Cities Index.
City_Council_Agenda_02-16-2022_Item_No._10

Calexico City Council
February 16, 2022

Document
City_Council_Agenda_02-16-2022_Item_No._10
Meeting
February 16, 2022
Body
Calexico City Council
Original file
95 KB
Text extracted from the city's file for reading and search. Open the original on www.calexico.ca.gov. That file is the official record.

AGENDA
ITEM
10 AGENDA STAFF REPORT
DATE: February 16, 2022
TO: Mayor and City Counci l
APPROVED BY: Miguel Figueroa, City Manager
PREPARED BY:

SUBJECT:

Lilliana Falomir, Public Works Manager - Adm tr ~
Authorize City Manager to File Notice of Completion for Sewer Main Replacement Project on Designated Streets.
------------------------------------------------------------------ ------------------------------------------------------------------ Recommendation:

Authorize City Manager to File Notice of Completion for Sewer Main Replacement Project on Designated Streets.

Background:

On March 2, 2020, the City of Calexico Public Works Department requested bids for Sewer Main Replacement Project. The project will consist of replacing the existing 8-inch and 4-inch gravity pipelines, installing and connecting each existing sewer service laterals along the new pipeline alignment. The locations of the sewer main replacement are:
• Paulin Avenue between 7th Street to 10th Street
• Dool Avenue between 5th Street and 7th Street
• Beach Avenue between 5th Street to 7th Street
On May 20, 2020, the City Council of the City of Calexico awarded a construction agreement with A&R Construction in the amount of $1,058,239.16 for Sewer Main Replacement Project on designated streets. Notice to proceed was issued July 15, 2021 .

Due to additional work that was not anticipated during the design phase of said project, the total construction amount of said project is $1 ,225,422.30.

Discussion & Analysis:

On January 20, 2022, A&R Construction completed the Sewer Main Replacement Project, therefore Public Works staff is recommending that the City Council of the City of Calexico authorize the City Manager to file Notice of Completion for said project.

AGENDA
ITEM
10 Fiscal Impact:

Capital Improvement Program Budgeted Item for FY 2021-2022 Wastewater Enterprise Fund $1,225,422.30
I Total $1 ,225,422.30 I
Coordinated With:

Public Works Department.

Attachment(s):

1. Notice of Completion.

RECORDING REQUESTED BY:

City of Calexico
AND WHEN RECORDED MAIL TO:

City of Calexico
Public Works Depmtment
608 Heber Avenue
Calexico, California 92231

SPACE ABOVE THIS LINE FOR RECORDER'S USE

NOTICE OF COMPLETION
Notice pursuant to Civil Code Section 3093, must be fil ed within 10 days after completion.

Notice is hereby given that:

1. The undersigned is owner or corporate officer of the owner of the interest or estate stated below in the prope1ty hereinafter described:

2. Thefullnameoftheowneris ____ _ C_ify exi_c_o _ ________________ _

3. The full address of the owner is 608 Heber Avenue, Calexico, California 92231

4. The nature of the interest or estate of the owner is:

In fee

5. The full names and full addresses of all persons, if any, who hold title with the undersigned as joint tenants or as tenants in common are

NAMES ADDRESSES
None

6. The full names and full addresses of the predecessors in interest of the undersigned, ifthe property was transferred subsequent to the commencement of the work or improvements herein referred to

NAMES ADDRESSES
None

7. A work of improvement on the propeity hereinafter described was completed on 01/20/2022. The work done was The project consisted of replacing the existing 8-inch and 4-inch gravify pipelines, installing and connecting each existing sewer service laterals along the new pipeline alignment.

8. The name of the contractor, if any, for such work of improvement was A&R Construction, 1631 River Drive, Brawley, CA 92227 05/20/2020
(Date of Contract)

9. The prope1ty on which said work of improvement was completed is in the City of_C_a_le_x_ic_o _____ _ County of Imperial , State of California , and is described as follows:

Sewer Main Replacement on Designated Streets

10. The street address of said prope11y is Paulin A venue between 7th Street to 10th Street, Dool A venue between 5th Street and 7th Street and Beach A venue between 5th Street to 7th Street Dated 02/16/2022
Miguel Figueroa, City Manager
City of Calexico

VERIFICATION
I, the undersigned, say: I am the Cify Manager, the declarant of the foregoing Notice of Completion; I have read said Notice of Completion and know the contents thereof; the same is true to my own knowledge. I declare under penalty of pe1jury that the foregoing is true and correct.

Executed on February 16, 2022, at Calexico, California
Miguel Figueroa, City Manager
City of Calexico

← All documents from this meeting