Golden State
Substation Rebuild
City Council Meeting
June 3, 2025
BWP Substations
Station Equipment Damage
Damaged Electrical
Equipment Building
Location of Damaged
Transformer
Demolition
Original Electrical
Equipment Building
Construction
Installation of Underground
Electrical Conduit
Construction Cont’d
Electrical Equipment
Building Foundation
Transformer
Firewall
Construction Cont’d
Electrical
Equipment Building
Construction Cont’d
Transformers
Construction Completed
Project
Schedule
and Cost
Station Energized in December 2024f
Budget: $17.1M
Actual Cost: $17.0M
Insurance Reimbursement
Summary
Enhanced Personnel Safety
Increased Capacity
Improved Operational Flexibility and Visibility
BWP’s Cost: About 25% of today’s cost