ATTACHMENT 1
https://cityofburbank-my.sharepoint.com/personal/acasillas_burbankca_gov/Documents/Desktop/10.03 CC MTG - Doty Bros. Change Order/Attachment 1 - Change & Extra Work Order #1.docx - A1-1 - (over) City of Burbank
Water and Power Department

CHANGE AND EXTRA WORK ORDER
Order No. 1
P. O. No.

Bid Schedule No. 1498
Date 10/3/2023
Project: Construct Distribution Underground Conduit System & Related Substructure Improvements - Citywide

The following change is hereby made a part of the Contract Documents enumerated in the Agreement Between City and Contractor dated _____April 12, 2021__________ and shall be performed under the same terms and conditions as required by the original Contract Documents. Except as modified herein, the original Contract Documents and all prior amendments shall remain in full force and effect and all of the terms of the Contract Documents are hereby incorporated in this Change Order.

Item Number Detailed description of work to be performed, with quantities In accordance with the applicable provisions of the specification as follows:

UNIT PRICE METHOD
Item Number Description Qty Unit Price Extension

COST PLUS PERCENTAGE METHOD FOR WORK PERFORMED BY CONTRACTOR:

Item Number Description and quantity at actual cost to Contractor Price

1. Materials

2. Direct Labor

3. Plant and Equipment Rental

4. Installation, Maintenance, Operation,
and Dismantling of Plant Equipment

Sub-Total
Add 15% of
Sub-Total
Total per this
method

EXTRA WORK PERFORMED OTHER THAN BY CONTRACTOR’S FORCES:

Item Number Description and quantity at actual cost to Contractor Price

1. Materials

2. Direct Labor

3. Plant and Equipment Rental

4. Installation, Maintenance, Operation,
and Dismantling of Plant Equipment

OTHER METHOD:

Sub-Total
Add % per
Contract
Total per this
method

Item Number Description Price
1 Additional bid items as described in BS1498 at the current unit prices. $ 2,500,000.00

The total price of the above requested changes and/or extra work is $ 2,500,000.00

For this request the date of Substantial Completion will increase/decrease by 0 day(s)

It is understood and agreed that any adjustment of the Contract Price associated with this Change Order includes compensation to the Contractor for all direct costs, indirect costs and expenses it has incurred or may incur in connection with the change in the Contractor’s Work, including but not limited to all costs, expenses and damages for any delay, disruption, acceleration, interference or hindrance and like costs associated with, resulting from, or incidental to the Change Order Work. Contractor hereby agrees that payments under this Change Order and extension of the Contract Time, if any, represent full satisfaction and final settlement of all such costs, expenses delays and damages set forth in the preceding sentence and Contractor waives and releases all claims for any and all additional costs or delays in the Contract Time.

Contractor/Design-Builder’s By Title
ATTACHMENT 1
https://cityofburbank-my.sharepoint.com/personal/acasillas_burbankca_gov/Documents/Desktop/10.03 CC MTG - Doty Bros. Change Order/Attachment 1 - Change & Extra Work Order #1.docx - A1-2 - (over)

DEPARTMENT APPROVAL

The work referred to hereinbefore is hereby approved for authorization by the City Manager, as follows:

Item Number Classification Additions to Contract Price

Alterations in Contract Work

Additions to contract work

Substitutions in contract work

Alterations in contract work

Substitutions in contract work

Deductions from contract work

$

$ 2,500,000.00

$

Deductions from Contract Price

$

$

$

Original Contract Price

Original Completion Date

Total of Orders
Authorized to Date

Total of this Order

Revised Contract Price

The date of Substantial Completion as of this Change Order is:

$ 1,000,000.00

April 11, 2023
Date of Completion

$ 0

$ 2,500,000.00

$ 3,500,000.00

N/A
New Date of Completion
I have confirmed with the Finance Division and therefore certify that the foregoing additional compensation is within the budgetary appropriation for this public improvement.

_______________________ ___________________________________ Date Dawn Roth Lindell, General Manager, BWP

CITY ATTORNEY'S APPROVAL

Approved as to form

By___________________________________

Date

Distribution:

Original – City Clerk (via Purchasing); Copies (4) – Contractor, Purchasing Department, Financial Management Department, Awarding Department.