ATTACHMENT 1
1 RESOLUTION NO. ____________
A RESOLUTION OF THE COUNCIL OF THE CITY OF
BURBANK AUTHORIZING THE CITY MANAGER TO
EXECUTE A DESIGN -BUILD CONTRACT WITH MUSCO
SPORTS LIGHTING, LLC. (CONTRACTOR) AND
DELEGATING AUTHORITY TO APPROVE PLANS AND
SPECIFICATIONS FOR EQUIPMENT TO UPGRADE THE
EXISTING 1500 -WATT METAL -HALIDE BALLFIELD
LIGHTING AT MCCAMBRIDGE PARK TO LIGHT -
EMITTING DIODE (LED) TECHNOLOGY.
THE COUNCIL OF THE CITY OF BURBANK FINDS:
A. Section 1205 of the Burbank City Charter and Burbank Municipal Code section 2-2- 111 provide that the City Council may waive formal competitive bidding by resolution and approve alternate project delivery methods such as a “cooperative agreement” to the award public works construction projects when it is in the best interests of the City.
B. The cooperative agreement delivery method allows the City to utilize another public agency’s bid, which includes language that the public agency is bidding on behalf of the member of the Cooperative, nationwide. This reduces the cost of goods and services by aggregating the purchasing power of public agencies nationwide, thus eliminating much of the time needed for a bid solicitation process and thereby streamlining the project timeline.
C. The cooperative agreement delivery method is an acceptable and preferable method of procurement for ballfield lighting equipment and installation, as each manufacturer provides proprietary equipment . M usco has the only monitoring service of its kind.
Musco’s Control-Link® delivers a sports lighting system that is managed w ith 24/7 support from a fully-staffed Musco team. Control-Link makes scheduling, controlling, and monitoring from a mobile phone or desktop computer accessible.
D. The ballfield lighting systems at McCambridge Park need replacement s to enhance lighting features and improve energy efficiency . As a result, the City’s Parks and Recreation Department (“Department”) , solicited a proposal under a cooperative purchase agreement to select a firm to perform the replacement of the existing ballfield lighting systems at McCambridge Park (“Project”).
E. The design-build project method has gained favor in the construction industry because it facilitates the coordination of civil, structural, and electrical engineering in all phases of project design and c onstruction, minimizes change orders through early collaboration between design and construction disciplines, and reallocates design liability, project management, and other risks from the City to the selected contractor.
ATTACHMENT 1
2 F. As a result, the Department desires to utilize the design-build project delivery method to complete the Project. The design-build method is both appropriate for this Project and in the best interests of the City due to the benefits outlined above. In furtherance of the Project, the Department, in conjunction with the Purchasing Manager, solicited a proposal from a design-build firm under an existing cooperative purchase agreement to complete the Project. A proposal was received by MUSCO Sports Lighting, LLC, and independently evaluated by City staff pursuant to the City’s normal competitive purchasing procedures.
THE COUNCIL OF THE CITY OF BURBANK RESOLVES:
1. Pursuant to Burbank Municipal Code section 2-2-116(I) and (J), the City Council hereby approves performing the Project using the cooperative agreement method of project delivery. Accordingly, the City Council hereby waives the traditional competitive bidding process as outlined in Burbank Municipal Code § 2-2-116 as it is determined that the cooperative agreement delivery method accompanied by a competitive proposal solicitation process is in the best interests of the City.
2. The design- build contract between the City and MUSCO Sports Lighting, LLC (“Contract”), for the design and construction of replacement ballfield lighting at McCambridge, on file at the City Council Office and the Purchasing Division are approved with such modifications as may be deemed appropriate by the City Manager or his designee.
3. The City Council hereby delegates authority to the Parks and Recreation Director, or her designee, to review, and in her discretion, to approve, the final Project plans and specifications prior to the issuance of a building permit.
4. This Project is categorically exempt from the California Environmental Quality Act (CEQA), pursuant to Section 15302 of the State CEQA Guidelines pertaining to replacement or reconstruction of exist ing structures and facilities, because the new ballfield lighting systems will be located on the same sites as existing ballfield lighting systems and will have substantially the same recreational purpose and capacity as the existing equipment.
5. The current total construction budget of the Project is estimated to be $735,331.50, but may be adjusted by the City Manager or his designee up to the total budgeted amount for the Project.
6. The City Manager or his designee is authorized to execute an agreement with MUSCO Sports Lighting, LLC for the replacement of the existing ballfield lighting systems at McCambridge Park, and the City Clerk is authorized to attest.
ATTACHMENT 1
3 7. The Cooperative Agreement shall be retained as a permanent record.
PASSED and ADOPTED this __ day of June, 2023.
_________________________
Konstantine Anthony
Mayor
Approved as to Form:
Attest: Office of the City Attorney
____________________________ By: _______________________ Kimberley Clark, City Clerk Jill Vander Borght Senior Assistant City Attorney
STATE OF CALIFORNIA )
COUNTY OF LOS ANGELES ) ss
CITY OF BURBANK )
I, Kimberley Clark, City Clerk of the City of Burbank, do hereby certify that the foregoing Resolution was duly and regularly passed and adopted by a vote of the Council of the City of Burbank at its regular meeting held on the __ day of June, 2023, by the following vote:
AYES:
NOES:
ABSENT:
______________________________