14 AGENDA STAFF REPORT
CALEXICO
DATE: February 15, 2023
TO: Mayor and City Council
APPROVED BY:
REVEIWED BY: Sandra L. Fonseca, Interim Finance Director PREPARED BY: Lilliana Falomir, Public Works Manager - Administrative SUBJECT: New River Improvement Project - Calexico Reach:
1. Award Bid Proposal from Mountain Cascade, Inc. in the Amount of $40,690,908.04.
2. Authorize City Manager to Sign Construction Agreement between the City of Calexico and Mountain Cascade, Inc. in the amount of $40,690,908.04 for the New River
Improvement Project - Calexico Reach.
Authorize City Manager to Sign Up to 5% Contingency
($2,034,545.40) for Administrative Expenses.
Recommendation:
It is recommended that the City Council approve the following items:
1. Award the Bid Proposal from Mountain Cascade, Inc. in the amount of $40,690,908.04.
2. Authorize City Manager to Sign Construction Agreement between the City of Calexico and Mountain Cascade, Inc. in the amount of $40,690,908.04 for the New River Improvement Project - Calexico Reach.
3. Authorize City Manager to Sign up to 5% Contingency ($2,034,545.40) for Administrative Expenses.
Background:
The New River is a Water of the United States and a California Water. It originates approximately 18 miles south of the US-Mexico Border, in the Mexicali Valley, Mexico. It enters the United States by the Calexico West Port of Entry, in Calexico, California. The City is proposing to implement New River Improvement AGENDA Project - Calexico Reach. The Project consists of three primary ITEM components:
14 1. Trash screen and diversion structure for the New River downstream from the International Boundary with Mexico.
Bypass encasement infrastructure for the New River from a point downstream of the International Boundary to a point downstream of the eastern boundary of the City of Calexico to address the public health threat that new River water quality poses to the southern area of the city.
3. A pump-back system to take treated wastewater from the existing Calexico Waste Water Treatment Plant (WWTP) and discharge it into the New River channel at a point near the proposed river diversion and encasement structure.
Milestones:
Project's Initial Funding from California Department of Water Resources On November 18, 2020, the City Council of the City of Calexico adopted Resolution 2020- 52, which in substantive part accepted twenty-eight million dollars ($28,000,000) of grant funds from the California Department of Water Resources (DWR) to build the New River Improvement Project - Calexico Reach (Project). The provided funding was based on the Opinion of Probable Project Cost prepared by Michael Baker International prepared for the Project in 2018 as part of its plans and specifications for the Project.
Funding Agreement #4600014089
April 26, 2021, the City of Calexico entered into Funding Agreement # 4600014089 with the California Department of Water Resources (DWR) for the disposition of twenty-eight- million dollars ($28,000,000) of state funds to build the Project. Of this amount, twenty- three million, seventy-ninety-five thousand dollars are set aside for construction of the Project. The rest of the money is set aside for Project administration, environmental compliance and permitting, and construction contracting and administration.
Project Permitting, Due Diligence, and Final Plans and Specifications Since the execution of the Funding Agreement with DWR, the City's efforts focused on finalizing the plans and specification for building the Project and obtaining the required permits to build the Project, including all environmental permits. In April 2022, the City obtained the necessary pre-construction permits to start building the Project and finalize the Project's plans and specifications to bid the Project. 1st Invitation for Bids
On May 16, 2022, the City issued, and the Imperial Valley Press published an Invitation for Bids for the construction of the Project. On June 28, 2022, the City received only one bid-from Mountain Cascade, Inc.—to build the Project at a cost of forty-one million, seven-hundred and thirty-four thousand, and six-hundred and seventy-six dollars ($41,734,276). On July 28, 2022, because the bid received significantly exceeded the available funding to build the Project, and without prejudice to the bidder, the City Council of the City of Calexico rejected the bid, during a public meeting, to allow for state funding partners to provide additional funding to implement the Project in its totality. It also directed the City staff to draft a new Invitation for Bids, with changes/provisions to implement the Project in Phases, as needed, and ensure the full amount of funding is available in a timely manner to implement the Project in its totality. 2n° Invitation for Bids
On August 10, 2022, in a Special City of Calexico Council public meeting, City staff presented a new Invitation for Bids for the Project as requested by the Council. The new Invitation for Bids, in relevant part, proposed to implement the Project in two Phases, with Phase 1 consisting of building the Trash Screen and Diversion Structure and Pump-back System; and Phase 2 consisting in the installation of the 72-inch bypass pipe; its energy dissipater, and stabilization and erosion control of an area at the western end of the Project. During the meeting, the City Manager informed the Council that, just before the Council meeting, DWR provided comments to City staff on the new Invitation for Bids.
The Council approved this new Invitation for Bids but directed the City staff to address the DWR comments before it issued and published the Bid.
The City staff and its Project consultants worked closely with the staff from DWR to address DWR's comments as directed by the Council. Additionally, City staff and its Project consultants worked closely with representatives of the State Water Resources Control Board (SWRCB), California Environmental Protection Agency (CalEPA), California Natural Resources Agency (CNRA), DWR, and elected officials to secure sufficient funding to build the Project in its totality as directed by the City Council.
On October 17, 2022, after addressing the DWR comments, the City issued the new IFB, hereafter referred to as "October 2022 new IFB." Michael Baker International (MBI)-the project design engineer—prepared a new Engineer Cost Estimate (ECE) in support of this new IFB. The October 2022 new IFB was published in the Imperial Valley Press and San Diego Union Tribune and was posted in various plan-rooms. Additionally, it was emailed directly to over 300 potential contractors. Further, City staff held two pre-bid meetings with potential bidders to provide an overview of the Project and answer questions about the Project. At the request of two bidders, the City extended the deadline for submitting bids from November 16 to November 30, 2022. On November 30, 2022, in spite of extended outreach to potential bidders and extension of the bid deadline, the City received again only one bid to build the Project. The bidder is again Mountain Cascade, Inc. (MCI), whose bid this time came in at forty-million, six-hundred and nine thousand, and nine-hundred and eight dollars with four cents ($40,609,908.04).
Attachment No. 1 is MCI's bid.
Additional Funding to Complete the Project and Bid Evaluation On January 3, 2023, SWRCB staff also informed the City Manager that the SWRCB Director of Financial Assistance has approved SWRCB staff's recommendation to award the City of Calexico eighteen million, five hundred and thirty thousand, and forty-seven dollars ($18,530,047.00) from the California-Mexico Border Rivers Program to complete construction of the Project. Pursuant to this additional funding for the Project, SWRCB and DWR executed an Interagency Agreement on January 30, 2023, to transfer the $18,530,047.00 in additional funding to DWR so that DWR can provide the additional funding to the City to build the Project in its entirety:
• This additional funding brings the total funds available for construction of the Project to forty-six million, five hundred and thirty thousand, and forty-seven dollars ($46,530,047).
• On February 15, 2023, the City Council will consider the adoption of a Resolution which (a) accepts the additional funding from SWRCB to build the Project, and (b) authorizes the City Manager to execute Amendment 2 to City-DWR Funding Agreement # 4600014089 to build the Project.
• Amendment 2, in substantive part, make the $18,530,047 in additional funding available to the City to build the Project, extends the deadline to build the Project till June 30, 2024.
Discussion & Analysis:
City staff and its Project consultants evaluated Mountain Cascade, Inc. bid to determine whether it is responsive and from a responsible bidder. It also held two meetings with DWR staff to discuss the bid, and a meeting with the bidder to ask for clarification on specific bid items.
West and Associates Engineering, Inc. (WAE), who represents the City on the Project as the City Engineer evaluated MCI's bid against the Project's Engineer Cost Estimate (ECE) that Michael Baker International prepared for the Project on October 10, 2022.
Attachment No. 2 provides WAE's evaluation of the bid. WAE also conducted job and professional references checks for MCI for specific jobs similar in nature and cost to the Project, to ensure MCI is qualified to build the Project (see Attachment No. 3). WAE analysis show that MCI's bid is responsive and that:
1. Most of the individual bid prices were within a reasonable level of deviation from the Engineer's Cost Estimate (ECE)
2. only thirteen (13) out of the 143 bid items had pricing that differed greatly from the ECE (by 300% or greater). However, these items represented only 7% of the overall bid price;
3. The checked references provided a positive review of MCI's work, with one reference highlighting MCI's "truly cares" about providing a "quality project for the client;" and
4. MCI has demonstrated a solid understanding of the essential tasks required for the Project and pleasant disposition to work with the City to make the Project construction successful.
The City Project Manager agrees with WAE conclusions. The City Project Manager also evaluated MCI's bid to determine whether it meets the specified requirements of the new Invitation for Bid (October 2022 |FB). Attachment No. 4 contains his evaluation, which also concludes that MCI's bid is responsive and meets the Invitation for Bids' requirements. The City Public Works Manager agrees with the conclusions also. The additional funding provided by the SWRCB to build the Project, together with the existing funding set aside for construction from the original Funding Agreement with DWR, is sufficient to cover the projected construction costs for the Project and includes a five percent (5%) contingency, which can be used to cover potential change orders for the Project.
Based on the foregoing, City staff recommending that the City Council of the City of Calexico award the bid proposal and authorize the City Manager to sign a construction agreement with Mountain Cascade, Inc. for the New River Improvement Project - Calexico Reach.
