Attachment 5
Olive Avenue Roadway configuration – Metro versus Staff Recommendation (First Street to Third Street) Top: M
etro curb-running bus lane between First Street and just east of San Fernando Boulevard Bottom: Staff Mixed Flow lanes transition to curb-running bus lane east of San Fernando to accommodate station curb extensions ATTACHMENT 5 -1
Ol
ive Avenue Roadway configuration – Metro versus Staff Recommendation (San Fernando and Olive intersection) Top: M
etro curb-running bus lane between First Street and just east of San Fernando Boulevard Bottom: Staff Mixed Flow lanes transition to curb-running bus lane east of San Fernando to accommodate station curb extensions ATTACHMENT 5 -2
Attachment 5
Burbank City Council
April 22, 2025