COR No. 150
AC Transitions on CLR at Business DW, Gutters and Ramps Between 5th and 3rd LS 1 $ 4,751.00 50% $ 2,375.50 50% $ 2,375.50
COR No. 151 Epoxy Down Delineators at Business Driveway 29+23 LS 1 $ 935.00 0% $ - 100% $ 935.00 COR No. 152 SWPPP Costs Due to Delay LS 1 $ 28,043.25 38% $ 10,656.44 62% $ 17,386.82 COR No. 153 Mandrel Conduits LS 1 $ 12,143.00 50% $ 6,071.50 50% $ 6,071.50 SubTotal: $ - $ - $ - $ 1,182,324.30 $ 379,393.10 $ 802,931.20 Construction Grand Subtotal: 8,185,688.88 $ $ 2,695,642.67 $ 5,490,046.21 $ 8,070,000.00 $ 2,499,439.05 $ 5,570,560.94