Fiscal Impact:
Capital Improvement Program Budgeted Item for FY 2022-2023 and 2023-2024 DWR State Grant - Fund No. 475-91-902-56003-000 $40,690,908.04 DWR State Grant - Fund No. 475-91-902-56003-000 (5% $2,034,545.40 Contingency)
Total $42,725,453.44
Coordinated With:
City Manager's Office.
City Attorney's Office.
Finance Department.
Public Works Department.
Attachments):
Mountain Cascade, Inc. Bid Proposal.
2. West and Associates Engineering Bid Evaluation.
3. Professional References Check for Mountain Cascade, Inc.
4. City Project Manager Bid Evaluation.
5. Mountain Cascade, Inc. Construction Agreement.
ATTACHMENT #1
JOB QUANTITIES AND PROPOSAL BID FORM
A. SIGNATORY STATEMENT
Please complete the following signatory statement:
TQ THE PUBLIC WORKS MANAGER OF THE CITY OF CALEXICO:
The undersigned hereby declares that it has carefully examined the location of the proposed work that it has examined the plans and specifications and read the accompanying instructions to bidders and hereby proposes to furnish all material except owner furnished materials, and do all work required to complete the said work in accordance with said plans and specifications and special provisions for the unit prices set forth in the following schedule. The bidder shall furnish prices for all items shown in the proposal.
"Name of Firm: _ Mountain Cascade, Inc.
END OF SIGNATORY STATEMENT
B. CONSTRUCTION CONTRACT AWARD
All bids are to be compared based on the Engineer's Cost Estimate for the Project and estimate of the quantities of work to be done. The Engineer's Cost Estimate puts the cost to build the Project at approximately thirty-four million, one hundred and ninety thousand, and five hundred and fifty- six dollars ($34,190,556). If awarded, the City shall award the construction contract to the responsive and lowest responsible bidder. City reserves the right to reject any and all bids.
C. JOB QUANTITIES AND BID PRICES FORMS
The following preliminary estimate of the quantities of work to be done and material to be furnished were prepared by MBI for the City and are approximate only, being given as a basis for the comparison of bids. The City of Calexico, does not expressly, or by implications agree that the actual amount of work, will correspond therewith, but reserves the right to increase or decrease the amount of and class of portion of the work that may be deemed necessary or expedient by the City. Tables 1 through 4, below, provide the quantities of work to be done and material to be furnished. Table 5 is set up to summarize the bid proposal. The tables constitute the Bid Price Forms also.
1. Overall Project Bid Items Schedule
Table Overall Project Bid tens a
SPECIRICATION SECTION & ITEM HOWANDUY" SUNT TOTAL
OTY LUNIT APRICE PRICE S
Mobilization/Demobilization Bid Items
Mobilization/Demobilization, Including Site Office Set
la Up/removal, Vehicle Set Up/removal, Bonds, etc. Not to IS Exceed 2% of Total Bid 700,000 700,000
(EXCLUDING CONTINGENCY)
NRIP CALEXICO REACH -66-
JOB QUANTITIES AND PROPOSAL BID FORM
Table 1-Overäll Project Bid Items
QUANTITY UNDE TOTAL
SPECNICATION SECTION & MEM: SPRICE PRICE:
LOTY UNIT
Staging (Housekeeping) of
Vehicles/Equipment/Materials
1b 1 LS 36,000 36 poo
Not Including Delivery (Delivery already included in
other bid items).
Traffic Control
Traffic Control for Approx. 200 LF of 2nd Street 1 LS
and, As-Needed, for Animal Shelter Drive 2,000 21,000
Water Pollution Control and other Permits Reimbursement Allowances За SWRCB Stormwater NDES Permit I LS 55,р00
55,000
RWQCB Low Threat Discharges NºDES Permit
3b 1 LS 1131,000
(for discharge of wastewater from dewatering Activities) 13/000 Other Permits & Reimbursement Allowances (See
30 1 LS
Technical Specs, Sec. 00 89 01, Parts 1.1.C.2 and 1.5) 110,000 110,000 Note: Items 3a, 3b, and 3c address permit fees and administration costs onty. Construction costs associated with these activities are addressed in the following sections as detailed in the Trash Screen --- and Diversion Structure, Pump Back System, and Bypass Encasement.
TABLE I (OVERALL PROJECT BID ITEMS) TOTAL 1,053,000
2. Trash Screen and Diversion Structure Bid Schedule
TABLE 2-TRASI SCREEN AND DIVERSION STRUCTURE BID SCHEDULE
SPECIFICATION SECTION & ITEM SC QUANTITY UNIT TOTAL
OTY. UNIT PRICE •PRICE
DIVISION 01
GENERAL REQUIREMENTS
01 35 19 - Temporary River Diversion
1 Temporary River Diversion LS
250,000 250,000
Subtotal
250,000
01 57 23 - Erosion and Sediment Control
1 Erosion and Sediment Control LS
111,500 11,500
Subtotal
1I,500
DIVISION 1 SUBTOTAL 2Ca,500
DIVISION 02
EXISTING CONDITIONS
02 30 00 - Subsurface Investigation
Subsurface Investigation 1 LS
800,000 800,000
Subtotal
800,000
02 41 13 - Site Demolition
NRIP CALEXICO REACH -67-
JOB QUANTITIES AND PROPOSAL BID FORM
TABLE 2-TRASH SCREEN AND DIVERSION STRUCTURE BID SCHEDULE
SPECIPICATION SECTION & ITEM QUANTHYS TOTAL
QTY APRICE PRICE
1 Removal of Existing DHS Security Gate and 1 EA
its Associated Hydraulic Actuation System.
Gate is located Upstream (South) of 2nd Street. 2,700 2,200 The Bridge Supporting the Gate and the Gate's
Actuation Hydraulic System shall be Left in
Place.
2 Remove Existing Chain Link Fencing LS
10,500 10,500
3 Clearing and Grubbing 1 LS $5,000 35000
Subtotal 48,200
DIVISION 2 SUBTOTAL 848,200
DIVISION 03
CONCRETE
03 10 00 to 03 39 00 - Cast in Place Concrete
1 Reinforced Concrete - Main Rectangular 788.0 CY
2000 11,576,000
Channel including Cutwater and Diversion
2 Transition Sections. 173.0 CY
Assume Reinforced Concrete for Now. 3000 519,000
(Possible Reinforced Gunnite Later)
3 Push-Up Weir (3' Thick) 135.4 CY
2000 270,800
4 Concrete Retaining Wall 175.0 CY
3000 525,000
DIVISION 03 SUBTOTAL
2,890,800
DIVISION 05
METALS
05 05 23 to 05 50 00 ~ Miscellaneous Metals
1 Trash Screens 3/8" x 3" Bar, Screen Support, 1 LS
52,000 S2,000
Trolley Rail Column Support, Etc.
