AGENDA
ITEM
15 Docusign Envelope ID: CF0BB8CF-E216-4E91-95D8-8993678A5EEF AGENDA
CALEXICO California ITEM

WHERE CALIFORNIA AND MEXICO MEET
15 CITY COUNCIL

AGENDA STAFF REPORT
DATE: December 17, 2025
TO: Mayor and City Council
APPROVED BY: Benjamin Martinez, City Manager
Signed by:

REVIEWED BY: Karla Chaparro, Finance Director karla Chaparro 3AA2C9E2Е876434...

Jve
PREPARED BY: Jesus Villegas, Public Works Director/City Engineer SUBJECT: Authorize Public Works Director/City Engineer to Sign Change Order No. 2 with Rove Engineering, Inc. in the Amount of $191,308.50 for Scaroni Road Pavement Rehabilitation State Project No. LPPSB1L-5168(034). =======
Recommendation:

It is recommended that the City Council of the City of Calexico approve the following:

1. Authorize Public Works Director/City Engineer to Sign Change Order No. 2 with Rove Engineering, Inc. in the amount of $191,308.50 for Scaroni Road Pavement Rehabilitation State Project No. LPPSB1L-5168(034).

Background:

The City of Calexico Public Works Department received a grant from California Department of Transportation (Caltrans) for FY 2023-2024 in the amount of $942.000.00 ($471,000.00 - State Grant and $471,000.00 - Local Match) for the Project No. LPPSB1L-5168(034) - Scaroni Road between Cole Boulevard and Jasper Road. The construction work consists of survey monument preservation, milling existing asphalt concrete pavement to a depth of 2', installation of a stress absorbing membrane interlayer (SAMI) with 3/8" aggregate over the milled surface, placement of 2" asphaltic concrete overlay surfacing over the SAMI, traffic striping and markings, sewer manhole rehabilitation, and traffic control.

On November 6, 2024, the City Council of the City of Calexico approved bid documentation for Scaroni Road Pavement Rehabilitation State Project No. LPPSB1L-5168(034) and authorized the Public Works Department to send the project out to bid.

Docusign Envelope ID: CF0BB8CF-E216-4E91-95D8-8993678A5EEF On May 7, 2025, the City Council of the City of Calexico approved the following:
a) Award Bid Proposal from Rove Engineering, Inc. in the Amount of $731,770.00 for Scaroni Road Pavement Rehabilitation State Project No. LPPSB1L-5168(034). b) Authorize Interim City Manager to Sign Construction Agreement between the City of Calexico and Rove Engineering, Inc. in the Amount of $731,770.00 for Scaroni Road Pavement Rehabilitation State Project No. LPPSB1L-5168(034). c) Authorize Interim City Manager to Approve Any Future Change Orders Not-to-Exceed $73,177.00 (10% of Rove Engineering, Inc. Base Bid) as Per City Ordinance No. 1218. d) Adopt Budget Amendment Resolution for Fund No. 412 - State Grant.

On September 3, 2025, the City Council authorized the City Manager to sign Change Order No. 1 with Rove Engineering, Inc. in the amount of $88,776.00 for the removal and replacement of four (4) 48" diameter sewer manholes on Scaroni Road.

Discussion and Analysis:

On July 23, 2025, Rove Engineering, Inc. began working on Scaroni Road Pavement Rehabilitation Project. The original specifications included road rehabilitation comprised of a 2- in mill of the existing A.C. paving, installation of a Stress Absorbing Membrane Interlayer (SAMI) and the installation of 2-in Hot Mix Asphalt. This proposed solution to extend the useful life of an asphalt pavement, although cost effective, requires that the structural integrity of the pavement is in adequate conditions, such as: a well compacted subgrade, a base layer that has a thickness appropriate to the vehicle loads that will be traveling on the road and compacted to a 95% relative density, and an Asphalt Concrete layer without major structural deficiencies.

