AGENDA
ITEM
16 AGENDA
CALEXICO California ITEM

WHERE CALIFORNIA AND MEXICO MEET
16 CITY COUNCIL

AGENDA STAFF REPORT
DATE: September 3, 2025
TO: Mayor and City Council
APPROVED BY: Benjamin Martinez, City Manager
REVIEWED BY: Karla Chaparro, Finance Director VU
PREPARED BY: Jesus Villegas, Public Works Director/City Engineer SUBJECT: Authorize City Manager to Sign Change Order No. 1 with Rove Engineering, Inc. in the Amount of $88,776.00 for Scaroni Road Pavement Rehabilitation State Project No. LPPSB1L-5168(034)
====E
Recommendation:

It is recommended that the City Council of the City of Calexico approve the following:

1. Authorize City Manager to Sign Change Order No. 1 with Rove Engineering, Inc. in the amount of $88,776.00 for Scaroni Road Pavement Rehabilitation State Project No.

LPPSB1L-5168(034).

Background:

The City of Calexico Public Works Department received a grant from California Department of Transportation (Caltrans) for FY 2023-2024 in the amount of $942.000.00 ($471,000.00 - State Grant and $471,000.00 - Local Match) for the Project No. LPPSB1L-5168(034) - Scaroni Road between Cole Boulevard and Jasper Road. The construction work consists of survey monument preservation, milling existing asphalt concrete pavement to a depth of 2", installation of a stress absorbing membrane interlayer (SAMI) with 3/8" aggregate over the milled surface, placement of 2" asphaltic concrete overlay surfacing over the SAMI, traffic striping and markings, sewer manhole rehabilitation, and traffic control.

On November 6, 2024, the City Council of the City of Calexico approved bid documentation for Scaroni Road Pavement Rehabilitation State Project No. LPPSB1L-5168(034) and authorized the Public Works Department to send the project out to bid.

On May 7, 2025, the City Council of the City of Calexico approved the following:
a) Award Bid Proposal from Rove Engineering, Inc. in the Amount of $731,770.00 for Scaroni Road Pavement Rehabilitation State Project No. LPPSB1L-5168(034). b) Authorize Interim City Manager to Sign Construction Agreement between the City of Calexico and Rove Engineering, Inc. in the Amount of $731,770.00 for Scaroni Road Pavement Rehabilitation State Project No. LPPSB1L-5168(034). c) Authorize Interim City Manager to Approve Any Future Change Orders Not-to-Exceed $73,177.00 (10% of Rove Engineering, Inc. Base Bid) as Per City Ordinance No. 1218. d) Adopt Budget Amendment Resolution for Fund No. 412 - State Grant.

Discussion and Analysis:

On July 23, 2025, Rove Engineering, Inc. began working on Scaroni Road Pavement Rehabilitation Project. The original specifications included the rehabilitation of six (6) manholes but after performing an extensive visual inspection, City staff is recommending the removal and replacement of four (4) 48" diameter sewer manholes. By replacing the sewer manholes, the City will be able to improve sewer infrastructure and prevent any future sinkholes along a newly paved road. For this reason, City staff is recommending that the City Council of the City of Calexico authorize the City Manager to sign Change Order No. 1 for Scaroni Road Pavement Rehabilitation Project.

Fiscal Impact:

Capital Improvement Program Budgeted Item for FY 2025-2026 Revenue
Fund No. 412-90-967 (State Grant) $471,000.00
Fund No. 237-90-967 (SB1) $333,947.00
Fund No. 547-90-940 (Wastewater Enterprise) $88,776.00
Total $893,723.00
Expenditure(s)
Original Contract $731,770.00
10% Contingency $73,177.00
Change Order No. 1 $88,776.00
Total $893,723.00
Coordinated With:

City Manager's Office.

Finance Department.

Public Works Department.

Attachment(s):

Rove Engineering, Inc. Change Order No. 1.

ATTACHMENT NO. 1

CITY OF CALEXICO

PUBLIC WORKS DEPARTMENT
CHANGE ORDER NO. 1
Name of Project: Scaroni Road Pavement Rehabilitation
MARIE State Project No. LPPSB1L-5168(034)
CALEXICO Name of Contractor: Rove Engineering, Inc.

CALMORNIA
He Caltua fed Treas Trai Date: September 3, 2025
# Description Price Price Time
Increase Decrease Extension
7 Sewer Manhole Rehabilitation 37,904.00
CCO#1 Remove and Replace 48" DIA Manholes $ 126,680.00
Sub-Total $ 126,680.00 37,904.00
Total $ 88,776.00
Contract Amount $ 731,770.00
Total Contract Amount (Contract + Change Order No. 1) $ 820,546.00 Benjamin A. Martinez, City Manager
City of Calexico, 608 Heber Avenue, Calexico, California Carlos Beltran, Construction Manager
Dynamic Consulting Engineers, 2415 Imperial Business Park Drive, STE B, Imperial, California Frank Duffy, Project Manager
Rove Engineering, Inc., P.O. Box 2108, El Centro, California ROVE Engineering-PROPOSAL
VE Rove Engineering Date Prepared: 12/31/2024 0:00
R
P.O. Box 2108
ENGINEERING Last Revision Date:

El Centro, CA 92021
Project Name: City of Calexico Sacroni Road Developer: City of Calexico Pavement Rehabilitation Project
Municipality: Address:

Project Type: Date: 8/20/2025
Solls Prepared By Frank Duffy
Plans Title Estimator
Author E Mail [email protected]
Regarding:

Gentlemen, our firm proposes to complete the following items of work in connection with the project referenced above. All work will be performed per field evaluations and Engineer direction.

Rates
Description Qly Unit Unit Price Total Cost Comments
4 EA $ 31,670.00 $ 126,680.00
Remove and Replace 48" DIA Manholes
Credits $
1 Sewer Manhole Rehabilitation EA $ (9,476.00) $ (37,904.00) $
Total $ 88,776.00
Inclusions: Exclusions:

Price Include remove and replace existing manholes Engineering, Testing, Permits, Survey, Certifications, compaction reports Installation of manhole liner Fees of any kind (unless caused by contractor) Striping Markings Decorative stone/Media/weed filter at basins for Landscape Dewatering or Processing of Saturated Soils
Manufacturer start-up and commissioning services are excluded Over Excavation beyond the specified depth listed above Removal of Material that cannot be productively ripped with a Caterpillar D6 Utilities in conflict with Subgrade prep shall be done by others.

Excavation or repairs and Disposal of any Debris or restoration Submitted This Date: 8/2012025 Rove Engineering Inc
Frank Duffy
PROPOSAL VALID FOR 15 DAYS ROVE Estimator
760-604-4299
ENGINEERING License # 1046101
Expiration-10/31/2024
P.O. Box 2108
El Centro, CA 92244
[email protected]