DIVISION 05 SUBTOTAL 52,000
DIVISIONS 08
OPENINGS
| Heavy Duty Aluminum Hatches, Stainless Steel | 1 LS
Ladders, and Access Hardware 46,000 46,000
DIVISIONS 08 SUBTOTAL 46,000
DIVISION 31
EARTHWORK
31 23 19 - Dewatering
1 Isolated Area Dewatering and Treatment 180 Days
| 4000 720,000
Subtotal 720,000
NRIP CALEXICO REACH -68-
JOB QUANTITIES AND PROPOSAL BID FORM
TABLE2, TRASH SCREEN AND DIVERSION STRUCTURE BID SCHEDULE
QUANTITY UNIT TOTAL
SPECIRICATION SECTION & TEM PRICE
PRICE
31 23 00 - Excavation Support and Protection
Sheeting/Shoring for River Isolation and 24,340 SF
Dewatering (Install and Remove) 80 1,947,200
Subtotal 1, 042,700
31 23 00 - Trenching, Backfilling and Compaction
1 3/4" Rock (from Local Calexico Source) 873 CY
70 61,110
2 Crushed and Broken Rock 582 CY
76 44,232
3 Mirafi 140N or Equivalent (Incl Labor) 2 Roll
13,000 26,000
4 Imported Fill 3,178 CY 39
123,942
Subtotal
1255,284
31 05 19 - Soil Stabilization
Soil Stabilization LS 32S,p00
$25,p00
Subtotal 525,000
31 23 00 - Earthwork / Stockpile
1 Excavation 5,257 CY
32 168,224
2 Stockpile 5,257 CY
16 84112
Subtotal 252,336
DIVISION 31 SUBTOTAL
3,499,820
DIVISION 32
EXTERIOR IMPROVEMENTS
32 12 16 - Asphalt Concrete Pavement
1 3.5" Asphalt (HMA) 420 Tons
LZ.S 14,500
2 10" Aggregate Base (Class 2) 542 CY 85p4 85 46,070
subtotal 140,570
32 13 13 to 32 13 73 - Portland Cemeut Concrete Pavement for Drive Access, Screenings, Overflow Apron 1 6" PCC (Concrete) 156 CY 900 140,400
2 6" Aggregate Base (Class 2) 156 CY 120 18'
, 720
Subtotal 1159,120
32 31 20-Fences and Gates
1 8-ft High Ornamental Security Fencing 282 LF 218 6476 4-ft High Ornamental Security Fencing 190 LF 174 33,060 3 8-ft Chain Link Security Fencing (Along Banks 1,400 LF 13.79 19 1, 306
NRIP CALEXICO REACH -69-
JOB QUANTITIES AND PROPOSAL BID FORM
TABLE 2- TRASH SCREEN AND DIVERSION STRUCTURE BID SCHEDULE
QUANTITY UNIT TOTAL
SPECINCATION SE CHION A TEM PRICE
PRICE
of New River North and South of the 2nd Street
Bridge)
Subtotal 113, 842
DIVISION 32 SUBTOTAL 413,532
DIVISION 33
UTILITIES
33 05 37 - Mechanical (General)
Cast-In 20" Dia Wall Sleeve 1 EA
798 798
w/ Waterstop for 16" Pump Back Pipe
16" Linkseal EA
(Rubber-Segmented Compressible Annular Seal) 1,900 1,900 Subtotal 2,698
33 12 48 to 33 12 71 - Valves
72" 316 Motor-Operated Stainless Steel Slide 1 EA
Gate (at Diversion Structure) 70,000 70,000
2 Seismic Actuator 1 EA 125,000 125,000
Subtotal | 195,000
DIVISION 33 SUBTOTAL
197,698
DIVISION 41
MATERIAL PROCESSING AND HANDLING EQUIPMENT
41 24 00 - Overhead Trolley Mounted Automatic Raking System 1 Trolley, Gripper Rack, Controls, Complete 1 LS
2,750,000 2,750,000
2 Manufacturer Engineering, Field Service, and
LS
Freight (Non-Taxable) 160,000 160,000
Conerete foundation (3'x3'x3') for Security
Solar Powered Light Poles (per Separate
Plans) EA 46,179.57
4 oncrete foundation (2' diameter by 6' hi, 166544.88
lindrical footing) for Security Sola
[ Powered Light Poles (per Separate Plans)
DIVISION 41 SUBTOTAL 2, 976, 179,57
DIVISIONS 26-40
ELECTRICAL, COMMUNICATION, SAFETY, SECURITY, & PROCESS INTEGRATION General Electrical Work
1 1 IS 55,000 S5,000
At 25% of Div 41 Raking System Costs
DIVISIONS 26-40 SUBTOTAL SS,000
SUMMARY S
TRASH SCREEN AND DIVERSION STRUCTURE
BID SCHEDULE TOTAL 11,240,729.52
NRIP CALEXICO REACH -70-
JOB QUANTITIES AND PROPOSAL BID FORM
3. Pump-Back System & Force Main Bid Schedule
STABLE 3-PUMP-BACK SYSTEM & FORCE MAIN BID SCHEDULE
QUANTITY SUNTT. TOTAL
SPECUFICATION SECTION & ITEM PRICE PRICE
OTY UNIT
DIVISION 02
SITEWORK
02 41 13 - Existing Conditions
1 Remove Existing 8" Sewer Effluent Pipeline 10 LF . 87 870 2 Remove Existing 16" Sewer Effluent Pipeline 20 LF 87
3 Remove Existing 18" Storm Drain 140 LF 44 1,76
4 Relocate Existing Storage Shed IS
1,300 1,300
5 Remove Existing Trees EA 820 820
Demolish Existing AC Pavement 985 SF 2.00
1,930
7 Remove Existing Chain-Link Fence 80 LF
15 1,200
Plug Existing Effluent Manhole LS 1,700
,700
9 Remove and Repair Irrigation Piping LS 1,300 1,300
10 General Clear and Grubbing LS 5,400 5,400
Subtotal
22,460
DIVISION 2 SUBTOTAL.
22,460
DIVISION 03
CONCRETE
03 30 00 - Cast in Place Concrete
1 Pump Building 12" Slab on Grade 45 CY 79,875
1,775
2 Pump Bases & Housekeeping Pads 14 CY
2,400 33,600
3 Column Footings 9.5 CY
1,800 17,100
4 Wet Well 12" Top Slab 6.5 CY
3,700 24,050
5 16-ft Sq. × 2-ft Thick Footing for Wet Well 19 CY 46 760 6 Emergency Generator Pad 2.5 CY 3,460
1,360
Subtotal
1158,785
03 40 00 - Pre-Cast Concrete
1 Pre-Cast Flow Meter Vault 1 EA 67,080.
67,000
2 5-ft Diameter Manhole EA
20,000 40,000
3 12-f Diameter Wet Well EA
I/2, obtotal 219,000 112,000
DIVISION 3 SUBTOTAL
377,785
DIVISIONS 04 - 10
(METALS, DOORS & WINDOWS, FINISHES, SPECIALTIES) FOR PUMP BACK BUILDING 1 Building Accessories 1,024 SF 51 152,224
DIVISION 4 - 10 SUBTOTAL 52,224
NRIP CALEXICO REACH -71-
JOB QUANTITIES AND PROPOSAL BID FORM
TABLE 3 - PUMP-BACK SYSTEM & FORCE MAIN BID SCHEDULE
SPECIFCATION SECTION & ITEM QUANTITY JUNIT TOTAL
OXY 3. UNTT PRICE PRICE
DIVISION 13
SPECIAL CONSTRUCTION
13 34 00 - Pre-Fabricated Metal Building
Pre-Fabricated Metal Building 1 LS 172,000 1172,006
DIVISION 13 SUBTOTAL
0$4472, 172,000
DIVISION 23
HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)
23 05 00 - Common Work Results for HVAC
1 Louvers LS
12,000 14000
Air Conditioning Unit for Elec. Room LS 33.000
Subtotal 4,5,000
23 34 00 - Mechanical Exhaust Fans
Mechanical Exhaust Fans LS 14,000
14,000
Subtotal 12,000
DIVISION 23 SUBTOTAL 57,000
DIVISION 26
ELECTRICAL
1 Conductors and Cables LS
> 60,000 560,000
2 Lighting Control Devices LS 256,000
256,000
3 Switchboards and Panelboards LS
471,000 471,000
4 Power Distribution Units LS
442,000 442,000
5 200 kW Diesel Engine Generator LS
3665,000 365,000
6 Transfer Switches LS 53
000 53,000
7 | 50 HP Variable Frequency Drive EA
666,000 198,000
DIVISION 26 SUBTOTAL 7,345,000
DIVISION 27
COMMUNICATIONS
27 13 23 - Fiber Optic Conduit, Cable, and Parts
Fiber Optic Conduit, Cable and Parts 4,000 - LE 46 1184,000 DIVISION 27 SUBTOTAL 184,000
DIVISION 31
EARTHWORK
31 23 16.13 - Trenching, Backfilling, and Compaction
1 T 24" PVC Efuent Diversion Pipe 174 CY 218 37,932
24" PVC Overflow Bypass Pipe 40 CY 877 34,880
18" PVC Storm Drain Pipe 84 CY 29,400
4 16" DIP Force Main Pipe 3,812 CY 1350 457,440
Building, Wet Well, and Slab Base 400 CY 131 4400
NRIP CALEXICO REACH -72-
JOB QUANTITIES AND PROPOSAL BID FORM
TABLE 3- PUMP-BACK SYSTEM & FORCE MAIN BID SCHEDULE
SPECINCATION SECTION & ITEM QUANTITY UNTE TOTAL
PRICE PRICE
Subtotal 6/2,052
31 23 19 - Dewatering and Treatment
Force Main Alignment LS 22,000 U,000
Pump Back Site Features LS 310,000 310,000
Subtotal 332,000
31 25 00 - Erosion and Sediment Controls
31 32 00 - Soil Stabilization
Erosion & Sediment Control
53000 12,000
2 Soil Stabilization 1 LS
55,000
Subtotal 67,000
31 50 00 - Excavation Support and Protection
Trench Shoring for 16" Force Main LS 27,000 21,000
2 Shoring for Pump Back Site Features LS 16, 100
16,900
Subtotal 43,900
DIVISION 31 SUBTOTAL 1,054,952
DIVISION 32
EXTERIOR IMPROVEMENTS
32 12 16- Asphalt Concrete Pavement and Base
