AGENDA
ITEM
9 AGENDA
CALEXICO California ITEM

WHERE CALIFORNIA AND MEXICO MEET
9 CITY COUNCIL

AGENDA STAFF REPORT
DATE: July 2, 2025
TO: Mayor and City Council
APPROVED BY: Armando Orozco, Interim City Manager AC
REVIEWED BY: Karla Chaparro, Finance Director
PREPARED BY: Liliana Falomir, Public Works Manager - Administrativag Tele SUBJECT: Adopt a Resolution of the City Council of the City of Calexico Ratifying the Submittal of Surface Transportation Block Grant (STBG) Application in the Amount of $681,000 with a Local Match of $89,000 (Measure "D"), Project Milestone Dates, and Timely Use of Funds for Cole Road between SR-98 and Bowker Road Rehabilitation Project.
=====SS==SSSS2ssssss=sass==== ------
Recommendation:

Adopt a Resolution of the City Council of the City of Calexico Ratifying the Submittal of Surface Transportation Block Grant (STBG) Application in the Amount of $681,000 with a Local Match of $89,000 (Measure "D"), Project Milestone Dates, and Timely Use of Funds for Cole Road between SR-98 and Bowker Road Rehabilitation Project.

Background:

On March 31, 2025, the Southern California Association of Governments (SCAG) called out for projects under the Surface Transportation Block Grant (STBG) for Fiscal Year 2026/2027 and 2027/2028. All Imperial Valley agencies were instructed to submit project listings based on the locally adopted criteria by SCAG. The criteria adopted are as follows:

A. Regional Priorities
Tier 1
• Clean Transportation
• Resilience of At-Rist Infrastructure
• Transit and Multimodal Integration
Transportation Demand Management (TDM)
• Transportation System Management and Goods Movement
Tier 2
• Complete Streets
• Natural Lands Preservation
• System Preservation
B. Federal Performance Management Areas
C. Community Economic Development Benefits
SCAG will evaluate the projects submitted, rank them and submit their recommendation to California Transportation Commission (CTC) for final adoption and STBG programming.

Discussion and Analysis:

On May 16, 2025, the Public Works Department submitted the following application to SCAG for consideration under STBG:
• Cole Road between SR-98 and Bowker Road Rehabilitation Project The project consists of grinding the existing asphalt pavement and overlaying (ARHM- GG on ARAM over Leveling Course), placement of pavement markings and traffic striping per CAMUTCD, and adjustment of existing utility lids to grade.

One of the requirements that is needed to finalize the application is for City Council to review and adopt a resolution that will support the above-mentioned project if it is awarded. For this reason, City staff is requesting that the City Council adopt a resolution ratifying the submittal of Surface Transportation Block Grant (STBG) application, project milestone dates, and timely use of funds.

Fiscal Impact:

Estimated Capital Improvement Program (CIP) Budget FY 2027-2028

REVENUE
Federal Grant - STBG $681,000
Local Match - Measure "D" $89,000
Total $770,000.00

EXPENDITURE
Fund No. 412-90-XXX-56000-000 $770,000.00
Total $770,000.00
Coordinated With:

City Manager's Office.

Finance Department.

Public Works Department.
2 Attachments):

1. Resolution No. 2025- of the City Council of the City of Calexico Ratifying the Submittal of Surface Transportation Block Grant (STBG) Application in the Amount of $681,000 with a Local Match of $89,000 (Measure "D"), Project Milestone Dates, and Timely Use of Funds.

ATTACHMENT NO. 1
RESOLUTION NO. 2025-—

A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF CALEXICO RATIFYING

THE SUBMITTAL OF SURFACE TRANSPORATION BLOCK GRANT (STBG)

APPLICATION, PROJECT MILESTONE DATES, AND TIMELY USE OF FUNDS WHEREAS, the City of Calexico is eligible to apply for and receive Federal and State transportation funds including STBG funds; and
WHEREAS, AB 1012 requires that state and federal funds be expended in a timely manner; and WHEREAS, the City of Calexico desires to ensure that its projects are delivered in a timely manner to avoid losing funds for non-delivery; and
WHEREAS, it is understood by the City of Calexico that failure for not meeting project milestone dates for any phase of a project may jeopardize federal or state funding to the Region; and NOW THEREFORE BE IT RESOLVED, that the City Council of the City of Calexico hereby agrees to ensure that all project milestone schedules for all project phases will be met or exceeded, a. The opportunity for public comment was provided at a public meeting; b. Local funds in the amount of $89,000.00 from Measure "D" will be used to leverage the federal funds for the project;
c. Project is consistent with the circulation element of the City of Calexico General Plan planning process;
d. Project is consistent with the adopted pavement management plan (for rehabilitation projects only;
e. The City Manager or his designee is authorized to execute grant application, and/or any documentation pertaining to STBG funding.

BE IT FURTHER RESOLVED, that failure to meet project milestone schedules may be deemed Asuite aent reusegan the lunds as demyd reepstation Commission Policy Board to terminate PASSED, APPROVED AND ADOPTED this 2d day of July 2025.

Diana Nuricumbo, Mayor
Attest:

Veronica Alvarado, City Clerk
Resolution No. 2025-—

Page 2 ends

Approved as to Form:

Carlos Campos, City Attorney
State of California)
County of Imperial) ss.

City of Calexico )
I, Veronica Alvarado, City Clerk of the City of Calexico, California do hereby certify that above and foregoing Resolution No. 2025-_ was duly passed, approved and adopted by the City Council at its regular meeting held on the 2d of July, 2025 by the following vote to-wit:

AYES:

NOES:

ABSENT:

Veronica Alvarado, City Clerk