BID SUMMARY:

Attachment #3

The table below lists the names of the qualified bidders and their bid amounts:

BIDDER TOTAL SUM BID BID DEPOSIT
M.C.E.C. $1,083,000.00 10%
Modern Construction Management, Inc.
dba MCM Construction, Inc.
$1,380,093.16
Corrected Total 10%
SBS Corporation $1,387,448.00
Corrected Total 10%
Modern General Contractor, Inc. Non-Responsive
Loengreen, Inc. Non-Responsive
ACRO Development, Inc. dba ACRO
Constructors Non-Responsive
JT Construction Group, Inc. Non-Responsive

As shown in the table above, MCEC Inc. submitted the lowest responsive bid.