Pump Back Site Paving 11,500 SF 25 281,500
Trench Pavement Restoration
2 12,060 SF 21
for 16" Force Main 253,260
Subtotal 540,760
32 31 13 - Chain Link Fences
1 | 8-ft High Chain link Fence 130 LF 69 8,970
Subtotal 5,950
DIVISION 32 SUBTOTAL 549,730
DIVISION 33
UTILITIES
33 11 11 — Ductile Iron Pipe and Fittings
16" DIP Zinc-Coated Restrained Joints 4,020 LF 275 1105,500 2 16" DIP Zinc-Coated Restrained Fitting LS 225,000 225,000 3 Pump Station DIP & Pittings 331,000
33l obtotal 1, 711, 500
33 I1 12 - Miscellaneous Appurtenances
1 Pipe Supports IS
7,400 7,400
Dismantling Joints EA 8,200 24,600
1" Blow-Off Assembly EA 16,000 16,000
4 2" Combo Air-Vac Assembly 2 EA 11,000 22,000
NRIP CALEXICO REACH -73-
JOB QUANTITIES AND PROPOSAL BID FORM
TABLE 3- PUMP BACK SYSTEM & FORCE MAIN BID SCHEDULE
QUANTITYA UNIT TOTAL
SPECIFICATION SECTION & ITEM PRICE
PRICE
Subtotal
70,000
33 11 15 / 33 11 33 / 33 30 31 - Piping
10" Stainless Steel Suction Pipe 1 LS 18,735.01 18,235, sal 2 18" PVC Storm Drain Pipe 140 LF 12'
10,080
3 24" PVC Effluent Diversion Pipe 120 LF
10,080 32 10,560
4 24" PVC Overflow Bypass Pipe 40 LF
1,200
Subtotal
46,575.61
33 12 16 / 33 12 18 / 33 12 71 / 33 12 74 - Valves
1 10" Plug Valves EA
12,600 37,800
2 10" Rubber Flapper Check Valve 3 EA
20,000 60,000
3 24" Manual Slide Gate (Stainless Steel) EA
45,0000
4 16" Duckbill Valve EA 21,900
22,000
Subtotal
164,800
33 32 30 - Centrifugal Pumps & Motors
1 Self-Prime Centrifugal Pumps & Motors EA
74,000 222,000
2 Manufacturer Site Visit (Start-Up) LS
3,200 3,200
Pump Witness Travel and Lodging 1 LS 5000 5800
Subtotal 230,200
DIVISION 33 SUBTOTAL
2,223,075.6l
DIVISION 40
PROCESS INTEGRATION
40 63 43 - PLC Panel
40 71 13 In-Line Flow Measuring System
70 72 13 - Field Instrumentation
PLC Panel LS 100
100
2 12" Magnetic Flow Meter IS 28,000
28,000
3 Field Instrunentation IS _ 781,000
781,000
DIVISION 40 SUBTOTAL 809,100
20202 CASUMMARY 154243
PUMP-BACK SYSTEM & FORCE MAIN
BID SCHEDULE TOTAL 7, 847, 326.611
NRIP CALEXICO REACH -74-
JOB QUANTITIES AND PROPOSAL BID FORM
4. Bypass 72-inch Pipe Encasement Bid Schedule
TABLE4-BYPASS 12-INCH PIPE ENCASEMENT BID SCHEDULE
QUANTITY UNIT TOTAL
SPECIFICATION SECTION & ITEM PRICE PRICE
QTY TUNIT
DIVISION 1
GENERAL REQUIREMENTS
01 57 30 - Temporary Floodplain Impacts from Installation of 72-in Bypass Pipe Preparation of Plan to Revegetate Impacted
1 LS 5,500 5,500
Area
2 Removal, Stockpile, and Care of removed I
Acres
Native Plants 5,520 5,520
3 Replanting of Stockpiled Plants and, as 1
Acres
necessary, new Nursery Native Plants 16,600 16,600
Subtotal
27,620
DIVISION 02
EXISTING CONDITIONS
02 30 00 - Subsurface Investigation
1 Subsurface Investigation LS 110,000
10,000
02 41 13 - Site Demolition
1 Remove Existing Trees 10 EA 530
5,300
2 Relocate Existing Street Light 1 EA 18,000
18,000
3 Remove/Replace Existing 6' Chain Link Fence 1,000 LF 68 68,000 Subtotal 91,300
DIVISION 02 SUBTOTAL |
101,300
DIVISION 03
CONCRETE
03 30 00 - Cast in Place Concrete
1 Concrete Energy Dissipater 1 LS
(with Concrete Foundation Mat) 268,000 268,000
2 Concrete Cleanout (B8/Locking Covers) 2 EA 3,400
1,700
3 Concrete Terrace Ditch (Westerly Slope) 1 IS 5pM /80,000 180,000
4 Cutoff Walls (Within 72" Pipe Trench) 146 EA 5000
780,000
Subtotal 1, 181, 400
DIVISION O3 SUBTOTAL. |1, 181, 400.
DIVISION 31
EARTHWORK
31 05 00 - Common Work Results for Earthwork
1 Earthwork/Stockpile (Trench Export) 29,000 CY - 4.00
1116,000
NRIP CALEXICO REACH -75-
JOB QUANTITIES AND PROPOSAL BID FORM
TABLE4-BYPASS 72-INCH PIPE ENCASEMENT BID SCHEDULE
SPECIFICATION SECTION & ITEM QUANTITY UNIT TOTAL
QTY UNIT PRICE PRICE
2 Earthwork (2:1 Slope at West) 37,125 CY
17 631,125
3 Earthwork (Diversion/Access Road) 6,000 CY
26 156,000
4 Embankment Fill (3 Months) EA
EA 321,000 32,000
5 Earthwork (Key at 2:1 Slope at West) 36.
10, 000 360,000
6 Earthwork (Recompact/Clear at Pads) 56,000 CY 1,008,000 Subtotal
2,268,125
31 23 16.13 - Trenching, Backfilling and Compaction
1 3/4" rock (from local Calexico source) 14,500 CY 40
580,000
2 Mirafi 140N or equivalent 385 EA 2.60
Labor and Equipment (dig/lay/backfill) 185 EA 3.504055
19,3 48495
31 23 19 - Dewatering and Treatment 250
72" Encasement (Open Areas) 6,525 LF
1, 631,250
72" Encasement (Westerly Slopes) 1,300 LF 250
325,000
72" Encasement (2nd Strect) 200 LE 250
50,000
Subtotal
12,006,250
31 25 00 and 31 32 00 - Erosion/Sediment Control and Soil Stabilization Erosion, and Sediment Control 1 LS 46,000 46,000
2 Soil Stabilization LS
1,038.91 11,038.98
Subtotal
51,038.91
31 50 00 - Excavation Support and Protection
| Trench Shoring for 72" Encasement Pipe LS 88,000 88,000 Subtotal
DIVISION I SUBTOIAL 8, 603,968.91
DIVISION 32
EXTERIOR IMPROVEMENTS
32 31 13 - Chain Link Fences
1 8-ft High Chain Link Fence 500 LF 62 | 31,000
DIVISION 32 SUBTOTAL | 31,000
DIVISION 33
UTILITIES
33 42 19 - Centrifugally Cast Fiberglass Reinforced Polymer Mortar Gravity Pipe and Fittings 1 72" CCFRPM Pipe (20-foot Sections) 8,025 LF 953 7, 647,825 72" CCRFPM Pipe Under 2nd Street 200 LF
2 340 68,000
(200 feet - Open Cut Trench)
3 Freight Delivery / Mobilization 202 EA 11,500
2,265,500
NRIP CALEXICO REACH -76-
JOB QUANTITIES AND PROPOSAL BID FORM
TABLE 4-BXPASS 72-INCH PIPE ENCASEMENT BID SCHEDULE
QUANTITY UNIT TOTAL
SPECIFICATION SECTION & ITEM PRICE
QTY UNIT PRICE
4 Manhole Riser with 30" Cone 11 EA 22,000 242,00
5 Freight Delivery / Mobilization 3 EA 19,000 57,000
Coupling Elbows/Bends 19 EA
(11.25 and 22.5) 7,000 133,000
7 18" High-Density Polyethylene (HDPE)| 48 LF 166 7,968 8 12" High-Density Polyethylene (HDPE) 1,490 LF 123 183,270 DIVISION 33 SUBTOTAL
10, 604,563
SUMMARY
BYPASS 72-INCH PIPE ENCASEMENT
BID SCHEDULE TOTAL 20,549,851.91
NRIP CALEXICO REACH -77-
JOB QUANTITIES AND PROPOSAL BID FORM
5. Bid Summary
TABLE 5 - BID SUMMARY
Table 1 - Overall Project Bid Items 15/1,05,000
Table 2 - Trash Sereen and Diversion Structure 11, 240,729.52 Table 3 - Pump-Back System 117342326641
Table 4- Bypass 72-in Pipe
#20,549,851.91
TOTAL $ 40, 690, 909.04
GRAND TOTAL BID (S1- $ 40, 680, 908.04
GRAND TOTAL BID PRICE WRITEN IN WORDs: Forty million, sixhundred ninety twas sand, ninchundredeight Dollars and four
Cents.
NRIP CALEXICO REACH -78-
JOB QUANTITIES AND PROPOSAL BID FORM
Addenda Acknowledgement/Signature
1.00 - The undersigned hereby acknowledges the receipt of the following addendum:
None : No. 194 - No. 2 DAtiNo. 38 ; No. 4 _; No. 5
(Place initials above all appropriate numbers)
2.00 - The undersign hereby certifies that this proposal/bid is genuine and not made in the interest of or on behalf of any undisclosed person, firm or corporation.
3.00 - The undersigned hereby accepts on the behalf of its firm all provisions and requirements of the contract documents, including but not limited to those related to time of completion and liquidated damages.
4.00 - The undersigned hereby certifies that they are authorized representative of the firm on whose behalf this proposal/bid is submitted and that they are acting at the direction and with the required approval of said firm, which is identified as follows:
Name of firm:
Mountain Cascade, Inc.
