent permit approval
thereafter, the developer shall
demonstrate adequate financial
capacity and committed funding
necessary to complete required
remediation, infrastructure, and all
other Specific Plan improvements.

The developer shall be required to
provide sufficient financial security,
including irrevocable, automatically
renewable standby letters of credit
Coleen Makin Feasible with refinement. Financial security in the form of irrevocable, automatically renewable standby letters of credit or cash deposits is consistent with item 12, and the City may specify acceptable forms of improvement security. Requiring a
demonstration of committed funding for all Specific Plan improvements before the first grading permit and each later permit may not be achievable for a build-out of 15 years or more and could be viewed as a constraint on housing. Staff recommends a phase-based approach: before each phase, the developer demonstrates financial capacity for that phase and posts security sized to complete or stabilize the work underway, with security for remediation and backbone infrastructure set in the DA.

Page 14 of 15 ends

Baylands Council Follow-Up Matrix | Page 9 of 9
# Council Statement Councilmember Staff Response
or cash deposits, in amounts
approved by the City.

Page 15 of 15 ends