AGENDA
ITEM
11 CITY COUNCIL

AGENDA STAFF REPORT

CALEXICO
Ms Caleven God Henne Ma
DATE: August 17, 2022
Mayor and City Council
PREPARED BY: Diego Favila, Fire Chief
SUBJECT: Authorize City Manager to Sign Change Order #6 for Oakview Constructors, Inc., for the New Fire Station Headquarters Project Recommendation:

Authorize City Manager to sign Change Order #6 in the amount of $72,352.00 from Oakview Constructors, Inc. to include additional construction materials and labor, and associated costs as described in each change order document for the new Fire Station Headquarters.

Background:

On March 12, 2020, the City Fire Department requested bids for the Calexico Fire Headquarters Station Replacement Project.

The project consists of:

Demolition of the existing two-story fire station #1 building will involve the separation of the building and building systems (structural, mechanical, electrical, plumbing and communications) from the existing police station, which is to remain in place. The contractor will salvage select items from the existing fire station prior to demolition and deliver these items to the City. All existing items to remain in place must be protected.

The existing ground mounted and guyed communication tower will be replaced with a new 90 feet high, ground mounted and freestanding AGENDA communication tower. ITEM
The new fire station will be on story and approximately 9,000 SF. The new station has three drive through apparatus bays with suppression support spaces, which include a turnout room with clean-up area, workshop, restroom, hose storage, air compressor room and mechanical support spaces. The firefighter living quarters include eight firefighter bunk rooms, four gender neutral restrooms, laundry, dayroom, dining, kitchen, and fitness room.

The apparatus bays are designed to be cooling center for the City during high temperature days.

The site improvements include a new concrete driveway approaches, front concrete apron, rear concrete apron, decorative metal fencing with pedestrian and automatic sliding gates and keypads. New paving area in between the new fire station and existing police station. Renovation of an existing ADA parking area and new gravel area for the horizontal hose drying rack. A new emergency generator with skid mounted fuel tank is included, an outside patio with BBQ area, and on-site parking for fire personnel. The project includes new and existing plantings and landscape areas, irrigation, and bio retention areas.

On June 3, 2020, the City Council approved Oakview Constructors, Inc. as the lowest responsible bidder for the new Calexico Fire Headquarters Station Replacement Project. The City Council authorized the City Manager to sign a Construction Agreement with Oakview Constructors and Award the bid proposal from Oakview Constructors in the amount of $5,827,400.

Discussion & Analysis:

Change Order #6 includes the following for a total sum of $72,352.00:
• PCO 44R3 Police Department Roofing Replacement
The approval of the additional costs and construction work with inclusion of this change order will increase the contract sum of $6,098,043.40 (original sum + previous change orders) to $6,170,395.40.

Fiscal Impact:

The Calexico Fire HQ Station total construction budget is $6,784, 144. The bid award to Oakview was a total of $5,827,400, which resulted in a savings of $956,744.

The Calexico Fire HQ Station project has a separate construction contingency budget of $542,732.
• To date, the City has issued Change Order #1 for $77,308 and Change Order #2 tor $63,630.
• With Change Orders #1 and #2, the project used $140,938 out of the total construction contingency budget.
• With Change Order #3, the project used $75,346.40 out of the total construction contingency budget.
• With Change Order #4, the project used $60,001.00 out of the total construction contingency budget.
• With Change Order #5, the project received a credit of -$5,642.00 out of the total construction contingency budget.

Please note that the previously listed contract amendments for Ten Over Studio have been removed from the construction contingency budget amount and applied to the overall fire station project budget and the line item for Fees and Contingencies for soft costs in the project budget.

The project has $199,736.60 remaining in the construction contingency budget.

Measure H Bond Proceeds - Change Order #6 for $72,352.00.

Coordinated With:

Fire Department.

Attachment(s):

1. Change Order #6.

CALEXICO FIRE HQ STATION

PRIME CONTRACT CHANGE ORDER
Prime Contract Change Order: #006
TO: City of Calexico Fire Department FROM: Oakview Constructors, Inc. 415 Fourth Street 959 Calimesa Blvd.

Calexico, California 92231 Calimesa, California 92320
DATE CREATED: 08/01/2022 CREATED BY: Candice Wong
CONTRACT STATUS: Approved REVISION: NA
DESIGNATED REVIEWER: Fire Chief Diego Favila REVIEWED BY: Fire Chief Favila DUE DATE: NA REVIEW DATES: 08/01/2022
SCHEDULE IMPACT: None TOTAL AMOUNT: $72,352.00
CONTRACT FOR: Calexico Fire HQ Station
ATTACHMENTS: Proposed Change Orders 44R3
POTENTIAL CHANGE ORDERS IN THIS CHANGE ORDER:

PCO Title Schedule Impact Amount
#
44R3 Police Department Roofing Replacement 7 working days. 9 calendar days $72.352.00 Total: $72,352.00
CHANGE ORDER LINE ITEMS:

