ID # Description Estimated Cost Responsibility Category Comments 1 Site Work $18,000.00 Tenant Cosmetic Planting/Irggigation & Resurface the Basketball Court
2 Hazardous Material Abatement $38,000.00 Operator Required Asbestos, lead and other typical hazardous
material were found on the property and
will require abatement
3 Structural Retrofit $115,000.00 Operator Required
Wall Anchorage and Section 7-150 of the
City of Burbank Building Code for
Earthquake Hazard Reduction
4 Roofing & Waterproofing $83,875.00 Operator Required Roof needs to be replaced 5 Energy Modernizations $83,000.00 Operator Required Insulation and New Windows to comply with Building Code and Energy Code
6 Cabinetry and other casework $75,000.00 Tenant Cosmetic Kitchen Cabinets, Bathroom Cabinets,
Kitchen Countertops and Bathroom
Countertops need to be upgraded and ADA
compatible
7 Finishes and Textures $50,000.00 Tenant Cosmetic Replace existing drywall, replace all flooring, new kitchen equipment
8 Interior and Exterior Paint $60,000.00 Tenant Cosmetic Interior and exterior walls currently have
lead based paint, both will have to be
mitigated and painted
9 Fire life safety systems $125,000.00 Operator Required Install Fire Sprinkler Systems 10 Mechanical $135,000.00 Operator Required Existing equipment needs to be replaced to meet current code and energy requirements
11 Electrical and Low Volt $175,000.00 Operator Required New 200 amp Sub Panel is required, LED Lighting, Cat6e cable throughout building
12 Plumbing $115,000.00 Operator Required
Entire plumbing system needs to be
replaced, new water heater, gas system and
earthquake requirements will need to be
upgraded
13 ADA Compliance $125,000.00 Operator Required
ADA code changes and compliance is
mandatory, the last ADA improvement
occurred over 20 years ago
14 Exterior $25,000.00 Tenant Cosmetic Minor gutter, plaster and downspout repairs 15 Temp Facility Removal $125,000.00 Tenant Required
Remove temporary trailers from the
premises as they are not up the code and
the cost to do that would outweigh the
benefit
Estimated Construction Cost $1,347,875.00 NA The Construction Costs are including prevailing wage
Contingency @ 15% $202,181.25 Required
We are including prevailing wage to capture
unforseen conditions during construction as
well as energy code upgrades
Total Estiamted Construction Cost $1,550,056.25
Construction Drawings $200,000.00 Required
The scope of work requires construction
drawings to be submitted for a building
permit, this cost would include hiring an
architect
Total Estimated Project Cost $1,750,056.25