Update on the New
Burbank Central Library
and Civic Center Project
City Council Study Session
November 19, 2024
PUBLIC
WORKS
• Library built in 1963
• Identified for renovation/replacement in 1989
• Planned Development and Measure L in 2003 for
Library, CSB, ASB (1966 bank) plus open space.
• New CSB completed 2008. PD expired 2018.
• ASB – Finance and MS staff move in 2001.
• Seismic upgrade and interior
improvements 2014.
• Library – carpet/paint 1992, electrical; IT
and other required updates.

Background
2 • 2021: Vision Study for a New Central Library
o Pursue new construction, not renovation
o Upper CSB parking lot is desired site
o Determine financially feasible path forward
• Late 2022: 1,600 survey responses, three
community meetings, CCB presentations,
project website created
History
3 • 2023 – March 2024:
o Steering Committee Formed
o Alternatives Analysis
o Housing Opportunity Sites Evaluations
o Financial Models
o Cost Estimates
o Procurement/Delivery Strategies
o Geotechnical/Phase I Report
History
4 • Build a modern Central Library for the community
• Create new open space for events and use by
downtown residents & others
• Encourage development of mixed-use and
mixed income housing on opportunity sites
• Demonstrate leadership in sustainability
• Support downtown economic
development
Project Goals
5 Conceptual site plan
6 Public-Private Partnership P3
Housing Construction Challenges:
• Rising construction costs due to inflation
• Increased borrowing costs due to higher interest rates • Higher operating costs per housing unit
• Rents not able to keep up with costs
 P3 no longer attractive to the industry without the
private construction elements and associated long-
term revenue
Potential Delivery Method
7 • Design/Build
o City contracts with a single design/build entity
o Risk transfer of design and construction services
o Provides collaborative evaluation of
construction and long-term costs vs budget
o Operations and maintenance needs and
impacts considered in design
o Early and continuous input from the
community, stakeholders and staff
Potential Delivery Method
8 • Long-term revenue potential from housing
opportunity sites on City-owned parcels remains
• More flexibility in City/developer timelines for
housing
• Design/construction costs for civic assets only
• Reduces timeline to facilitate meeting grant
expenditure requirements
“Unbundling” Housing
9 ASB Site Demolition $1,000,000
New Central Library $65,000,000
City Offices (ASB Departments) $15,000,000
Subterranean Parking $28,000,000
Plaza/Open Space $18,000,000
______________________________________________________________________________________________ Current Estimate $127,000,000
2027 Estimate with 5%/Year Escalation : $147,000,000
O&M and Capital Costs
• Library: $1.5M/year; $5M in 5 years
• ASB: $1.2M/year; $2M in 5 years
Estimated Cost
10 • Project Management RFP (award Spring 2025)
• Downtown Burbank TOD SP and EIR (Summer 2025)
• Design/Builder RFQ/RFP process in FY25-26
(award Summer 2026)
Next Steps
11 Q&A