At the beginning of the project, Rove Engineering conducted a pavement coring plan, to gather information on the existing paving structure along Scaroni Road, and to confirm that the proposed rehabilitation solution would be appropriate for the existing conditions of the road. The results of the coring indicated that sections of the road DO NOT HAVE BASE MATERIAL UNDERNEATH, creating weakness in the overall capacity of the pavement to bear the loads it is intended to withstand. Consequentially, the existing potholes are of such depth, that additional void areas will keep forming in the structure, compromising the integrity of the road and the safety of its users.

After discussions between the City of Calexico (Owner), Rove Engineering (Contractor), Dynamic Consulting Engineers (Resident Engineer) and Kimley Horn (Engineer of Record), Rove Engineering recommended the removal of 8-in of the existing asphalt, pulverization and treatment for its use as base, followed by the installation of a 4-in layer of ¾-in HMA Pavement Mix. This change in scope will undoubtedly yield a product without any underlying deficiencies, to the benefit of the City of Calexico.

For this reason, City staff is recommending that the City Council of the City of Calexico authorizes the Public Works Director/City Engineer to sign Change Order No. 2 for Scaroni Road Pavement Rehabilitation Project.

Page 2 of 3 ends

Docusign Envelope ID: CFOBB8CF-E216-4E91-95D8-8993678A5EEF Fiscal Impact:

Capital Improvement Program Budgeted Item for FY 2025-2026 Revenue
Fund No. 412-90-967 (State Grant) $471,000.00
Fund No. 237-90-967 (SB1) $452,078.50
Fund No. 547-90-940 (Wastewater Enterprise) $88,776.00
$1,011,854.50
Expenditure(s)
Original Contract Amount $/31,770.00
Change Order No. 1 $88,776.00
Change Order No. 2 $191,308.50
New Contract Amount $1,011,854.50
Coordinated With:

City Manager's Office.

Finance Department.

Public Works Department.

Attachments):

Exhibit 1. Photo Report - Road Condition
Exhibit 2. Site Plan - Scaroni Rd between Cole Rd & Jasper Rd (Aerial View) Exhibit 3. Change Order No. 2
Exhibit 4. Cost Proposal - Rove Engineering, Inc.

Page 3 of 3 ends

Docusign Envelope ID: CFOBB8CF-E216-4E91-95D8-8993678A5EEF Exhibit 1
Docusign Envelope ID: CF0BB8CF-E216-4E91-95D8-8993678A5EEF Exhibit 1
Photo Report - Change Order #2
Scaroni Road Pavement Rehabilitation
State Project No. LPPSB1L-5168(034)
Public Works Department

ROAD CLOSED
•TO

THRU TRAFFIC
VIC

Page 1 of 3 ends

Docusign Envelope ID: CFOBB8CF-E216-4E91-95D8-8993678A5EEF Exhibit 1
Photo Report - Change Order #2
Scaroni Road Pavement Rehabilitation
IB BAE
CALEXICO State Project No. LPPSB1L-5168(034)
Public Works Department

Page 2 of 3 ends

Docusign Envelope ID: CF0BB8CF-E216-4E91-95D8-8993678A5EEF Exhibit 1
Photo Report - Change Order #2
Scaroni Road Pavement Rehabilitation
State Project No. LPPSB1L-5168(034)
Public Works Department
ROAD
CLOSED
Pre

Page 3 of 3 ends

Docusign Envelope ID: CFOBB8CF-E216-4E91-95D8-8993678A5EEF Exhibit 2
Docusign Envelope ID: CF0BB8CF-E216-4E91-95D8-8993678A5EEF Scaroni Road between Cole Blvd and Jasper Road
Exhibit 2

JASPER ROAD
Site Plan

SCARONI ROAD

COLE ROAD
1" = 689 ft 12/09/2025
This map may represent a visual display of related geographic information. Data provided here is not a guarantee of actual field conditions. To ensure complete accuracy, please contact the responsible staff for the most up-to-date information.