PCO # 44R3 : Police Department Roofing Replacement
# Description Amount
44R3 There is more work required to repair the police department roof than originally anticipated $72,352.00 and as shown in the contract documents. Once the existing roofing materials were removed. the extent of repair work was increased. This repair work is being authorized after regular contract time, so costs for Oakview supervision is included Subtotal: $72.352.00
Grand Total: $72.352.00
The Original Contract Sum: $5,827.400.00
Net Change by Previously Authorized Change Orders: $270,643.40 The Contract Sum Prior to this Change Order was: $6.098.043.40 The new Contract Sum including this Change Order will be: $6,170,395.40 The Contract time is changed by this Change Order: 9 Calendar Days

Page 1 of 2 ends

CALEXICO FIRE HQ STATION

PRIME CONTRACT CHANGE ORDER
=
CONTRACTOR:

OAKVIEW CONSTRUCTORS, INC.

BY DATE
CITY OF CALEXICO:

FIRE DEPARTMENT:

BY DATE
CITY OF CALEXICO:

CITY MANAGER:

BY DATE

Page 2 of 2 ends

P.O. Box 625 (909) 795-0990
959 Calimesa Blvd. Fax (909) 795-3150
Calimesa, CA 92320-0625 CA License #462847
DIR #1000024003
July 27, 2022
Candice Wong
Ten Over Studio, Inc.
539 Marsh Street
San Luis Obispo, CA 93401
Re: Calexico Fire Headquarters Station
City of Calexico
CHANGE ORDER PROPOSAL NO. 257-44R2 44R3
NARRATIVE: Cost for labor and material for additional work required at the Existing Police Station Roof per RFI 257-135 including additional 17'x31' affected adjacent area
In response to the concerns shared over lack of consistent Supervision by Oakview, supervision and overhead costs have been added at a reduced rate in lieu of the standard markup rates.

Rosscrete Roofing, Inc. $ 50,986.00
10% Overhead Profit $ 200.00
5% Overhead Profit $ 2,449.30
Subtotal $ 53,635.30
Oakview Constructors, Inc.

Labor to build and install a 14" minimum high curb for existing condensing unit:
2 Carpenter- 48 hours @ 94.25/hr $ 4,524.00
1 Superintendent- 7 days @ 90.79/hr $ 5,084.24
Material & Hardware $ 600.00
Misc. Sheet Metal, Flashing & Cap $ 3,000.00
Total Overhead Costs Charged per Calendar Day 7 days @ 684.58/day $ 4,792.06 Temp Toilets @14.14/day
Temp Fence @ 16.44/day
Home Office [email protected]/day
Subtotal $ 18,000.30
15% Overhead Profit

0.00 71,635.60
1% Bond $
716.36
Total $ 72,351.96
Total Proposal $ 72,352.00
Time Extension Required: Undetermined at this time
OAKVIEW CONSTRUCTORS, INC.
*Please note that no work will be completed without written authorization or approval of this change order proposal. Any costs associated with delays due to lack of written authorization of this change order proposal will be at the sole expense of the Owner.

Rosscrete Roofing, Inc
26 July 2022
Ms. Amber Moran
Project Manager
Oakview Constructors, Inc.
959 Calimesa Blvd.

Calimesa, CA 92320
Reference: Calexico Fire Department Station Headquarters Subject: Revision to Change Order # 2, Roof Repairs to existing Bldg.

Dear Amber,
The following shall address our Change Order # 2 for additional extra work required @ the Police Station Roof. (That Change Order is attached for clarity).

The total amount of Change Order # 2 was $ 46,986.00. Due to time frames and new assigned start date, Cost increases have taken place in both material and labor. The material Charge will be an additional $ 2,900.00. The labor charge will be an additional # 1,100.00. The breakdown is as follows. • Original Material, complete w/markup. $ 22,901.00
• New Material increase in material. (Including Mark-up) $ 2,900.00 : Original Labor Total w/markup $ 23,587.50
New Material increase in Labor. (Including Mark-up) $ 1,100.00 New Total Increase in Change Order. ...$ 4,000.00
Original Change Order #2 Request:

Additional Monies Added to Cahnage Order #2: $ 46.000.00 4,000.00 Revised Change Order # 2 Request: $ 50,986.00
Please call should you have additional questions.

Respectfully,
Greg Caringella
Greg Caringella
Rosscrete Roofing, Inc.
w/ attachements
PO Box 691, Rialto, CA 92377• (909) 356-1091• FAX (909) 356-9056 LIC #738539
Rosscrete Roofing, Inc
11 May 2022
Ms. Amber Moran fer
Estimating 1-6-202
Oakview Constructors, Inc.
959 Calimesa Blvd.

Calimesa, CA 92320
Reference: Calexico Fire Station Headquarters REVISED FROM 1/27/2022 Subject: Additional Work Required @ Existing Police Station Roof Dear Amber,
The following shall address additional non-contractural work required at the Calexico Fire Department Headquarters. This work was addressed in a 1/27/2022 Letter. A through field review has revealed there is additional work that needs to be accomplished to return the Police Station Roof to a normal, serviceable condition.