Address of firm: 555 Exchange Court, Livermore, CA 94550 Telephone Number: () 925-373-8370 Fax Number: (..) 925-373-0940 Contractor's Liçense Number: ' 42 Type: A & HAZ
Signed: David Hicks Date: 11/30/22
V.P. of Estimating/Secretary
END OF PROPOSAL/BID FORM
NRIP CALEXICO REACH -79-
JOB QUANTITIES AND PROPOSAL BID FORM
ATTACHMENT #2
WEST&ASSOCIATES
ENGINEERING IN C
December 20, 2022
Ms. Lilliana Falomir and Mr. Jose Angel, P.E.
City Public Works Manager / City Project Manager
City of Calexico
608 Heber Avenue
Calexico, CA 92231
Subject: Bid Analysis and Recommendations for the New River Improvement Project - Calexico Reach Dear Ms. Falomir and Mr. Angel,
Per our telephone and email conversations, West & Associates Engineering (WAE) has completed our bid analysis for the New River Improvement Project (NRIP) - Calexico Reach. Our review was conducted on the bid submitted by Mountain Cascade, Inc. (MCI). We understand that MCI's bid represents the sole bid received by the City for the NRIP at the date of bid closing (Wednesday November 30, 2022). Therefore, the purpose of our bid analysis was to verify that the bid submitted by MCI is a responsive bid (i.e. a bid that complies with the Bid Documents), and that MCI is qualified to perform the work in accordance with the Contract Documents. The results of our bid analysis is provided below and on the following page.
Background
Based on our conversations with the City, we understand that the City's Project Manager (PM) and Public Works Department Manager (PWM) reviewed MCI's bid to ensure it complies with the bid requirements specified in the City's Invitation for Bids (IFB). The City found that MCI's bid contained the necessary attachments, including the bonding forms and guaranty check (payable to the City of Calexico). To this extent, the City found that MCI's Bid is a responsive bid. The details of the City's review of MCl's bid are provided in a separate City Staff Report. However, to complete the review of MCl's bid to a satisfactory level for the NRIP funding partners/stakeholders, WAE was tasked with review of MCI's bid from a technical standpoint.
Scope of Review
As the Consultant City Engineer for the NRIP, WAE has been providing the City with general bidding support for the NRIP. As such, our services for this bid analysis included preparation of a bid tabulation, background verification of project references provided in MC's bid, and coordination with the City and NRIP partners/stakeholders to convey the results of our review.
Our team prepared a bid tabulation in Excel, in order to review MCI's bid for accuracy and for conformity to the requirements of the City's IFB. The results of the bid tabulation analysis revealed that most of the individual bid prices were within a reasonable level of deviation from the Engineer's Cost Estimate (ECE). Only thirteen (13) out of the 143 bid items had pricing that differed greatly from the ECE (by 300% or greater). However, these items represented only 7% of the overall bid price!. Our team 1 Besides these items, there was one (1) minor calculation error in MCl's bid, which results in an additional amount of $57,500 that should have been added for freight/delivery of the large 72-inch bypass pipe. If the Council awards the contract to MCI, this error would be corrected after execution of the Construction Contract Agreement with MCL West & Associates Engineering, Inc. • 78 Anacapa Court, Foothill Ranch, CA 92610 • 949.716.7670 | 714.728.8082 • westaeng.com City of Calexico
Bid Analysis and Recommendations for the New River Improvement Project - Calexico Reach December 20, 2022
presented the bid tabulation to the City PM, whereupon the City PM reviewed the tabulation and concurred with our team's analysis. Based on this bid tabulation analysis, WAE and the City PM have determined that MCI provided a responsive bid in this regard also.
Our team also conducted a background check of the project references provided by MCI. A total of three (3) project references were contacted. The references were asked about MCI's overall jobsite performance, telephone and email coordination, responsiveness to field issues, and schedule. Each reference provided a positive review of MCI's work, with one reference highlighting MCI's "truly cares" about providing a "quality project for the client." The results of the background checks were shared with the City PM.
Finally, our team (WAE), the City PM, and the City PWM held two (2) meetings with the Department of Water Resources (DWR) to discuss MCI's bid. One meeting occurred on December 6, 2022, and the other meeting on December 9, 2022. The latter meeting included members of MC's staff and the City PM and PWM. During the latter meeting, MCI suggested that there was potential opportunity for "value engineering", which may be able to reduce overall construction costs, or to offset any potential increases in construction costs in other areas of the project.
Recommendations
As a result of the above bid analyses, WAE, the City PM, and the City PWM have all determined that MCI has provided a responsive bid, is a responsible bidder, is invested in cost savings for the City, and has the appropriate level of experience for this project. Therefore, we recommend that the City award the NRIP construction contract to MCI.
Thank you for this opportunity. Please contact me if you have any questions.
Sincerely,
We
Phillip West, P.E., QSD/QSP
Principal/President
West & Associates Engineering, Inc.
(949) 716-7670 Office | (714) 728-8082 Cell
[email protected]
West & Associates Engineering, Inc. 78 Anacapa Court, Foothill Ranch, CA 92610 949.716.7670 | 714.728.8082 • westaeng.com ATTACHMENT #3
Archived: Tuesday, December 20, 2022 5:27:36 PM
From: James Larot
Sent: Thu, 8 Dec 2022 14:50:59
To: 'Bryan Joe'
Ce: Phillip West
Subject: RE: Reference Check for Mountain Cascade Inc (MCI) Sensitivity: Nonnal
Good Morning Bryan,
Here is some information:
Bidders Reference Check
Contract: Canal Replacement, Segment 2 Pipeline Project.
The Pipeline Project consisted of construction of approximately 6,000 feet of 10-foot diameter pipeline from the west side of Marsh Creek past Sellers Avenue in Oakley, a 10-foot diameter flood isolation structure at the Canal headworks at Rock Slough Intake, and a 24-inch bypass pipeline at Pumping Plant No. 4. The Pipeline Project originally had a construction duration of two years from January 1, 2014 through December 31, 2015, and required shutdown of Rock Slough Intake from April 2014 to November 2015.
Contractor: Mountain Cascade, Inc. or MCI
Reference: Awarded at CCWD Board Meeting of October 2, 2013. Project located in Oakley, CA.
Contact: James Larot Phone Number: (925) 688-8393
Contract Amount: $15,650,000 plus 5% change order authority of $782,500 for a total amount not to exceed $16,432,500.
How was MCI's performance on the project overall? Very good.
Was MC's superintendent and foreman responsive to issues and questions? Yes.
Did MCI submit their submittals on-time? Yes.
Did the project finish on schedule? If not, were any schedule extensions justifiable or reasonable? Yes. Early completion. Original final completion date was January 15, 2016. Was completed ahead of schedule on September 16, 2015.
Were there any change orders or product substitution requests? If so, were thev justifiable? Yes, there were forty-five (45) change orders. They were ustifiable. Total executed Change Orders was $723,368.28 How was the quality of MCI's jobsite safety and traffic control? Good. long bottom st canal Seanent find em a mered reeler more than ted sediment foun Would you work with MCI again? Yes.
Hope that helps.
Thank you,
James R. Larot, Jr.
Operations Control Administrator
C 925-260-5425
P 925-688-8393
[email protected]
CONTRA COSTA WATER DISTRICT
1331 Concord Avenue, Concord, CA 94520
Facebook | Twitter
From: Bryan Joe <[email protected]>
Sent: Thursday, December 8, 2022 9:23 AM
To: James Larot < [email protected]>
Cc: Phillip West <[email protected]>
Subject: Reference Check for Mountain Cascade Inc (MCI) Good Morning,
We are consultants for the City of Calexico and are conducting a reference check for the low-bidder (Mountain Cascade Inc or "MCI") on the City's New River Improvement Project. We were provided a reference from MCI for a project that they worked on for your agency. The project reference is the Canal Levee Elimination & Flood Control project, which MCI completed in September 2015 (or thereabouts).
We would like to receive feedback from you on MCI's performance on this project. In particular, we would like to receive feedback on the following:
• How was MCI's performance on the project overall?
• Was MCI's superintendent and foreman responsive to issues and questions? • Did MCI submit their submittals on-time?
• Did the project finish on schedule? If not, were any schedule extensions justifiable or reasonable? • Were there any change orders or product substitution requests? If so, were they justifiable? • How was the quality of MCI's jobsite safety and traffic control? • Any notable issues found and/or fixed by MCI? (Unforeseen or anticipated issues). • Would you work with MCI again?
If you are unsure of any of the answers to our questions above, that is ok. We appreciate any feedback you can provide.
Thank you,
Bryan
BRYAN JOE
Project Coordinator | West & Associates Engineering, Inc.
Office 949.716.7670 | Cell 714.308.8845
www.westaeng.com| [email protected]
WEST&ASSOCIATES
Archived: Tuesday, December 20, 2022 5:27:39 PM
From: Dustin nott
Sent: Thu, 8 Dec 2022 10:50:34
To: Bryan Joe
Cc: Phillip West
Subject: RE: Reference Check for Mountain Cascade Inc (MCI) Sensitivity: Normal
Good morning Bryan,
Answers to your questions:
• How was MCI's performance on the project overall?
• MCI did a great job for us on this very complex project. • Was MCI's superintendent and foreman responsive to issues and questions? • Yes. Very helpful with communicating potential issues ahead of time and provided cost effective solutions. • Did MCI submit their submittals on-time?