Docusign Envelope ID: CF0BB8CF-E216-4E91-95D8-8993678A5EEF Exhibit 3
Docusign Envelope ID: CFOBB8CF-E216-4E91-95D8-8993678A5EEF Exhibit #3

CITY OF CALEXICO

PUBLIC WORKS DEPARTMENT
CHANGE ORDER NO. 2
Name of Project: Scaroni Road Pavement Rehabilitation
State Project No. LPPSB11-5168(034)
CALEXICO Name of Contractor: Rove Engineering, Inc.

CALIEDRALA Date: December 17, 2025
# Description Price Price Time
Increase Decrease Extension
CCO2.1 |Pulverize Road $ 57,928.50
CC02.2 Grade and Compact Existing $ 41,377.50
CC02.3 Pave 4" Section of 3/4" HMA $ 613,200.00
5 Hot Mix Asphalt 375,037.50
6 SAMI 146,160.00
Sub-Total $ 712,506.00521,197.50
Total 191,308.50
Contract Amount $ 820,546.00
Total Contract Amount (Contract + Change Order No.
1 and 2) $ 1,011,854.50
Jesus Villegas Peimbert, Public Works Director/City Engineer City of Calexico, 608 Heber Avenue, Calexico, California Carlos Beltran, Construction Manager
Dynamic Consulting Engineers, 2415 Imperial Business Park Drive, STE B, Imperial, California Frank Duffy, Chief Operating Officer (Public Works)
Rove Engineering, Inc., P.O. Box 2108, El Centro, California

Page 1 of 1 ends

Docusign Envelope ID: CF0BB8CF-E216-4E91-95D8-8993678A5EEF Exhibit 4
ROVE Engineering-PROPOSAL
OVE Rove Engineering Date Prepared: 12/31/2024 0:00
P.O. Box 2108 Last Revision Date:

ENGINEERING
El Centro, CA 92021
Project Name: City of Calexico Sacroni Road Developer: City of Calexico Pavement Rehabilitation Project
Municipality: Address:

Project Type: Date: 12/5/2025
Soils Prepared By Frank Duffy
Plans Title Estimator
Author E Mail [email protected]
Regarding:

Gentlemen, our firm proposes to complete the following items of work in connection with the project referenced above. All work will be performed per field evaluations and Engineer direction.

Rates
Description Qly Unit Unit Price Total Cost Comments
1 165510 SF $ 0,35 $ 57,928.50 Pulverize 8"
Pulverize road
165510 SF 0.25 $ 41,377.50 Grade and compact balance
2 $ grade no export
Grade and compact existing
Pave 4" section of 3/4" HMA 4380 TN $ 140.00 $ 613,200.00 $
$
CREDITS $
Hot Mix Asphalt 2055 TN $ (182,50) $ (375,037.50)/
SAMI 18270 SY $ (8.00) $ (146,160.00)/
Total 191,308.50
Inclusions: Exclusions:

Price Includes Pulverizing existing roadway to 8" depth Engineering, Testing, Permits, Survey, Certifications, compaction reports Grading and compacting to balance road with no export of additional material Fees of any kind (unless caused by contractor) Striping Markings Installation of new 4" section of 314" HMA Decorative stone/Media/weed filter at basins for Landscape Dewatering or Processing of Saturated Soils
Manufacturer start-up and commissioning services are excluded Over Excavation beyond the specified depth listed above Removal of Material that cannot be productively ripped with a Caterpillar D6 Utilities in conflict with Subgrade prep shall be done by others.

Excavation or repairs and Disposal of any Debris or restoration Submitted This Date: 12/8/2025 Rove Engineering Inc
Frank Duffy
PROPOSAL VALID FOR 15 DAYS ROVE COO
760-604-4299
ENGINEERING License # 1046101
Expiration-10/31/2024
P.O. Box 2108
El Centro, CA 92244
[email protected]