Scope of Work
The pictures you have forwarded indicate the existing field condition varies from original set of plans. We have also included our field sketches in this package to delineate that extra work requirement.

The Police Department had a complete 6" tapered insulation system covered with a built-up roof over the existing plywood sheeting, that was mentioned earlier.

Additional roofing work is also required at the existing front canopy at the police station. We will complete the tie-in to match the existing roof elevation and drainage pattern. There is no tapered insulation available to us as of now. We are going to have to field fabricate the taper from standard block EPS insulation. The taper will be covered with (1) layer of ¼" Ultra-Light Secure Rock cover board. The coverboard shall be covered with a new (4) ply, cap sheet built up roof consisting of (1) layer of 25# base sheet, (2) layers of Type IV ply sheet and (1) layer of fiberglass cap sheet, installed in full moppings of asphalt. The tie-in work shall receive our Rosscrete (1) year Warranty. It will not be eligible for a manufacturers warranty. Adjacent to the effected area, there is a 17' x 31' roof area that has extensive nail damage that is also in need of repair.

The existing RTU that was left in place must be set on a new platform approximately 14" higher than the decking. This must be accomplished to complete a proper roof tie-in. The same would be required for existing duct work or penetrations.
1/2
PO Box 691, Rialto, CA 92377• (909) 356-1091 • FAX (909) 356-9056 LIC #738539
Rosscrete Roofing, Inc
Material and Labor Breakdown
Labor: (25) Mandays@ $ 680.00/day = $ 17,000.00
Per Diem: (25) Mandays @ $ 85.00/day = $ 2,125.00 (Per Section D & E of Total Labor: $ 21,250.00 Master LaborAgreement)
Material:
(5) rolls 25# Base Sheet@ $ 41.00/roll $ 205.00
(8) rolls Ply IV Interply @ $ 47.00/roll $ 329.00
(20) rolls 72# Fiberglass Cap Sheet @ $ 38.00/roll 760.00 (11) sqs. ¼" Ultra Light Secure Rock Cover Board/$68.00/sq.$ 748.00 (8) sqs. ¼" EPS Taper System @ $ 400.00/sq. $ 3,200.00
Fasteners (1) lot @ $ 2,460.00 $ 2,460.00
Cases Low Rise Foam Adhesive @ $ 1,840.00/cs. $ 3,680.00 (3) Bdl. 3" × 3" fiber cant strip @ $ 50.00/bdl. 150.00 (1) Sack White Roofing Granules @ $ 33.00/sk 33.00
(1) 5- gal Asphalt Primer @ $ 70.00/pail $ 70.00
(2) 3.5 gal # 264 Apoc Elastomeric Mastic @ $ 103.00/pail $ 206.00 (6) ea. 10'- 1" Aluminum Term Bar @ $ 20.00/ea. 120.00
(1) roll 4" Fiberglass web @ $ 19.00/roll 19.00
(10) ctns. Type IV Asphalt @ $ 75.00/ctn 75.00
(11) sqs. 3.3" Base Polyiso Insulation @ $ 255.00 $ 2,805.00 Sheet Metal (1) Lot $ 4,200.00
Subtotal $19,060.00

8.25% Sales Tax $ 1,572.00
Total Material $ 20,632.00
RECAP
Labor: 21,250.00
Material: 20,632.00
Trip Charge 750.00
Gradall Equip 1,500.00
Subtotal 44,132.00
11% 0 & P 4,854.00
Total a 0 is hange range for Realis 48,986.00
Discount
Grandtotal 46,986.00 ( This Change Order)
Respectfully Submitted,
Greg Caringella
Greg Caringella | Project Manager
Rosscrete Roofing, Inc.
2/2
w/attachments
PO Box 691, Rialto, CA 92377• (909) 356-1091 • FAX (909) 356-9056 LIC #738539
4'
го
CleAN/Reusz GuTTer AND MeTAl
Nero 13'
meTal →
NeeD
cure MeTAl DolAIl
i Plat form 100' Neesco
< 13'→
NEED PlAT
T
NeRAs To Be RAIsca
+ New merel
→ € Nero edgemeral
19'
-FRONT Of

POLICE STATION
½- 1½ 9 pc 10° FlAT.:
1½ - 2"½= 9 pe con "4 105 B/F
22 - 3%2= 9 pc
5% - 4'2= 10 Rolls Ply
9 pc
13 , Rolla Cap
4½- 5"2=8 pc CHECA
15 AsphalT PERLiTE.
5% - 6"2=8 pc 1 Primer
1½ securrock 20 sHELTs Screo/ PlATeS
5 pc eA.
4 pc 4 ре 4 рс Ч рс 4 pr 4 pe
4%1½ 3%y+·½ 42 + $2
FiELD of paof CAHORY
3/8/22, 7:53 AM
Google Maps
Go gle Maps
Galeiee Phe
Google
Imagery ©2022 Google, Maa dala 02022, MaD data 02022 10 h https://www.google.com/maps/@32.6695325,-115.4924839,43m/data=|3m1!1e3 420 E 5th St - Google Maps
Go gle Maps 420 E 5th St