• Did the project finish on schedule? If not, were any schedule extensions justifiable or reasonable? • Were there any change orders or product substitution requests? If so, were they justifiable? • Yes, and justifiable. Unforeseen conditions, buried debris, contaminated soil encounter, etc.. • How was the quality of MCI's jobsite safety and traffic control? • Any notable issues found and/or fixed by MCI? (Unforeseen or anticipated issues). • Yes. Several unforeseen work-around/modifications necessary in areas new design underground piping conflicted with old system(s) discovered not shown in as-built drawings.
• Would you work with MCi again?
° Yes
Good luck to you and your team with your project.
Thanks,
D sti ott
stimator
ood ellow ros.
C 925-580-2200
D 925-245-21 1
From: Bryan Joe <[email protected]>
Sent: Thursday, December 8, 2022 9:29 AM
To: Dustin nott<Dustin @goodfellowbros.com>
Cc: Phillip West <[email protected]>
Subject: Reference Check for Mountain Cascade Inc (MCI) Good Morning,
We are consultants for the City of Calexico and are conducting a reference check for the low-bidder (Mountain Cascade Inc or "MCI") on the City's New River Improvement Project. We were provided a reference from MCI for a project that they worked on for your agency. The project is Oakland Army Base, which MCI completed in April 2019 (or thereabouts).
We would like to receive feedback from you on MCI's performance on this project. In particular, we would like to receive feedback on the following:
• How was MCl's performance on the project overall?
• Was MCI's superintendent and foreman responsive to issues and questions? • Did MCI submit their submittals on-time?
• Did the project finish on schedule? If not, were any schedule extensions justifiable or reasonable? • Were there any change orders or product substitution requests? If so, were they justifiable? • How was the quality of MCI's jobsite safety and traffic control? • Any notable issues found and/or fixed by MCI? (Unforeseen or anticipated issues). • Would you work with MCI again?
If you are unsure of any of the answers to our questions above, that is ok. We appreciate any feedback you can provide.
Bryan
BRYAN JOE
Project Coordinator | West & Associates Engineering, Inc.
Office 949.716.7670 | Cell 714.308.8845
www.westaeng.com | [email protected]
WEST&ASSOCIATES
Archived: Tuesday, December 20, 2022 5:27:41 PM
From: tockton, elly
Sent: Tue, 13 Dec 2022. 11:26:45
To: Bryan Joe
Ce: Phillip West
Subject: Re: E TERN L Reference Check for Mountain Cascade Inc (MCI) Sensitivity: Normal
Hello - please see responses below.
Thank you,
elly Stockton
Plant Construction
Sent from my iPhone
On Dec 12, 2022, at 6:16 PM, Bryan Joe <[email protected]> wrote:
u-257?
Good Evening,
We are consultants for the City of Calexico and are conducting a reference check for the low-bidder (Mountain Cascade Inc or "MCI") on the City's New River Improvement Project. We were provided a reference from MCI for a project that they worked on for your agency. The project is Treasure Island/Yerba Buena Street Improvements.
We would like to receive feedback from you on MCI's performance on this project. In particular, we would like to receive feedback on the following:
• How was MCI's performance on the project overall?
MCI had a few setbacks but ultimately performed on an extremely challenging project. • Was MCI's superintendent and foreman responsive to issues and questions? Yes - MCI always responded proactively and was very solutions oriented when it came to issues. •
• Did MCI submit their submittals on-time?
When the submittals came from their office, yes. They struggled a bit with submittals from their subcontractors, biggest one being Tesco. • Did the project finish an schedule? If not, were any schedule extensions justifiable or reasonable? The schedule for this project was justifiably extended through no issue with MCI. • Were there any change orders or product substitution requests? If so, were they justifiable? Yes, there were change orders for added scope and they were justified. While substitutions were submitted, many were not approved due to the need to follow City Standards, therefore MCI provided specified products. • How was the quality of MCI's jobsite safety and traffic control? MCI had good jobsite safety protocols and traffic control. • Any notable issues found and/or fixed by MCI? (Unforeseen or anticipated issues).
MCI spent a fair amount of time working with the City, both water and sewer departments to get newly installed pump stations up and running. There was a disconnect between design documents and what the departments actually needed. MCI worked well with the City teams to get things operating the way they needed.
• Would you work with MCI again?
Yes, I would work with MCI again. I worked with one of their principles who truly cares about providing a quality product for the client.
If you are unsure of any of the answers to our questions above, that is ok. We appreciate any feedback you can provide.
Thank you,
Bryan
BRYAN JOE
Project Coordinator | West & Associates Engineering, Inc.
Office 949.716.7670 | Cell 714.308.8845
www.westaeng.com | [email protected]
WEST&ASSOCIATES
This e-mail message is intended only for the personal use of the recipients) named above. If you are not an intended recipient, you may not review, copy or distribute this message. If you have received this communication in error, please notify Plant Construction Company, L.P. Support ([email protected]) immediately by e-mail and delete the original message.
ATTACHMENT #4
NRIP CALEXICO REACH
MEMORANDUM
DATE: December 27, 2022
TO: Ms. Lily Falomir, City of Calexico Public Works Manager FROM: Jose L. Angel, P.E., Project Manager: far 1. Angel RE: NRIP Calexico Reach (Project) - Review of 11/30/2022 Mountain Cascade Inc. Bid Dear Lily,
I have reviewed the bid that Mountain Cascade, Inc. (MCI) submitted on November 30, 2022, to requirements of the Invitation for Bids the city issued on October 17, 2022 for the Project. Exhibit 1 (attached) presents a matrix that I prepared for the review of and my analysis of the bid. My review and analysis indicate that:
1. MBl's bid is responsive to the new IFB;
2. MCI's bid meets the Bid Requirements specified in the new IFB;
3. MCI is a California licensed contractor, in good standing with the California Department of Consumer Affairs; and
4. MCI and its proposed subcontractors are registered with the Department of Industrial Consequently, it is my opinion that MCI's bid is responsive to the new IFB. Additionally, I have reviewed the evaluation that West and Associates Engineering (WAE) conducted of MCI's bid and the job reterences check it conducted on MCl. I agree with WAE's conclusions, including that MCl is a responsible bidder and qualified to build the Project. Further, I agree with WAE's recommendation for the City to award the contract for construction of the Project to MCI.
Please let me know if you have questions about this matter or would like more details on any of the topics covered. I am available at (760) 877-0234. Thanks.
Attachment:
Exhibit 1 - Evaluation of Mountain Cascade's Bid for Compliance with Bid Requirements NRIP CALEXICO REACH -1-
MAY-JUL 2021 INVOICES
EXHIBIT 1
MOUNTAIN CASCADE, INC. - BID EVALUATION
Table 1 - Evaluation of Mountain Cascade's Bid for Compliance with Bid Requirements Requirement Bidder's Complies with
Description Required Documentation Requirement
ID Response/Documentation
(Yes/No)?
A completed and signed Signed acknowledgement form
Notice of IF addenda acknowledgement (see Proposal's p. 14) . See Acknowledgement of Addenda (see Page 79) must be included also Proposals p. 34-44 for the Item 6, p. 8 in the Bid Proposal. Proposal's copies of the Addenda.
Bid Instructions
a. Sealed Proposal must be received City Clerk's certification that Submitted sealed proposal by City by 2:00 PM on November Proposal was sealed. Proposal 30, 2022 read out loud on 11/30/2022 at
approximately 2:20 PM by City
Clerk.
Notice of IFB City Clerk's certification that Bidders Namvelope has Item 7a-7.d,p. b. Envelope with name of Bidder Proposal was in envelope with Bidders name.
Bidder's proposal uses Bid
Bidder's Bid Schedules must Forms of IF and lines up one- to-one against Tables 1-5 of
c. Proposal must comply with Bid line up one-to-one against IFB. See Proposal's p. 1 through Requirement 2 (see below) Tables 1-5 of IFB. Must also page 13. It also includes proper include proper certification. certification (see Proposal at p. 1 Mountain Cascade Proposal consists of 48 pages. It used the exact Bid Forms included in the FB. Therefore, its Proposal shows the page numbers of the IFB.
For the purpose of this evaluation though, I have assigned to its Proposal sequential page numbers. The Proposal with the assigned page numbers is attached hereto also.
MCl's BID EVALUATION REGARDING REQUIREMENTS OF NEW IFB -1- Table 1 - Evaluation of Mountain Cascade's Bid for Compliance with Bid Requirements Requirement Bidder's Complies with
Description Required Documentation Requirement
Response/Documentation
(Yes/No)?
d. Bid Info 1. Proposal/bid form (see
1. Proposal/bid form Proposal at p. 1-13)
2. 10% bid bond 2. 10% bid bond. See Proposal
3. Proposal Agreement at p. 24 for Bond from
4. Subcontractors listing Liberty Mutual Insurance
5. Workmen's comp Company, with a 10% Bond
6. Drug/alcohol testing reqs, payable to City of Calexico;
7. Non-collusion declaration p. 25 for Public Notary's
8. Corporate certification certification; p. 26 for
Power of Attorney.
3. Proposal Agreement. See
Proposal at p. 30.
4. Subcontractors listing. See
Same as Bid Info Proposal at:
• Page 15 for Griffin
Dewatering?
and All Valley Fence
and Materials
and A&R Construction
Pressure Grout
Company
V Ditch Co. and Legacy
Reinforcing Steel Co.
