AGENDA
ITEM
17 AGENDA
CALEXICO California ITEM

WHERE CALIFORNIA AND MEXICO MEET
17 CITY COUNCIL

AGENDA STAFF REPORT
DATE: November 6, 2024
TO: Mayor and City Council
APPROVED BY: Juan Contreras, Acting City ManagerJAe
REVIEWED BY: Sandra Fonseca, Interim Finance Director SF SUBJECT: Authorize Acting City Manager to Sign and File Notice of Completion for Renovations to Calexico Fire Station No. 2.
===- == ====
Recommendation:

Authorize Acting City Manager to sign and file Notice of Completion for Renovations to Calexico Fire Station No. 2.

Background:

On March 6, 2024, the City Council of the City of Calexico awarded the bid proposal for the Renovations to Calexico Fire Station No. 2 to A&N Quality Builders in the amount of $966,559.00 and authorized the City Manager to approve any future change orders not-to-exceed $48,328.00 (5% of A&N Quality Builders Base Bid) as Per City Ordinance No. 1218.

On April 16, 2024, the City Manager approved Change Order No. 1 in the amount of -$24,560.00.

On May 8, 2024, the City Council of the City of Calexico approved Change Order No. 2, 3, 4 and 5 in the amount of $315,284.00.

On June 5, 2024, the City Council of the City of Calexico approved Change Order No. 6 through 12 in the amount of $247,927.00.

On August 21, 2024, the City Council of the City of Calexico approved Change Order No. 13 in the amount of $15,505.00.

On September 4, 2024, the City Council of the City of Calexico approved Change Order No. 14 in the amount of $7,066.00.

On October 22, 2024, the City Council of the City of Calexico approved Change Order No. 15 and 16 in the amount of $24,956.00 bring A&N Quality Builders new contract amount to $1,577,297.00.

Discussion and Analysis:

On October 31, 2024, A&N Quality Builders completed the renovations to Calexico Fire Station No. 2. City staff is recommending that the City Council of the City of Calexico authorize the Acting City Manager to sign and file Notice of Completion of said project.

Fiscal Impact:

No fiscal impact at this time.

Coordinated With:

City Manager's Office.

Fire Department.

Public Works Department.

The Holt Group, Inc.

Attachments):

1. Notice of Completion.
2 ATTACHMENT NO. 1
RECORDING REQUESTED BY:

City of Calexico
AND WHEN RECORDED MAIL TO:

City of Calexico
Office of the City Clerk
608 Heber Avenue
Calexico, California 92231

SPACE ABOVE THIS LINE FOR RECORDER'S USE

NOTICE OF COMPLETION
Notice pursuant to Civil Code Section 3093, must be filed within 10 days after completion.

Notice is hereby given that:

The undersigned is owner or corporate officer of the owner of the interest or estate stated below in the property hereinafter described:

2. The full name of the owner is City of Calexico

3. The full address of the owner is 608 Heber Avenue, Calexico, California 92231

4. The nature of the interest or estate of the owner is:

In fee

5. The full names and full addresses of all persons, if any, who hold title with the undersigned as joint tenants or as tenants in common are

NAMES ADDRESSES
None

6. The full names and full addresses of the predecessors in interest of the undersigned, if the property was transferred subsequent to the commencement of the work or improvements herein referred to

NAMES ADDRESSES
None

7. A work of improvement on the property hereinafter described was completed on_October 31, 2024. The work done was removal/replacement of clay tile and built-up roofing, renovations to plumbing, mold mitigation, H.V.A.C., and electrical systems, new interior finishes and painting.

8. The name of the contractor, if any, for such work of improvement was A&N Quality Builders, 998 Industry Way, El Centro, CA 92243 March 12, 2024
(Date of Contract)

9. The property on which said work of improvement was completed is in the City of_Calexico County of_Imperial , State of California , and is described as follows:

Renovations to Calexico Fire Station No. 2

10. The street address of said property is 900 Grant Street, Calexico, CA 92231 Dated November 6, 2024
Juan Contreras, Acting City Manager
City of Calexico

VERIFICATION
I, the undersigned, say: I am the Acting City Manager, the declarant of the foregoing Notice of Completion; I have read said Notice of Completion and know the contents thereof; the same is true to my own knowledge. I declare under penalty of perjury that the foregoing is true and correct.

Executed on November 6, 2024, at_Calexico , California
Juan Contreras, Acting City Manager