2 Please note that MCI crossed-out "Precision Electric" as a subcontractor and replaced it with Southern Contracting Company.
MCI's BID EVALUATION REGARDING REQUIREMENTS OF NEW IFB - 2- Table 1 - Evaluation of Mountain Cascade's Bid for Compliance with Bid Requirements Bidder's Complies with
Requirement Description Required Documentation
Response/Documentation Requirement
(Yes/No)?
• Page 20 for Southern
Contracting Co.
5. Workmen's comp. See
Proposal at p. 31.
6. Drug/alcohol testing reqs.
See Proposal at p. 32.
7. Non-collusion declaration.
See Proposal at p. 27.
8. Corporate certification. See
Proposal at pages 29 and
33. Other:
See Proposal at p. 28 for
certification of Site
Examination
Notice of IFB See Proposal at p. 46 for copy
Bidder must be licensed by California See Bid Requirement 18, below of Contractor's License No.
Item 7.g, p. 8 422496
Bid
Requirement Examination of Plans and Specifications Prima facie Submittal of Proposal on Time 1 (IFB p. 12)
Proposal Form must be made pursuant Bidder's Bid Schedules must Bidder's proposal uses Bid to "Job Quantities and Proposal Bid line up one-to-one against Forms of IF and lines up one- Bid Forms" of IFB. Tables 1-5 of IFB. Must also
Requirement to-one against Tables 1-5 of
include proper certification. IFB. See Proposal at p. 1 2 (IFB p. 12) through 13. It also includes
proper certification.
MCI's BID EVALUATION REGARDING REQUIREMENTS OF NEW IFB
Table 1 - Evaluation of Mountain Cascade's Bid for Compliance with Bid Requirements Requirement Complies with
ID Description Required Documentation Response/Documentation Requirement (Yes/No)?
Bidder's Guaranty: Proposal must be k Cash, cashier's check, certified Bon in ery mutual in trance Bid accompanied by cash, cashier's check, check, or bond payable to City Requirement certified check, or bidder's bond made Company 8 (IFB p. 13) payable to the City of Calexico for an
amount equal to at least ten percent
(10%) of the amount of said bid
Compliance with Laws and Regulations: Contractor's Certification of See Proposal at p. 29 for Bid • Licensed Contractor Qualifications for License Certification of Qualifications Requirement Classification and p. 46 for copy of
18 (IFB p. 14) Contractor's License No.
422496
Bidder's and subcontractors' Registration ID See DIR's at:
Bid
registration with DIR Registrations (force.com)
Requirement
19 (IFB p. 19)
Registration No. 1000005190
MCI's BID EVALUATION REGARDING REQUIREMENTS OF NEW IFB
ATTACHMENT #5
CONSTRUCTION AGREEMENT
CITY OF CALEXICO, CALIFORNIA
THIS AGREEMENT is made this 15" day of February, 2023, 2022, by and between the City of Calexico, a Municipal Corporation of the State of California ("CITY"') and Mountain Cascade, Inc. ("Contractor"). The City and the CONTRACTOR for consideration stated herein agree as follows:
1. Description of Project
CONTRACTOR shall provide for the construction of the New River Improvement Project - Calexico Reach in accordance with the October 17, 2022, Bid Documents and approved plans and Technical Specifications for the Project.
2. Description of Work
2.1 The work shall be done in conformance to the approved Plans and Specifications for the Project, and consists of three major Project components:
1. Installing a Trash Screen across the New River and building a structural concrete Diversion Structure for the New River at a point approximately 900 feet downstream from the US-Mexico International Boundary in Calexico. These tasks also entail:
a. Construction of a temporary diversion channel and coffer dam to build the Diversion Structure and Trash Screen.
b. Demolition work and site improvements in the Trash Screen and Diversion Structure area including grading, erosion control, fencing, installing two security gates to access and/exist the area, lighting, and constructing a new paved access road over an existing dirt road.
c. Removal of an existing US Department of Homeland Security (DHS) screen that is across the New River, between 2nd Street and the International Boundary, just upstream of the proposed location for the Trash Screen and Diversion Structure.
The bridge supporting the DHS screen shall be left in place.
2. Constructing a Pump-back System to replace the polluted water in the river channel between the Diversion Structure and that outfall of the 72-in Outfall with clean, treated and disinfected wastewater from the Calexico Wastewater Treatment Plant (WWTP). The Pump-back System consists of a 5.0-million gallons per day sewage pump station and the installation of approximately 4,000 feet of a 16-inch Ductile Iron Pipe (DIP) forcemain.
3. Installing approximately 1.5 miles of a 72-inch underground fiberglass reinforced mortar pipe (FRM pipe) to convey via gravity polluted New River water from the Diversion Structure to a point just upstream of where the All-American Canal Siphon goes over the New River. This work also requires:
a. Building an Energy Dissipater at the end of the 72-inch FRM pipe to prevent erosion of the New River channel at the outfall of the 72-inch FRM pipe. b. Construction of a small temporary coffer dam to build the Energy Dissipater.
NRIP CALEXICO REACH -86-
CONSTRUCTION AGREEMENT
c. Approximately 200 feet of micro tunneling under 2nd Street, as part of the installation of the 72-in FRM pipe.
d. Grading and erosion control of an area just above where the 72-inch FRM pipe outfalls into the River.
2.2 The work shall be accomplished within 300 days from the date of the Notice of Proceed.
2.3 CONTRACTOR shall furnish all of the labor, tools, equipment, and services required to perform all of the work in connection with the construction of Calexico New River Improvement Project - Calexico Reach in accordance with the invitation for Bids, incorporated by reference as though fully set herein. Said construction shall be in accordance with CITY approved plans and specifications prepared by Michael Baker International, and applicable state prevailing wages laws and regulations. Said invitation for bids, plans and specifications, are prevailing wages laws and regulations are as fully a part of the Agreement as if hereto attached or herein repeated.
3. Time for Completion
The work shall be commenced on the date stated in Notice to Proceed is issued for the Project, and shall be completed within the allotted working days after the date stated in such Notice.
4. Compensation
4.1 CITY shall pay the CONTRACTOR for the performance of this Agreement according to the terms and conditions contained in the Project's Invitation for Bids and Proposal or bid submittal by CONTRACTOR. CONTRACTOR shall take full payment in accordance with the following item prices incorporated as part of the proposal or bid submitted by CONTRACTOR.
4.2 CONTRACTOR agrees to receive and accept said compensation as full payment for furnishing all materials and for doing all the work contemplated and embraced in this agreement; also for all loss or damage, arising out of the nature of the work aforesaid, or from any unforeseen difficulties or obstructions which may arise or be encountered in the prosecution of the work until its acceptance by CITY and for all risks of every description connected with the work; also for all expenses incurred by or in consequence of the suspension or discontinuance of work and for well and faithfully completing the work in the manner and according to the plans and specification, and the requirements of the CITY Engineer. This provision in no way limits the CONTRACTOR's duties under other provisions herein.
NRIP CALEXICO REACH -87-
CONSTRUCTION AGREEMENT
5. Industry Standards
The CONTRACTOR agrees that is performance, and that of its employees or subcontractors, under this Agreement shall be performed in accordance with the standards customarily adhered to byan experienced and competent contractor using the degree of care and skill ordinarily exercised by reputable professionals practicing in the same field in the State of California. Where approval by the CITY, the CITY Manager, or other representatives of the CITY is required, it is understood to be general approval only and does not relieve the CONTRACTOR of responsibility for complying with all applicable laws, codes and quality construction and business practices.
6. Insurance
6.1 The CONTRACTOR shall not begin performing under this Agreement until it has: (a) obtained insurance certificates reflecting evidence of all insurance required herein; however, the CITY reserves the right to request, and the CONTRACTOR shall submit, copies of any policy upon reasonable request by the CITY; (b) obtained CITY approval of each company or companies as required herein; and (c) confirmed that all policies contain the specific provisions required herein. Further the CONTRACTOR shall not modify any policy or endorsement thereto which increases the CITY'S exposure to loss for the duration of this Agreement.
6.2 Types of Insurance.
At all times during the term of this Agreement, CONTRACTOR shall maintain insurance coverage as follows:
1. Commercial General Liability
For all of the CONTRACTOR's operations, including contractual, broad form property damage, completed operations, and independent CONTRACTOR's liability, the CONTRACTOR shall keep in full force and effect, during any and all work on this Project, all applicable insurance to cover personal injury, bodily injury and property damage, providing coverage to a combined single limit of $1,000,000 per occurrence, subject to an annual aggregate of $2,000,000 for general liability, completed operations and personal injury other than bodily injury. Agreementual liability shall include coverage of tort liability of another party to pay for bodily injury or property damage to a third person or organization. Agreementual liability limitation endorsement is not acceptable.
2. Commercial Automobile Liability
For all the CONTRACTOR's automobiles including owned, hired and non-owned automobiles, the CONTRACTOR shall keep in full force and effect, automobile insurance for bodily injury and property damage providing coverage to a combined single limit of $1,000,000 per occurrence. Insurance certificate shall reflect coverage for any automobile [any auto]. The CITY shall be named as an additional insured, but NRIP CALEXICO REACH -88-
CONSTRUCTION AGREEMENT
only for liability arising out of the use of CONTRACTOR's automobiles and only arising out of the performance of this Agreement.
3. Worker's Compensation
For all of the CONTRACTOR's employees who are subject to this Agreement and to the extent required by the State of California, the CONTRACTOR shall keep in full force and effect, a workers compensation policy. That policy shall provide a minimum of $1,000,000 of employees liability coverage and the CONTRACTOR shall provide and endorsement that the insurer waives the right of subrogation against the CITY and its respective elected officials, officers, employees, agents and representatives.
6.3 Rating Requirements
All bonds used to guarantee work and performance under this Agreement and all insurance required by express provision of this Agreement shall be carried only by responsible insurance companies that have been at least and "A" or "A" and "V" rating by AM BEST, that are licensed and approved by the State to do business in the State of California, and that have been approved by the CITY.
6.4 Deductibles
All deductibles on any policy shall be the responsibility of the CONTRACTOR.
6.5 Specific Provisions Required
Each policy required under Section 6 herein, shall expressly provide, and an endorsement shall be submitted to the City, that:
1. Except as to Workers Compensation, the City of Calexico and its respective elected officials, officers, employees, agents, and representatives shall be named as additional insureds. The CITY's Additional Insured status must be reflected on additional insured endorsement which shall be submitted to the CITY.
2. The policies are primary and any insurance that may be carried by the CITY is non- contributing, as reflected in an endorsement which shall be submitted to the CITY.
3. The policies cannot be canceled, non-renewed or materially changed except after thirty calendar days prior written notice by the CONTRACTOR to the CITY by certified mail, as reflected in an endorsement which shall be submitted to the CITY except for non-payment of premium, in which case ten (10) days notice will be provided.
4. Before performing under this Agreement, the CONTRACTOR shall provide the CITY with all Certificates of Insurance accompanied with all endorsements.
NRIP CALEXICO REACH -89-
CONSTRUCTION AGREEMENT
5. The CONTRACTOR may obtain additional insurance not required by this Agreement.
7. Agreement or Compliance with Labor Code
CONTRACTOR certifies that it is aware of the provisions of Section 3700 of the Labor Code which requires every employer to be insured against liability for Worker's Compensation or to undertake self insurance in accordance with the provisions of that Code, and will comply with such provisions before commencing the performance of the work of this Agreement.
8. Control of Agreement
The improvement contemplated in the performance of this contract is a project over which the City of Calexico shall exercise general supervision. The CITY therefore shall have the right to assume full and direct control over this contract whenever the CITY, at its sole discretion, shall determine that its responsibility to the State of California so requires.
9. Conflicting Terms
If an apparent conflict or inconsistency exists between the main body of this Agreement and the bid, proposal or other incorporated document, the main body of this Agreement shall control. If a conflict exists between applicable federal, state, or local law, rule, regulation, order, or code and this Agreement, the law, rule, regulation, order, or code shall control. Varying degrees of stringency among the main body of this Agreement, the Exhibits, and laws, rules, regulations, orders, or codes are not deemed conflicts, and the most stringent requirements shall control. Each party shall notify the other immediately upon the identification of any apparent conflict or inconsistency concerning this Agreement.
10. Indemnification and Hold Harmless Agreement
10.1 With respect to any liability, including but not limited to claims asserted or costs, losses, attorney fees (for attorney of CITY's choosing), or payments for injury to any person or property caused or claimed to be caused by the acts or omissions of the CONTRACTOR, or the CONTRACTOR's employees, agents, and officers, arising out of any services performed involving this project, the CONTRACTOR agrees to defend, indemnify, protect, and hold harmless the CITY, its agents, officers, or employees from and against all liability. Also covered is liability arising from, connected with, caused by, or claimed to be caused by the active or passive negligent acts or omissions of the CITY, its agents, officers, or employees which may be in combination with the active or passive negligent acts or omissions of the CONTRACTOR, its employees, agents or officers, or any third party. The CONTRACTOR's duty to defend, indemnity, protect and hold harmless shall not include any claims or liabilities arising from the soles negligence or sole willful misconduct of the CITY, its agent, officers or employees. This section in no way alters, affects or modifies any of CONTRACTOR's other obligations and duties herein.
NRIP CALEXICO REACH -90-
CONSTRUCTION AGREEMENT
10.2 The CONTRACTOR agrees to pay any and all costs the CITY incurs enforcing the indemnity and defense provisions herein.
11. Notices
In all cases where written notice is required under this Agreement, service shall be deemed sufficient if the notice is deposited in the United States mail, postage paid. Proper notice shall be effective on the date it is mailed, unless provided otherwise in this Agreement. For the purpose of this Agreement, unless otherwise agreed in writing, notice to the parties herein shall be addressed CITY CONTRACTOR:
City of Calexico Mountain Cascade, Inc.
Public Works Department 555 Exchange Court
608 Heber Avenue Livermore, CA 94550
Calexico, CA 92231
12. Non-Assignment
The CONTRACTOR shall not assign the obligations under this Agreement, whether by express assignment or by sale of the company, nor any monies due or to become due, without the CITY's prior written approval. Any assignment in violation of this paragraph shall constitute a Default and is grounds for immediate termination of this Agreement, at the sole discretion of the CITY. In no event shall any putative assignment create a contractual relationship between the CITY and any putative assignee.
13. Independent Contractors
The CONTRACTOR and any SUBCONTRCTORS employed by the CONTRACTOR shall be independent contractors and not agents of the CITY.
14. Compliance with Controlling Law
14.1 The CONTRACTOR shall comply with all laws, ordinances, regulations, and policies of the federal, state and local governments applicable to this Agreement, including California Labor Code section 1720 relating to the payment of prevailing wages, including inspection and land surveying work. In addition, the CONTRACTOR shall comply immediately with all directives issues by the CITY or its authorized representatives under authority of any laws, statures, ordinances, rules or regulations. The laws of the State of California shall govern and control the terms and conditions of this Agreement.
14.2 Pursuant to the Labor Code of the State of California, or local laws applicable thereto, the CITY has ascertained that the CONTRACTOR shall be responsible for paying NRIP CALEXICO REACH -91-
CONSTRUCTION AGREEMENT
prevailing wages as established by the State of California, Director of Industrial Relations. Under Section 1776 of the State Labor Code, the CONTRACTOR, and all subcontractors, are required to keep accurate payroll records. This Section specifies the content thereof, inspection and duplication procedures, and certain notices required of the CONTRACTOR pertaining to their location.
14.3 Whenever the CONTRACTOR or any representative, agent or employee Of CONTRACTOR performing a public works project is found by the Department of Industrial Relations ("DIR") or the CITY to be in violation of the prevailing wage requirements imposed by law, the CONTRACTOR shall indemnify and hold CITY harmless from any and all liability arising from such violation, including any and all liability imposed on the City. The CONTRACTOR's duty to indemnify the CITY pursuant to this section shall include any and all costs and expenses incurred by the CITY therefrom, including but not limited to any penalties imposed on the CITY by DIR or any other state agency and reasonable attorney's fees.
14.4 Nothing in this section shall be construed to limit, alter or amend the CONTRACTOR's duty to indemnify under any other provisions of this Agreement.
15. Jurisdiction and Venue
The venue for any suit or proceeding concerning this Agreement, the interpretation or application of any of its terms, or any related disputes shall be in the County of the Imperial, State of California.
16. Integration
This Agreement and the exhibits and references incorporated into this Agreement fully express all understandings of the Parties concerning the matters covered in this Agreement. No change, alteration, or modification of the terms or conditions of this Agreement, and no verbal understanding of the Parties, their officers, agents, or employees shall be valid unless made in the form of a written change agreed to in writing by both parties or an amendment to this Agreement agreed to both Parties. All prior negotiations and agreements are merged into this Agreement.
17. Counterparts
This Agreement may be executed in counterparts, which when taken together shall constitute a single signed original as though all parties had executed the same page.
18. No Waiver
No failure of either the CITY or the CONTRACTOR to insist upon the strict performance by the other of any covenant, term or condition of this Agreement, nor any failure to exercise any right or remedy consequent upon a breach of any covenant, term, or condition of this Agreement, shall NRIP CALEXICO REACH -92-
CONSTRUCTION AGREEMENT
constitute a waiver of any such breach or such covenant, term or condition. No waiver of any breach shall affect or alter this Agreement, and each and every covenant, condition, and term hereof shall continue in full force and effect to any existing or subsequent breach.
19. Severability
The unenforceability, invalidity, or illegality of any provision of this Agreement shall not render any other provision of this Agreement unenforceable, invalid, or illegal.
NRIP CALEXICO REACH -93-
CONSTRUCTION AGREEMENT
IN WITNESS WHEREOF, the parties hereto through their agent duly authorized, have executed this Agreement as of the day and year first above written.
ATTEST:
GABRIELA GARCIA Esperanza Colio Warren
City Clerk of the City of Calexico City Manager of the City of Calexico
CONTRACTOR
By:_
Signature Date
Printed Name and Title
Licensed in accordance with an act
Providing for the registration of contractors,
License No.
APPROVED AS TO FORM AND EXECUTION
Carlos Campos Date
City Attorney
END OF AGREEMENT
NRIP CALEXICO REACH -94-
CONSTRUCTION AGREEMENT